Final | 8/25/2015 | 8/26/2015 | 8/26/2015 | A | PASS |
Rex Boyles
|
|
|
Final out clubhouse. Phone #: ###-#### Inspection requested via web by Rafael Castillo final 100% including corridors perm. occupancy ok
|
Final | 8/24/2015 | 8/24/2015 | 8/24/2015 | P | PART |
Eric Story
|
|
|
Spa panel GFI breakers. Phone #: ###-#### Inspection requested via web by Rafael Castillo verified gfci on pumps and spa equipment
|
Final | 8/14/2015 | 8/15/2015 | 8/15/2015 | P | CANC |
Rex Boyles
|
|
|
Rafial - ###-#### not needed
|
Final | 8/14/2015 | 8/15/2015 | 8/15/2015 | A | PART |
Rex Boyles
|
|
|
Rafial - ###-#### Temporary Occupancy ok for 1st floor Still need GFCI's for spa pumps
|
Final | 8/14/2015 | 8/14/2015 | 8/14/2015 | P | PART |
Rex Boyles
|
|
|
Clubhouse inspection, spa and tanning booth. Phone #: ###-#### Inspection requested via web by Rafael Castillo final ok 1st floor except GFCI for spa pumps NEC 680.22(B), and additional "in line" water pressure pump not installed yet.
|
Electrical Rough-In | 8/13/2015 | 8/13/2015 | 8/13/2015 | A | PASS |
Rex Boyles
|
|
|
Clubhouse inspection. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok middle elevator lobby ceiling. Walk thru clubhouse for pre inspection
|
Electrical Rough-In | 8/10/2015 | 8/10/2015 | 8/10/2015 | A | PASS |
Rex Boyles
|
|
|
Parking garage grid ceiling. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok all of garge t grid ceiling ok to cover
|
Electrical Rough-In | 8/6/2015 | 8/6/2015 | 8/6/2015 | P | PASS |
Rex Boyles
|
|
|
Parking garage grid ceiling inspection west. Phone #: ###-#### Inspection requested via web by Rafael Castillo partial r/i west side t bar ceiling see e sheets
|
Electrical Rough-In | 8/5/2015 | 8/5/2015 | 8/5/2015 | A | PASS |
Rex Boyles
|
|
|
Garage ceiling grid inspection west wing. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok t bar ceiling west see e sheets
|
Electrical Rough-In | 7/31/2015 | 7/31/2015 | 7/31/2015 | P | PASS |
Rex Boyles
|
|
|
Ground in generator slab. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok
|
Electrical Rough-In | 7/29/2015 | 7/29/2015 | 7/29/2015 | P | PASS |
Rex Boyles
|
|
|
Grid ceiling inspection in clubhouse. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i clubhouse and adjoining rms t bar ceilings ok to cover
|
Permanent Service | 6/30/2015 | 6/30/2015 | 6/30/2015 | A | PASS |
Rex Boyles
|
|
|
Permanent service inspection for MMC#1. Phone #: ###-#### Inspection requested via web by Rafael Castillo p/s u/g n ok northeast service meter pack
|
Electrical Rough-In | 6/10/2015 | 6/10/2015 | 6/10/2015 | A | PASS |
Rex Boyles
|
|
|
Parking garage ceiling. Phone #: ###-#### Inspection requested via web by Rafael Castillo parking garage ceiling insulation above t grid ok Note: concerned about unit heaters in ceiling cavity blowing directly on rows of feeders. asked Rafael to see about getting them relocated.
|
Electrical Rough-In | 6/5/2015 | 6/5/2015 | 6/5/2015 | A | PASS |
Rex Boyles
|
|
|
Shaft, drop ceilings 3rd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo drop ceilngs ok rms. 303,304,337,336and 337. also vent. shaft in rm. 342. also u.ground in parking garge east ok to cover.
