Final | 7/11/2014 | 7/14/2014 | 7/14/2014 | A | PASS |
Daryl DeGrange
|
|
|
We are requesting a final inspection on this project for Monday in the early am. Our onsite contact is Rich @ ###-####. Thank you Phone #: ###-#### >> Inspection requested via web by Clint Tate final ok
|
Electrical Rough-In | 1/14/2014 | 1/15/2014 | 1/15/2014 | A | PASS |
Daryl DeGrange
|
|
|
Bob would like a rough-in inspection on pump room of Bldg 8 at HP. He can be reached at ###-####. Thank you. Phone #: ###-#### >> Inspection requested via web by Clint Tate rough-in ok cover new exterior wall
|
Electrical Rough-In | 11/18/2013 | 11/19/2013 | 11/19/2013 | A | PASS |
Daryl DeGrange
|
|
|
Underground cover inspection. Please contact Guy Thomas with any questions ###-#### Phone #: ###-#### >> Inspection requested via web by Clint Tate rough-in ok cover conduits under slab
|