Final | 7/29/2015 | 7/30/2015 | 7/30/2015 | P | PASS |
Rex Boyles
|
|
|
Phone #: ###-#### Inspection requested via web by Celinda Winters final ok
|
Final | 7/17/2015 | 7/20/2015 | 7/20/2015 | A | PART |
Daryl DeGrange
|
|
|
Partial 2nd floor Phone #: ###-#### Inspection requested via web by Celinda Winters partial final for all of second floor but room 219
|
Final | 7/8/2015 | 7/9/2015 | 7/9/2015 | P | PART |
Rex Boyles
|
|
|
Partial final please Phone #: ###-#### Inspection requested via web by Celinda Winters not 100% trimmed out yet. OK to start moving equiptment in. Temp. occupany ok
|
Conference | 6/3/2015 | 6/4/2015 | 6/4/2015 | A | DONE |
Rex Boyles
|
|
|
Consultation please Phone #: ###-#### Inspection requested via web by Celinda Winters discuss terminations in generator ATS and r/i of small section of wall ok
|
Permanent Service | 5/11/2015 | 5/12/2015 | 5/12/2015 | A | PASS |
Rex Boyles
|
|
|
Phone #: ###-#### Inspection requested via web by Celinda Winters p/s u/g n ok
|
Electrical Rough-In | 5/8/2015 | 5/8/2015 | 5/8/2015 | P | PASS |
Rex Boyles
|
|
|
Ceiling rough-in bathrooms 2nd floor Phone #: ###-#### Inspection requested via web by Brandon Winters r/i ok
|
Conference | 5/4/2015 | 5/4/2015 | 5/4/2015 | P | DONE |
Rex Boyles
|
|
|
consultation on generator Phone #: ###-#### Inspection requested via web by Brandon Winters discuss grounded conductor separation at generator and transfer switch. bond nuetral at main disconnect only.
|
Electrical Rough-In | 4/16/2015 | 4/17/2015 | 4/17/2015 | P | PASS |
Rex Boyles
|
|
|
Interior Wall - 2nd floor Phone #: ###-#### Inspection requested via web by Celinda Winters r/i 2nd floor walls ok
|
Electrical Rough-In | 4/16/2015 | 4/17/2015 | 4/16/2015 | A | CANC |
Rex Boyles
|
|
|
Interior Wall - 2nd Floor Phone #: ###-#### >> Inspection requested via web by Celinda Winters Inspection cancelled from web by: Celinda Winters
|
Electrical Rough-In | 4/13/2015 | 4/14/2015 | 4/14/2015 | A | PASS |
Daryl DeGrange
|
|
|
remaining 1st floor walls Phone #: ###-#### Inspection requested via web by Brandon Winters rough-in ok cover 1st floor walls
|
Electrical Rough-In | 4/2/2015 | 4/3/2015 | 4/3/2015 | P | PASS |
Rex Boyles
|
|
|
exterior walls rough-in Phone #: ###-#### Inspection requested via web by Brandon Winters r/i exterior walls 1st and 2nd flr ok
|
Electrical Rough-In | 4/2/2015 | 4/3/2015 | 4/2/2015 | A | CANC |
Rex Boyles
|
|
|
exterior wall rough-in Phone #: ###-#### >> Inspection requested via web by Brandon Winters Inspection cancelled from web by: Brandon Winters
|
Conference | 2/20/2015 | 2/20/2015 | 2/20/2015 | P | DONE |
Rex Boyles
|
|
|
Consult on Panel Room Phone #: ###-#### Inspection requested via web by Celinda Winters Discuss toilet waste above transfer switch. need drain deversion pan to divert liquids
|
Electrical Rough-In | 1/19/2015 | 1/20/2015 | 1/20/2015 | P | PASS |
Cevyn Recla
|
|
|
underground cover by elevator pit area Phone #: ###-#### Inspection requested via web by Brandon Winters Underground at elevator pit, OK to cover
|
Electrical Rough-In | 1/7/2015 | 1/7/2015 | 1/7/2015 | P | PASS |
Rex Boyles
|
|
|
under slab Phone #: ###-#### Inspection requested via web by Brandon Winters underslab r/i ok to cover
|
Electrical Rough-In | 1/5/2015 | 1/5/2015 | 1/5/2015 | P | PASS |
Rex Boyles
|
|
|
Trench inspection please Phone #: ###-#### Inspection requested via web by Celinda Winters 100% u.ground ok to cover
|
Electrical Rough-In | 12/22/2014 | 12/23/2014 | 12/23/2014 | P | PASS |
Rex Boyles
|
|
|
Trench inspection please Phone #: ###-#### Inspection requested via web by Celinda Winters r/i u.ground secondaries up to trash enclosure ok to cover
|