Final | 5/11/2015 | 5/11/2015 | 5/11/2015 | P | PASS |
Rex Boyles
|
|
|
Phone #: ###-#### Inspection requested via web by kendall bender corrections made final ok
|
Final | 5/8/2015 | 5/8/2015 | 5/8/2015 | A | FAIL |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by kendall bender 358.26- Max number of bends between pull points with EMT shall not exceed 360 degrees. run to fire panel 410.46- Luminaires with exposed metal parts shall have means of connecting equipment grounding conductor. No lug ran thru hole in base
|
Permanent Service | 4/23/2015 | 4/23/2015 | 4/23/2015 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by kendall bender Correction made p/s u/g n ok House panel
|
Permanent Service | 4/21/2015 | 4/22/2015 | 4/22/2015 | A | FAIL |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by kendall bender Corrections not complete. 240.24(A)- Top breaker height shall not exceed 6'7". 250.119- Grounding electode and equipment ground conductors shall be identified bare or green. Tryed to call 2 times no answer or voice mail on either call
|
Permanent Service | 4/17/2015 | 4/17/2015 | 4/17/2015 | P | FAIL |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by kendall bender 110.24- AIC rating shall be calculated and posted with available fault current and date calculated prior to permanent service. 240.24(A)- Overcurrent devices shall be installed so the operating handle in it's highest point does not exceed 6'7".
|
Electrical Rough-In | 4/13/2015 | 4/14/2015 | 4/14/2015 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by kendall bender Perimeter and demizing walls only rough in ok cover
|
Conference | 4/13/2015 | 4/13/2015 | 4/13/2015 | P | DONE |
Rock A. Hudson
|
|
|
Making note of more than 1 permit exists on this building ele15-01002 for TI
|
Electrical Rough-In | 3/24/2015 | 3/25/2015 | 3/25/2015 | A | PASS |
Rock A. Hudson
|
|
|
under slab floor boxes Phone #: ###-#### Inspection requested via web by kendall bender 3 floor boxes and conduits south end of building rough in ok cover
|
Temporary Service | 12/11/2014 | 12/11/2014 | 12/11/2014 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by kendall bender t/s u/g n ok
|
Temporary Service | 12/9/2014 | 12/10/2014 | 12/10/2014 | A | FAIL |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by kendall bender 110.12(A)- Unused openings shall be closed. 250.4(A)(1)- Electrical equiptment shall be connected to earth with a method described in 250.53. 310.16- #10 THHN conductors not rated for 50 amp overcurrent protection. Install panel cover
|
Final | 11/7/2014 | 11/10/2014 | 11/10/2014 | A | CANC |
Rock A. Hudson
|
|
|
pole bases Phone #: ###-#### Inspection requested via web by kendall bender Needed rough in inspection
|
Electrical Rough-In | 11/10/2014 | 11/10/2014 | 11/10/2014 | P | PASS |
Rock A. Hudson
|
|
|
pole bases Phone #: ###-#### Inspection requested via web by kendall bender Pole base rough in ok pour
|
Electrical Rough-In | 11/6/2014 | 11/7/2014 | 11/7/2014 | A | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by kendall bender Underground for pole bases rough in ok cover
|
Electrical Rough-In | 10/9/2014 | 10/10/2014 | 10/10/2014 | A | PASS |
Daryl DeGrange
|
|
|
Uffer inspection Phone #: ###-#### Inspection requested via web by kendall bender Rough-in ok cover concrete enecased electrode
|