Final | 10/28/2016 | 10/28/2016 | 10/28/2016 | A | PASS |
Rock A. Hudson
|
|
|
Fire caulked 7th floor electrical room wall. Installed arch flash stickers. We are opening up a new permit for open items. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Core and shell final ok
|
Final | 10/18/2016 | 10/19/2016 | 10/19/2016 | A | NR |
Rock A. Hudson
|
|
|
Reinspect items needed completion for final of Core and Shell. Contact is Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Mandatory for final- Repair firewall 7th floor ELE rm rt of door. Arc flash warnings on all electrical equipment. Other items cans be covered by new permit mostly cosmetic issues. 4th fl. ELE rm shall not be used for storage. 1st fl. cable tray bond need to terminate at tray. VRT ramp light trims needed 6. VRT fuse down 2 480 volt AC units. VRT, 2nd, 3rd floor parking garages complete heat trace installation. 1st floor GBAD future TI shall support blue MC. 1st floor GBAD shall include fire riser metal underground water pipe for grounding electrode system. 3rd fl. GBAD BSU future TI box required for MC in ceiling near door. RTU-1 service receptacle had open neutral. Walkway up lighting and inground drivers listing or field evaluate. Some existing step light covers needed and junctions need attention. Broken PVC connectors N. E. far corner.
|
Final | 10/11/2016 | 10/12/2016 | 10/12/2016 | P | FAIL |
Rock A. Hudson
|
|
|
Walk the 9 story Clearwater building for a final. Start on the roof working way down. Contact is Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves 10th fl.- Disconnect handle, label disc. for man cave, fire caulk wall penetration for low volt communication conduit, MH lense broke on roof area, completely cover light box for light in stairway. Arc flash in all elec equipment. 9th- Fire caulk above door in elec room. 8th- Open box above luminaire in elec rm. 7th- Fire caulk elec rm corridor wall. 5th- Elec rm fire caulk ceiling to 6th, south unfinished area blank covers for boxes near patio door. 4th- Elec rms shall not be used for storage, fire alarm box open in elec rm. 3rd- Strap flex to trans. 2nd- Blank boxes in server rooms, blank in elec rm, Equipment rm label disconnect. 1st- Fire caulk ceiling to 2nd and N. wall, VRT- ramp lights trim or cover, GBAD- 5th Wiring shall be 1 1/2" down from roof deck, 4th- Elec rm control box cover. Roof HVAC unit service receptacles not working on large units. 2nd- Parking panel labels, Fire caulk ceiling to 3, shall have clear work space. 1st- Communication flex shall not be supported off EMT in future TI.
|
Conference | 10/11/2016 | 10/11/2016 | 10/11/2016 | P | DONE |
Rock A. Hudson
|
|
|
Talk about items required to get a final on Core and Shell. Contact Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Will reschedule for tomorrow.
