Final | 6/18/2014 | 6/18/2014 | 6/18/2014 | A | PASS |
Daryl DeGrange
|
|
|
Phone #: ###-#### >> Inspection requested via web by Thomas Jenkins final ok
|
Final | 5/23/2014 | 5/27/2014 | 5/27/2014 | A | PART |
Daryl DeGrange
|
|
|
Phone #: ###-#### >> Inspection requested via web by Thomas Jenkins Partial final ok Branch circuits for exterior signs shall be terminated in junction box
|
Electrical Rough-In | 5/12/2014 | 5/13/2014 | 5/13/2014 | A | PASS |
Daryl DeGrange
|
|
|
Ceiling inspection Phone #: ###-#### >> Inspection requested via web by Thomas Jenkins rough-in ok cover ceiling grid
|
Electrical Rough-In | 4/18/2014 | 4/21/2014 | 4/21/2014 | A | PASS |
Bob Reichert
|
|
|
Phone #: ###-#### >> Inspection requested via web by Thomas Jenkins walls only ok cover
|
Electrical Rough-In | 4/2/2014 | 4/3/2014 | 4/3/2014 | P | PASS |
Bob Reichert
|
|
|
Inspection for rest of floor boxes Phone #: ###-#### >> Inspection requested via web by Thomas Jenkins ok cover center section u/g only
|
Electrical Rough-In | 3/31/2014 | 4/1/2014 | 3/31/2014 | A | PASS |
Daryl DeGrange
|
|
|
Inspection of floor boxes in slab. General would like to pour part of slab Tuesday at 10am so if you could make this one of your first stops. Thank you Phone #: ###-#### >> Inspection requested via web by Thomas Jenkins Rough-in ok cover North third and South third pours
|