Final | 11/8/2013 | 11/8/2013 | 11/8/2013 | P | PASS |
Bob Reichert
|
|
|
Bob Phone #: ###-#### ok final, no card
|
Permanent Service | 11/5/2013 | 11/5/2013 | 11/5/2013 | P | PASS |
Daryl DeGrange
|
|
|
Bob Phone #: ###-#### p/s u/g n ok
|
Electrical Rough-In | 11/1/2013 | 11/1/2013 | 11/1/2013 | P | PASS |
Daryl DeGrange
|
|
|
ceiling cover // Bob Phone #: ###-#### rough-in ok cover ceiling grid
|
Electrical Rough-In | 10/30/2013 | 10/30/2013 | 10/30/2013 | P | PASS |
Daryl DeGrange
|
|
|
partial r/i -- Dan Phone #: ###-#### rough-in ok cover soffits with LED recessed luminaires
|
Rough-In Permanent Service | 10/25/2013 | 10/25/2013 | 10/25/2013 | P | PASS |
Daryl DeGrange
|
|
|
Bob Phone #: ###-#### p/s u/g n ok
|
Electrical Rough-In | 10/16/2013 | 10/16/2013 | 10/16/2013 | A | PASS |
Daryl DeGrange
|
|
|
Phone #: ###-#### >> Inspection requested via web by Dan Hardisty rough-in ok cover interior demizing walls
|
Electrical Rough-In | 8/13/2013 | 8/13/2013 | 8/13/2013 | P | PASS |
Daryl DeGrange
|
|
|
bob Phone #: ###-#### rough-in ok cover underground low voltage conduits
|
Electrical Rough-In | 8/9/2013 | 8/9/2013 | 8/9/2013 | P | PART |
Doug A Poedy
|
|
|
Please look at ufer on East side of building and 4 inch PVC running to the outside of the foundation. PVC heading north will be encased in concrete. Phone #: ###-#### >> Inspection requested via web by Dan Hardisty. 4 inch conduit ok. Footing on plastic, so 2 ground rods and tie to rebar ok with #4 copper. Ok to pour footing. Still needs ground rods for service inspection.
|
Electrical Rough-In | 7/2/2013 | 7/2/2013 | 7/2/2013 | A | PASS |
Daryl DeGrange
|
|
|
Requesting a partial underground rough in inspection. Phone contact number is for Bob Thomas. Phone #: ###-#### >> Inspection requested via web by Dan Hardisty rough-in ok cover
|
Electrical Rough-In | 7/1/2013 | 7/1/2013 | 7/1/2013 | P | FAIL |
Daryl DeGrange
|
|
|
Requesting an underground partial roughin inspection. Contact number is for Bob Thomas. Phone #: ###-#### >> Inspection requested via web by Dan Hardisty underground covered before inspection, expose conduits, call for reinspection
|
Electrical Rough-In | 6/27/2013 | 6/27/2013 | 6/27/2013 | P | PASS |
Daryl DeGrange
|
|
|
rough-in ok cover underground service feeder conduits
|
Final | 6/27/2013 | 6/27/2013 | 6/27/2013 | A | CANC |
Daryl DeGrange
|
|
|
There is a construction entrance on Bridger St.At the NE section of the job there is a deep hole with 3-4" conduits. We will shade these with 3/4" Gravel before covering. Phone #: ###-#### >> Inspection requested via web by Dan Hardisty Needs to be scheduled as rough-in inspection, final inspection will terminate permit.
|