|
Electrical Rough-In | 9/26/2016 | 9/26/2016 | 9/26/2016 | P | PASS |
Rock A. Hudson
|
|
|
Ceiling cover for South East soffit can lights over entry ramps on Capitol Street. Contact is Mark Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Soffit and entrance to parking garage ramp as noted on print rough in ok cover
|
Electrical Rough-In | 9/20/2016 | 9/21/2016 | 9/21/2016 | A | PASS |
Rock A. Hudson
|
|
|
TCO, check heat trace, and door on 2nd floor electric room. Phone #: ###-#### Inspection requested via web by Toby Groves All heat trace terminated in boxes, 2nd floor electrical room door mounted with proper hardware. Signed TCO sheets
|
Electrical Rough-In | 9/20/2016 | 9/20/2016 | 9/20/2016 | A | PASS |
Rock A. Hudson
|
|
|
Walk 2nd floor 5 story for TCO. Contact is Toby Groves. ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Levels 1, 2, 3, core and shell temp occupy ok
|
Electrical Rough-In | 9/18/2016 | 9/19/2016 | 9/19/2016 | P | DONE |
Rock A. Hudson
|
|
|
Discuss TCO for remaining 5 story. Contact is Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Discussed remaining issues for TCO of 5 story. All wiring needs completed on basement and perimeter areas
|
Electrical Rough-In | 9/18/2016 | 9/19/2016 | 9/19/2016 | A | PASS |
Rock A. Hudson
|
|
|
TCO 4th floor, prefunction areas, stairs 3,4,5. Discuss TCO for remaining 5 story. Contact is Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves No issues in stairways, no access to 2nd floor parking garage, 3rd floor parking garage items are terminate heat tape, close open boxes, entrance to parking garage not complete not built yet, framing now. Listing for tinted window drivers part of window as listed package
|
Final | 9/18/2016 | 9/19/2016 | 9/18/2016 | A | CANC |
Rock A. Hudson
|
|
|
TCO 4th floor, prefunction areas, stairwells 3,4,and 5. Discuss TCO for remainder of the 5 story. Contact is Toby groves ###-#### Phone #: ###-#### >> Inspection requested via web by Toby Groves Inspection cancelled from web by: Toby Groves
|
Final | 9/16/2016 | 9/16/2016 | 9/16/2016 | P | FAIL |
Eric Story
|
|
|
Walk 5 story for TCO. Contact is Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves
exit signs need installed x 2
|
Conference | 9/14/2016 | 9/14/2016 | 9/14/2016 | P | DONE |
Rock A. Hudson
|
|
|
Conference more about TCO. Contact is Toby groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves
temporary lighting in stairway...also areas approved by building inspector...listing of driver for auto tint on windows
|
Electrical Rough-In | 9/12/2016 | 9/12/2016 | 9/12/2016 | P | PASS |
Rock A. Hudson
|
|
|
Ceiling for cover inspection Prefunction areas 2nd and 4th floor. Walk core and shell to look for possible TCO issues. Contact is Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves 4 floor bath hardlid rough in ok cover, Discussed fire caulking, finish all egress paths, euipment room and gear labels, panic hardware on all electrical room doors with gear rated 800 amp or more.
|
Electrical Rough-In | 9/11/2016 | 9/12/2016 | 9/12/2016 | P | CANC |
Rock A. Hudson
|
|
|
Pre TCO walk for District 5 story. Walk to identify items that may need taken care of for TCO later in the week. Contact is Toby Groves ###-#### Phone #: ###-#### >> Inspection requested via web by Toby Groves Inspection cancelled from web by: Toby Groves
|
Electrical Rough-In | 9/1/2016 | 9/2/2016 | 9/2/2016 | A | PASS |
Eric Story
|
|
|
Ceiling cover inspection. 4th floor GBAD pre function room. Contact is Mark Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves pre-function room ceilings where open j-boxes above grid ok cover(noted on inspection book)
|
Electrical Rough-In | 8/31/2016 | 9/1/2016 | 9/1/2016 | A | PASS |
Eric Story
|
|
|
Wall cover inspection. 4th floor elevator shaft wall in GBAD. Contact is Mark Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves 4th floor elevator wall ok cover
|
Electrical Rough-In | 8/24/2016 | 8/25/2016 | 8/25/2016 | A | PASS |
Rock A. Hudson
|
|
|
Inspect fire corridor walls and ceiling for cover first floor GBAD by stair 5. Contact is Mark Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves 2nd floor breezeway hardlid and 1st floor GBAD emergency corridor hardlid and walls rough in ok cover
|
Rough-In Permanent Service | 8/22/2016 | 8/22/2016 | 8/22/2016 | P | CANC |
Rock A. Hudson
|
|
|
5 Story 4th floor Ballroom Ceiling for cover inspection. Contact is Mark Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Needed rough in only.