|
Permanent Service | 5/15/2015 | 5/15/2015 | 5/15/2015 | P | PASS |
Rex Boyles
|
|
|
Rough-in shafts 3rd floor, units 3rd floor west, permanent service MMC#2. Phone #: ###-#### Inspection requested via web by Rafael Castillo service "MMC#2" p/s u/g n ok
|
Permanent Service | 5/13/2015 | 5/14/2015 | 5/14/2015 | A | PASS |
Rex Boyles
|
|
|
Permanent service for HSB, drop ceilings 2nd floor east. Phone #: ###-#### Inspection requested via web by Rafael Castillo p/s u/g n ok west service "HSB" only
|
Electrical Rough-In | 5/14/2015 | 5/14/2015 | 5/14/2015 | P | PASS |
Rex Boyles
|
|
|
Permanent service for HSB, drop ceilings 2nd floor east. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceilings in rms. 210 and 216. Also r/i ok vent. shaft mc supports in rms. 221 thru224, 226 thru230 and 240 and 241
|
Electrical Rough-In | 4/29/2015 | 4/29/2015 | 4/29/2015 | A | PASS |
Rex Boyles
|
|
|
West end clubhouse walls, shafts 2nd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok clubhouse walls 100%, partial r/i shafts ok(see e sheets)
|
Electrical Rough-In | 4/28/2015 | 4/28/2015 | 4/28/2015 | P | PASS |
Rex Boyles
|
|
|
Clubhouse walls west end of building. Phone #: ###-#### Inspection requested via web by Rafael Castillo partial clubhouse r/i ok bathrooms and east wall at ramp see e sheets
|
Electrical Rough-In | 4/20/2015 | 4/20/2015 | 4/20/2015 | P | PASS |
Rex Boyles
|
|
|
Electrical shafts on 2nd floor. North exterior wall in clubhouse. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok club house partial walls and hardlids, see e sheets. r/i ok ventilation shafts 217,218 and 220
|
Electrical Rough-In | 4/1/2015 | 4/2/2015 | 4/2/2015 | A | PASS |
Rex Boyles
|
|
|
Rough-in exterior walls only 1st floor clubhouse. Verify okay for unit rough-in over roofed areas on 4th and 5th floors. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok clubhouse exterior south wall. NOTE: ok to continue electrical installation on 3rd, 4th and 5th floors at east wing only
|
Electrical Rough-In | 12/19/2014 | 12/19/2014 | 12/19/2014 | P | PASS |
Rex Boyles
|
|
|
Call Chris for inspection of spa ground. Merry Christmas. Phone #: ###-#### Inspection requested via web by Rafael Castillo spa bonding to steel and handrails ok to cover
|
Electrical Rough-In | 12/18/2014 | 12/19/2014 | 12/19/2014 | A | NR |
Rex Boyles
|
|
|
Grounding for spa. Phone #: ###-#### Inspection requested via web by Rafael Castillo not ready
|
Electrical Rough-In | 12/17/2014 | 12/17/2014 | 12/17/2014 | A | PASS |
Rex Boyles
|
|
|
Underground installation west end of clubhouse. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i slab west half of clubhouse ok
|
Electrical Rough-In | 11/26/2014 | 11/26/2014 | 11/26/2014 | A | PASS |
Rex Boyles
|
|
|
Underground rough-in south SOG area. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i south east clubhouse area slab ok
|
Electrical Rough-In | 11/19/2014 | 11/20/2014 | 11/20/2014 | P | PASS |
Rex Boyles
|
|
|
Ufer in electrical room 115, underground in south end SOG, conduit in masonry. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ufer ok so. west corner
|
Temporary Service | 10/6/2014 | 10/7/2014 | 10/7/2014 | P | CANC |
Rock A. Hudson
|
|
|
Direct burial cable installation for temporary power to job site. Phone #: ###-#### Inspection requested via web by Rafael Castillo Needed r/i inspection
|
Electrical Rough-In | 10/7/2014 | 10/7/2014 | 10/7/2014 | P | PASS |
Rock A. Hudson
|
|
|
Direct burial cable installation for temporary power to job site. Phone #: ###-#### Inspection requested via web by Rafael Castillo rough in ok cover
|
Conference | 9/26/2014 | 9/29/2014 | 9/29/2014 | A | DONE |
Rock A. Hudson
|
|
|
Temporary power for construction elevator. Phone #: ###-#### Inspection requested via web by Rafael Castillo Discussed using a transformer to step up voltage for temp power to elevator. 450.11(B)- Source Marking. A transformer shall be permitted to be supplied at the marked secondary voltage, provided that the installation is in accordance with the manufacturer’s instructions.
