Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberELE14-03084
StatusExpired
Name B & B ELECTRIC
Site Address 526 E ORION CT
Project Name 
Customer Number 
ePlanReviewNo
Description
Electrical Permit - New: New home
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Expired2/1/20192/1/20192/1/2019PPASS
DetailsDaryl DeGrange
No activity within 180 days. This permit is EXPIRED. A new permit is required to complete this job.
Conference6/18/20186/18/20186/18/2018PDONE
DetailsMark Moncarr
Mark-this is the GC-he has ?''s-please call when on way- Phone #: ###-#### Met and talked with GC on site. Job is still in progress.
Permanent Service8/25/20168/25/20168/25/2016PPASS
DetailsJames Ady
Adding new disconnect and panel for solar. Will be ready later this afternoon. Thank You! Phone #: ###-#### Inspection requested via web by Eric Brown p/s u/g rec ok
Electrical Rough-In8/9/20168/9/20168/9/2016PPASS
DetailsJames Ady
Pool bonding inspection. Phone #: ###-#### Inspection requested via web by Eric Brown Pool bond only rough in ok
Electrical Rough-In12/4/201512/4/201512/4/2015PPASS
DetailsEric Story
Please call Mike Marks (###-####) to schedule a time to inspect the main level and basement. Thank You Phone #: ###-#### Inspection requested via web by Eric Brown main level and basement except addition ok cover
Permanent Service10/28/201510/29/201510/29/2015APASS
DetailsEric Story
Phone #: ###-#### Inspection requested via web by Eric Brown p/s u/g n ok
Permanent Service10/26/201510/27/201510/27/2015AFAIL
DetailsEric Story
Service only Phone #: ###-#### Inspection requested via web by mike brown 250.50 grounding electrode required for main breaker and discconects
Electrical Rough-In9/23/20159/23/20159/23/2015PPASS
DetailsEric Story
Will be on site and ready for upstairs rough in right after lunch. Thank You Phone #: ###-#### Inspection requested via web by Eric Brown upstairs only ok cover
Electrical Rough-In4/20/20154/21/20154/21/2015APASS
DetailsDaryl DeGrange
Rough in inspection for remaining soffit. Thank You Phone #: ###-#### Inspection requested via web by Eric Brown Rough-in ok cover remainder soffet cans/ fire chalk completed
Electrical Rough-In3/25/20153/26/20153/26/2015AFAIL
DetailsDaryl DeGrange
Inspection for remaining soffit recessed cans. Thank you Phone #: ###-#### Inspection requested via web by Eric Brown Not all wiring penetrations to can lighting are fire chalk at this time,
Electrical Rough-In2/2/20152/2/20152/2/2015PPASS
DetailsCevyn Recla
Upper soffit reinspection. Thank you Phone #: ###-#### Inspection requested via web by Eric Brown
Soffit cans OK to cover, two hour fire boxes and caulked OK
Final1/30/20152/2/20152/2/2015AFAIL
DetailsCevyn Recla
Upper soffit inspection Phone #: ###-#### Inspection requested via web by Eric Brown
called Eric, soffit boxes around cans need fire caulk at penetrations.
Final12/5/201412/8/201412/5/2014PCANC
DetailsCevyn Recla
Right after lunch would be great and I will be there.

Thanks

Mike Phone #: ###-#### >> Inspection requested via web by Mike Cole Inspection cancelled from web by: Mike Cole