|
Electrical Rough-In | 8/22/2016 | 8/22/2016 | 8/22/2016 | P | PASS |
Rock A. Hudson
|
|
|
5 Story 4th floor Ballroom Ceiling for cover inspection. Contact is Mark Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Ceiling inspection for this area for 2 3" conduits feeding roof top units. Rough in ok cover
|
Electrical Rough-In | 8/19/2016 | 8/19/2016 | 8/19/2016 | A | PASS |
Rock A. Hudson
|
|
|
Retail C space for TCO for BSU bike racks. Contact is Eric Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves Use of retail C for temp storage for bike racks. temp use ok
|
Electrical Rough-In | 8/17/2016 | 8/17/2016 | 8/17/2016 | P | PASS |
Rock A. Hudson
|
|
|
Wall rough in Stair 5 Floors 5,4,3 possibly 2. Contact is Eric Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves core and shell stairwell number 5 floors 2-5 roughin ok to cover
|
Electrical Rough-In | 8/15/2016 | 8/15/2016 | 8/15/2016 | P | PASS |
Rock A. Hudson
|
|
|
4th floor 3 bathroom hardlid rough in ok cover
|
Final | 8/15/2016 | 8/15/2016 | 8/15/2016 | P | CANC |
Rock A. Hudson
|
|
|
4th floor bathroom ceiling cover inspection in 5 story GBAD. Also signature in TCO binder sheets for core and shell in the 9 story that have not been signed. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Needed rough in inspection
|
Electrical Rough-In | 8/8/2016 | 8/8/2016 | 8/8/2016 | P | PASS |
Rock A. Hudson
|
|
|
Wall rough in for cover remaining walls in Stair 4 in GBAD Canopy light rough in on South and North side of GBAD first level exterior. Contact is Eric Gibson ###-####3. Phone #: ###-#### Inspection requested via web by Toby Groves D-6 elevator lobby and out soffit, East alley lid, stair 4 levels 1 and 2 wall rough in ok cover
|
Electrical Rough-In | 7/28/2016 | 7/29/2016 | 7/29/2016 | A | PASS |
Rock A. Hudson
|
|
|
Ceiling rough in 1st floor. Service corridors. Contact is Toby Groves ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves Rear elevator lobby grid and west service corridor grid rough in ok cover. West side of building sign whips shall terminate in a outdoor rated box
|
Electrical Rough-In | 7/28/2016 | 7/28/2016 | 7/28/2016 | P | PASS |
Rock A. Hudson
|
|
|
First floor ceiling inspection. Contact is Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves 1st floor main hall and emergency corridor grid rough in ok cover
|
Electrical Rough-In | 7/27/2016 | 7/27/2016 | 7/27/2016 | P | PART |
Rock A. Hudson
|
|
|
TCO walk. Wall rough in for cover stair 4. Ceiling inspection cover first floor lobby. Contact Toby Groves ###-####. As late in the afternoon as possible for your schedule. Phone #: ###-#### Inspection requested via web by Toby Groves Stair 4 floors 2 thru 5 wall rough in ok cover. 1st floor main lobby only and elevator lobby grid rough in ok cover
|
Conference | 7/26/2016 | 7/26/2016 | 7/26/2016 | P | DONE |
Rock A. Hudson
|
|
|
Walk building for TCO items later in the afternoon. Contact Toby Groves ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves Both stairways complete up to top floor. Elecrical openings in stairways are for low volt door controls and communications. Items needed to complete for occupancy are in basement terminate lightning grounding conductor to building steel. Bus duct fire stop needed on all floors. Should be installed Wednesday. 1st floor- emergency corridor grid has not been built as 4pm, no lighting. Fire pump room 1 1/2hr door assembly. Main lobby corridor, elevator lobby, and main lobby grid not complete, trim bathrooms, disconnect handle height, electrical room being used as storage, outdoor egress lighting needs completed. 7th floor- Disconnect handle height, all covers on HVAC unit in equipment rm.
