Final | 3/27/2017 | 3/28/2017 | 3/28/2017 | A | PASS |
Tom Saunders
|
|
|
Javier Phone #: ###-####...
ok to final
|
ELE-Aging Inspection | 2/16/2017 | 2/16/2017 | 2/16/2017 | | DONE |
Tom Saunders
|
|
|
talked with homeowner...unaware needed to schedule final...will schedule
|
ELE-Aging Inspection | 7/13/2016 | 7/13/2016 | 7/13/2016 | | CANC |
Eric Story
|
|
|
too busy
|
ELE-Aging Inspection | 4/4/2016 | 4/4/2016 | 4/6/2016 | | PASS |
Rock A. Hudson
|
|
|
Still under construction
|
ELE-Aging Inspection | 1/4/2016 | 1/4/2016 | 1/4/2016 | | DONE |
Rock A. Hudson
|
|
|
Still under construction
|
ELE-Aging Inspection | 8/13/2015 | 8/13/2015 | 8/13/2015 | | CANC |
Rock A. Hudson
|
|
|
Too busy
|
Electrical Rough-In | 7/3/2014 | 7/3/2014 | 7/3/2014 | P | PASS |
Bob Reichert
|
|
|
Javier Phone #: ###-#### ri ok, check breaker tie down at final, check for lb access at final right over panel
|
Electrical Rough-In | 7/1/2014 | 7/2/2014 | 7/2/2014 | A | FAIL |
Daryl DeGrange
|
|
|
Javier Phone #: ###-#### sub panel requires main breaker with tie down, still have nail plate and 1 1/4 issues
|
Electrical Rough-In | 6/30/2014 | 7/1/2014 | 7/1/2014 | A | FAIL |
Rock A. Hudson
|
|
|
Javier Phone #: ###-#### 300.4- NM calbe shall be maintain 1 1/4" from framing surface. 300.4- Where NM cable is ran through bored holes less than 1 1/4" from framing surface they shall be protected from physical damage by nail plate. Receptical outlets shall be located above 18" due to possible fuel storage.
|
Electrical Rough-In | 7/10/2013 | 7/11/2013 | 7/11/2013 | A | PASS |
Daryl DeGrange
|
|
|
Javier Phone #: ###-#### rough-in ok cover trench to water feature
|
Electrical Rough-In | 7/2/2013 | 7/3/2013 | 7/3/2013 | A | PASS |
Daryl DeGrange
|
|
|
Javier Phone #: ###-#### rough-in ok cover trench from house to shop
|
Conference | 6/21/2013 | 6/21/2013 | 6/21/2013 | P | DONE |
Daryl DeGrange
|
|
|
javier Phone #: ###-#### Discussed requirements for installing power underground to unattach structure.
|