Final | 5/18/2015 | 5/18/2015 | 5/18/2015 | P | PASS |
Rock A. Hudson
|
|
|
Treon Phone #: ###-#### Final ok
|
Electrical Rough-In | 5/13/2015 | 5/13/2015 | 5/13/2015 | P | PASS |
Rock A. Hudson
|
|
|
Treon Phone #: ###-#### 4th floor OR corridor areas grid rough in ok cover
|
Electrical Rough-In | 3/25/2015 | 3/25/2015 | 3/25/2015 | P | PASS |
Rock A. Hudson
|
|
|
Treon Phone #: ###-#### Nurse station walls and soffit. 3 OR hard lids. In OR rooms ceiling support system is suspended, electrical and structural engineers to provide certification that ceiling system is rated to support 12 LED fixtures weighing approx 50 lbs each. Approving cover assuming documentation will be provided. Areas noted rough in ok cover
|
Electrical Rough-In | 2/18/2015 | 2/18/2015 | 2/18/2015 | P | PASS |
Rock A. Hudson
|
|
|
Treon Phone #: ###-#### 4th floor shower near OR rough in ok cover
|
Electrical Rough-In | 2/17/2015 | 2/17/2015 | 2/18/2015 | P | FAIL |
Daryl DeGrange
|
|
|
call about parking // treon Phone #: ###-#### Remove receptacle and relocate light switch from shower stall
|