|
Electrical Rough-In | 7/25/2016 | 7/25/2016 | 7/25/2016 | A | PASS |
Rock A. Hudson
|
|
|
9th floor elevator lobby ceiling inspection. Contact is Eric Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves Area noted rough ok cover
|
Electrical Rough-In | 7/22/2016 | 7/22/2016 | 7/22/2016 | P | PASS |
Rock A. Hudson
|
|
|
Ceiling inspection for cover. First floor lobby. 9th floor lobby. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves 1st floor lobby hardlit and bath foyer ceiling rough in ok cover
|
Electrical Rough-In | 7/18/2016 | 7/18/2016 | 7/18/2016 | P | PASS |
Rock A. Hudson
|
|
|
Can light ceiling inspection for cover high ceiling at column line A and B breeze way. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Breezeway lid complete rough in ok cover
|
Electrical Rough-In | 7/14/2016 | 7/14/2016 | 7/14/2016 | P | PASS |
Rock A. Hudson
|
|
|
Stair 3 rough in inspection. Contact is Eric Gibson. ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Stair 3 floors 1 thru 4 wall rough in ok cover
|
Electrical Rough-In | 7/13/2016 | 7/13/2016 | 7/13/2016 | P | PASS |
Rock A. Hudson
|
|
|
Ceiling cover inspection retail bathrooms first floor. Contact is Eric Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves Retail B bath hardlids Rough in ok cover
|
Electrical Rough-In | 7/8/2016 | 7/8/2016 | 7/8/2016 | P | PASS |
Rock A. Hudson
|
|
|
Ceiling inspections elevator lobbies. Contact is Eric Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves Called contact no answer signed book on 7th and 8th floor elevator lobby ceilings rough in ok cover
|
Electrical Rough-In | 7/7/2016 | 7/7/2016 | 7/7/2016 | A | PASS |
Rock A. Hudson
|
|
|
Ceiling inspection elevator lobbies. Reinspect fire Corridor first floor. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves 1st floor corridor, Elevator lobbies 1 thru 6 ceiling as noted in book rough in ok cover
|
Electrical Rough-In | 7/6/2016 | 7/6/2016 | 7/6/2016 | A | PASS |
Eric Story
|
|
|
Elevator lobby ceiling inspection. Ceiling inspection Gridline B in GBAD. Ceiling inspection fire Corredor first floor. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves elevator lobby hard lid cielings on floors 2,3,4 only ok cover
|
Electrical Rough-In | 6/30/2016 | 6/30/2016 | 6/30/2016 | A | PASS |
Eric Story
|
|
|
Cover inspections for 9 story East canopy 1st floor. 5 story bathroom walls. Contact is Eric Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves east 3 soffit cans and 4th floor bathrooms as noted on sign in book ok cover
|
Electrical Rough-In | 6/24/2016 | 6/24/2016 | 6/24/2016 | A | PASS |
Rock A. Hudson
|
|
|
Can light rough in 4 line exterior breeze way ceiling. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Breezeways as noted on contractor print rough in ok cover
|
Electrical Rough-In | 6/17/2016 | 6/17/2016 | 6/17/2016 | P | PASS |
Rock A. Hudson
|
|
|
Ceiling cover inspection. Can lights and LEDs in south breezeway at GBAD. Eric Gibson is contact. ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves Beezeway from capitol to grove center to 5 column only lid rough in ok cover
|
Electrical Rough-In | 6/16/2016 | 6/16/2016 | 6/16/2016 | A | PASS |
Rock A. Hudson
|
|
|
9th floor bathroom ceiling cover inspection. Eric Gibson is your contact. ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Bathroom hardlids rough in ok cover and noted on prints and books
|
Permanent Service | 6/7/2016 | 6/7/2016 | 6/7/2016 | P | PASS |
Rock A. Hudson
|
|
|
Service inspection VRT level. Contact Toby Groves ###-####. If you could give me a call 15min prior please it will give me time to meet you. Thanks. Phone #: ###-#### Inspection requested via web by Toby Groves p/s u/g n ok 4 meters required
|
Electrical Rough-In | 6/6/2016 | 6/6/2016 | 6/6/2016 | A | PASS |
Rock A. Hudson
|
|
|
Cover inspection for can lights in north soffit. Contact is Eric Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves North outside canopy soffit rough in ok cover
|
Electrical Rough-In | 6/2/2016 | 6/2/2016 | 6/2/2016 | P | PASS |
Rock A. Hudson
|
|
|
First floor wall cover inspection. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves 1st floor north corridor and bathrooms wall rough in ok cover noted in book in red.