|
Electrical Rough-In | 9/23/2014 | 9/23/2014 | 9/23/2014 | P | PASS |
Rock A. Hudson
|
|
|
Underground rough in for cover. Phone #: ###-#### Inspection requested via web by Rafael Castillo Electrical room 115 all underground in area as noted on contractor print rough in ok cover
|
Electrical Rough-In | 9/12/2014 | 9/12/2014 | 9/12/2014 | A | PASS |
Rock A. Hudson
|
|
|
Underground feeders on the utility side. Phone #: ###-#### Inspection requested via web by Rafael Castillo Rough in ok cover
|
Conference | 9/3/2014 | 9/4/2014 | 9/4/2014 | A | DONE |
Rock A. Hudson
|
|
|
Discuss new layout of meter pack centers in light of new information. Phone #: ###-#### Inspection requested via web by Rafael Castillo Discussed work space and egress doors of electrical rooms. due to the size of rooms sll clearances seem to be satisfied. told can not permit any reduction in work space for any gear panel.
|
Electrical Rough-In | 8/22/2014 | 8/22/2014 | 8/22/2014 | P | PASS |
Rock A. Hudson
|
|
|
Underground northwest conduit. Phone #: ###-#### Inspection requested via web by Rafael Castillo Re inspected S.W. service conduit and west branch circuit conduit runs. Rough in ok cover
|
Electrical Rough-In | 8/21/2014 | 8/21/2014 | 8/21/2014 | A | PASS |
Rock A. Hudson
|
|
|
Underground rough-in of feeders entering south end of building and underground in NW corner of building. Phone #: ###-#### Inspection requested via web by Rafael Castillo Service conduit S.W. corner and branch circuit conduits N.W coner headed south rough in ok cover
|
Electrical Rough-In | 8/15/2014 | 8/15/2014 | 8/15/2014 | P | PASS |
Rock A. Hudson
|
|
|
Rough-in at shear wall on P line, ufer ground in mechanical room footing. Phone #: ###-#### Inspection requested via web by Rafael Castillo As noted on contractor print
|
Temporary Service | 8/7/2014 | 8/8/2014 | 8/8/2014 | A | PASS |
Rock A. Hudson
|
|
|
Temporary power pole next to McAlvain''s trailer. Phone #: ###-#### Inspection requested via web by Rafael Castillo Informed contractor of 6x6" minimum required by Idaho Power. 4x6" present short swing. t/s o/h n ok
|
Electrical Rough-In | 8/7/2014 | 8/8/2014 | 8/8/2014 | A | PASS |
Rock A. Hudson
|
|
|
Rough in of boxes and conduit in shear wall in southwest part of building. Phone #: ###-#### Inspection requested via web by Rafael Castillo Under ground and mason boxes marked on contracor print rough in ok cover
|
Temporary Service | 8/5/2014 | 8/7/2014 | 8/6/2014 | A | CANC |
Rock A. Hudson
|
|
|
Contact Electrical Foreman - Rafael Castillo Phone #: ###-#### Inspection requested via web by Cathy Duchek Contractor asked to canc. will reschedule
|
Electrical Rough-In | 8/6/2014 | 8/6/2014 | 8/6/2014 | P | PASS |
Rock A. Hudson
|
|
|
Underground rough-in. Phone #: ###-#### Inspection requested via web by Rafael Castillo Under ground south east electrical room as noted on contractor print. Rough in ok cover
|
Electrical Rough-In | 7/30/2014 | 7/30/2014 | 7/30/2014 | P | PASS |
Rock A. Hudson
|
|
|
Underground rough-in. Phone #: ###-#### >> Inspection requested via web by Rafael Castillo Far N. E. corner as noted on contractor print under ground rough in ok cover
|
Electrical Rough-In | 7/28/2014 | 7/28/2014 | 7/28/2014 | P | PASS |
Rex Boyles
|
|
|
Underground rough-in northeast corner of building. Phone #: ###-#### Inspection requested via web by Rafael Castillo partial u.ground slab n.east corner ok
|
Electrical Rough-In | 7/24/2014 | 7/24/2014 | 7/24/2014 | P | PASS |
Rock A. Hudson
|
|
|
Underground and conduit in foundation stem walls. Phone #: ###-#### >> Inspection requested via web by Rafael Castillo N. E. corner stubs as noted on contractor print rough in ok cover
|
Electrical Rough-In | 7/21/2014 | 7/21/2014 | 7/21/2014 | P | PASS |
Rock A. Hudson
|
|
|
Concrete encased electrode, 4 4" sleeves N.E. corner as noted on contractors print rough in ok cover
|
Final | 7/21/2014 | 7/21/2014 | 7/21/2014 | P | CANC |
Rock A. Hudson
|
|
|
Ufer inspection. Phone #: ###-#### >> Inspection requested via web by Rafael Castillo Needed rough in inspection
|