Final | 1/27/2015 | 1/27/2015 | 1/27/2015 | P | PASS |
Rex Boyles
|
|
|
Mitch Phone #: ###-#### final ok
|
Final | 1/26/2015 | 1/27/2015 | 1/27/2015 | A | NH |
Rex Boyles
|
|
|
Phone #: ###-#### Inspection requested via web by Mitch Whited no access
|
Permanent Service | 11/6/2014 | 11/10/2014 | 11/10/2014 | P | PASS |
Rock A. Hudson
|
|
|
Mitch// please call 30 min prior Phone #: ###-#### p/s o/h rec ok
|
Electrical Rough-In | 11/10/2014 | 11/10/2014 | 11/10/2014 | P | PASS |
Rock A. Hudson
|
|
|
Mitch// please call 30 min prior Phone #: ###-#### Warm wall load center contractor to install hardy board then drywall in bay panel resides. Rough in ok cover
|
Final | 11/2/2014 | 11/3/2014 | 11/3/2014 | A | CANC |
Rex Boyles
|
|
|
Phone #: ###-#### Inspection requested via web by Mitch Whited needed r/i
|
Electrical Rough-In | 11/3/2014 | 11/3/2014 | 11/3/2014 | P | PART |
Rex Boyles
|
|
|
Phone #: ###-#### Inspection requested via web by Mitch Whited r/i ok look for part 2 of rough in for loadcenter
|