Final | 4/15/2015 | 4/16/2015 | 4/16/2015 | A | PASS |
Bob Reichert
|
|
|
We are requesting a final inspection for this project tomorrow 4/16/15. Our contact for this is Todd Hall @###-####. Thank you Phone #: ###-#### Inspection requested via web by Clint Tate ok final, signed card
|
Temporary Service | 3/2/2015 | 3/2/2015 | 3/2/2015 | P | CANC |
Bob Reichert
|
|
|
We are requesting a temp. occupancy inspection for this afternoon. Our onsite contact is Luke Hardy @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate see final
|
Final | 3/2/2015 | 3/2/2015 | 3/2/2015 | P | PART |
Bob Reichert
|
|
|
We are requesting a temp. occupancy inspection for this afternoon. Our onsite contact is Luke Hardy @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate partial final ok,shall finish panel schedules and elevator, signed t/o card
|
Electrical Rough-In | 2/17/2015 | 2/18/2015 | 2/18/2015 | P | PASS |
Cevyn Recla
|
|
|
We are requesting a ceiling cover inspection for tomorrow 2/18/15 in the pm. Our contact is Luke @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate Ceiling cover ok, 5 rooms
|
Electrical Rough-In | 1/9/2015 | 1/12/2015 | 1/12/2015 | A | PASS |
Rock A. Hudson
|
|
|
We are requesting an inspection for a pole base for Monday 1/12/15 during the AM. Our onsite contact is Luke @###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate pole base rough in ok cover
|
Electrical Rough-In | 12/23/2014 | 12/24/2014 | 12/24/2014 | P | DONE |
Bob Reichert
|
|
|
We are requesting a rough-in inspection for tomorrow afternoon. Our contact is Luke @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate still under construction
|
Temporary Service | 12/15/2014 | 12/15/2014 | 12/15/2014 | P | CANC |
Bob Reichert
|
|
|
We are requesting a service inspection for this afternoon. Our contact is Luke Hardy @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate see p/s
|
Permanent Service | 12/15/2014 | 12/15/2014 | 12/15/2014 | P | PASS |
Bob Reichert
|
|
|
We are requesting a service inspection for this afternoon. Our contact is Luke Hardy @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate p/s u/g n ok
|
Permanent Service | 12/4/2014 | 12/8/2014 | 12/8/2014 | P | NR |
Bob Reichert
|
|
|
We are requesting a permanent service inspection for Monday 12/8/14 in the aftermoon. Our onsite contact is Kory Peterson @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate met electrician, told needed to post available fault current per NEC 110.24(A), then recall, rest ok
|
Electrical Rough-In | 11/18/2014 | 11/20/2014 | 11/20/2014 | A | PART |
Bob Reichert
|
|
|
We are requesting a wall rough-in inspection for Thursday 11/20/14 in the AM. Our onsite contact is Kory @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate ok cover perimeter walls only-will do interior walls later
|
Electrical Rough-In | 11/5/2014 | 11/6/2014 | 11/6/2014 | A | PASS |
Bob Reichert
|
|
|
We are requesting a rough-in inspections for tomorrow 11/6/14 in the AM. Our site contact is ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate west firewall only ok cover
|
Electrical Rough-In | 10/31/2014 | 11/3/2014 | 11/3/2014 | A | PASS |
Bob Reichert
|
|
|
We are requesting an underground inspection for Monday morning Nov. 3rd. Our contact for this is Kory Peterson @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate ok cover u/g from transformer to building
|
Electrical Rough-In | 9/17/2014 | 9/18/2014 | 9/18/2014 | P | PASS |
Bob Reichert
|
|
|
We are requesting a rough-in inspection on the rest of the underground for tomorrow afternoon 9/18/14. Our onsite contact is Luke @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate ok pour slab, u/g ok
|
Electrical Rough-In | 9/16/2014 | 9/17/2014 | 9/17/2014 | A | PASS |
Bob Reichert
|
|
|
We are requesting an underground inspection for tomorrow 9/17/14 during the AM. Our onsite contact is Luke Hardy @ ###-####. Thank you Phone #: ###-#### Inspection requested via web by Clint Tate ok cover service related u/g only
|
Electrical Rough-In | 9/3/2014 | 9/3/2014 | 9/3/2014 | P | PASS |
Bob Reichert
|
|
|
We are requesting an underground inspection for this afternoon. Our onsite contact is Luke Hardy @ ###-####. Thank you! Phone #: ###-#### >> Inspection requested via web by Clint Tate ok pour concrete encased electrode
|
Electrical Rough-In | 9/2/2014 | 9/2/2014 | 9/2/2014 | P | NR |
Bob Reichert
|
|
|
We are requesting an underground inspection for this afternoon, our onsite contact is Luke Hardy @ 208.484.6499. Thank you Phone #: ###-#### >> Inspection requested via web by Clint Tate met contractor, general contractor not ready for electrical
|