Final | 5/15/2015 | 5/15/2015 | 5/15/2015 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Randy Fletcher Final ok
|
Final | 3/31/2015 | 4/7/2015 | 4/7/2015 | A | FAIL |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Randy Fletcher 210.8- GFCI receptacle outlets for jetted tub shall be installed in a readily accessible location. Verbal left message with contractor.
|
Final | 1/26/2015 | 1/27/2015 | 1/28/2015 | A | NR |
Rock A. Hudson
|
|
|
corrections made. Phone #: ###-#### Inspection requested via web by Randy Fletcher All terminations recessed in floor and cable secured in place.Check junction below stat remains accessible. Rough in ok cover
|
Electrical Rough-In | 1/27/2015 | 1/27/2015 | 1/27/2015 | P | PASS |
Rock A. Hudson
|
|
|
All terminations recessed in floor. Check junction below stat remains accessible. Floor heat rough in ok cover
|
Final | 1/23/2015 | 1/23/2015 | 1/23/2015 | P | NR |
Cevyn Recla
|
|
|
on circuits for bath remodel Phone #: ###-#### Inspection requested via web by Randy Fletcher floor cable needs repair
|
Electrical Rough-In | 1/20/2015 | 1/22/2015 | 1/22/2015 | A | PASS |
Rock A. Hudson
|
|
|
circuits for bath remodel Phone #: ###-#### Inspection requested via web by Randy Fletcher Floor heat and 2 circuits for jetted tub rough in ok cover
|