|
Electrical Rough-In | 5/25/2016 | 5/25/2016 | 5/25/2016 | A | PASS |
Rock A. Hudson
|
|
|
2nd floor electric room of 5 story. Wall rough in for cover. Contact is Eric Gibson. ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Walls rough in ok cover and noted in book
|
Electrical Rough-In | 5/21/2016 | 5/23/2016 | 5/23/2016 | A | PASS |
Rock A. Hudson
|
|
|
Ceiling rough in inspection 2nd and 8th floor restrooms. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Hardlids noted and marked in book rough ino ok cover
|
Conference | 5/20/2016 | 5/20/2016 | 5/20/2016 | A | DONE |
Rock A. Hudson
|
|
|
Instillation method of low voltage lighting in sidewalks. Contact is Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Discussed the use of ENT for low voltage luminaires poured in sidewalk. Fittings shall be listed for use encased in concrete. Shall provide listing for luminaires. One provided not listed for US.
|
Electrical Rough-In | 5/16/2016 | 5/16/2016 | 5/16/2016 | P | PASS |
Rock A. Hudson
|
|
|
First floor South side wall rough in inspection. Contact is Eric Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves Check HVAC above hood in Buffalo Wild Wings. South 1st floor bathrooms, fire corridor and fire rooms wall rough in ok cover
|
Electrical Rough-In | 5/11/2016 | 5/11/2016 | 5/11/2016 | P | PASS |
Rex Boyles
|
|
|
Wall and ceiling cover inspection bathrooms on floors 6,7, and10. Contact Eric Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves r/i ok 6th, 7th floor bathroom ceilings, 9th floor bathroom walls and 9th floor elevator lobby walls
|
Conference | 5/2/2016 | 5/2/2016 | 5/2/2016 | P | DONE |
Rex Boyles
|
|
|
Walk thru and verify working clearances for HVAC units in ceilings with ESI and HVAC installers. Verify working space in electrical rooms. Contact Toby Groves ###-####. If possible 15min prior to arrival so all parties can be notified and ready to walk. Thank you. Phone #: ###-#### Inspection requested via web by Toby Groves walk thru floors 2 thru 6 to identify problem areas. Superintident with ESI "Ron" says he will relay info to TML and Lea electric for their problem areas also where there isn't at least 24" clearance MINIMUM for HVAC control boxes. Linesets, sprinkelers,duct work and electrical conduits in front of control boxes and not meeting clearances. Also performed r/i inspection on 2 and 3
|
Electrical Rough-In | 5/2/2016 | 5/2/2016 | 5/2/2016 | P | PASS |
Rex Boyles
|
|
|
Walk thru and verify working clearances for HVAC units in ceilings with ESI and HVAC installers. Verify working space in electrical rooms. Contact Toby Groves ###-####. If possible 15min prior to arrival so all parties can be notified and ready to walk. Thank you. Phone #: ###-#### Inspection requested via web by Toby Groves r/i ok 2nd floor n. west office walls and 3rd floor wall see ESI prints
|
Electrical Rough-In | 4/28/2016 | 4/28/2016 | 4/28/2016 | P | PASS |
Rex Boyles
|
|
|
Bathroom Ceiling inspection for cover floors 3,4,5. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves r/i ok bath hardlids also was asked again to look at problem areas for HVAC controllers. Mechanical contractor running linesets and blocking control boxes in multiple ares still even after previous conference
|
Electrical Rough-In | 4/13/2016 | 4/13/2016 | 4/13/2016 | P | PASS |
Rex Boyles
|
|
|
Wall rough in inspection. Stair 2,9th floor and Penthouse. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves stairwell 1 and 2 100% except penthouse stairwell. Also 9th floor electrical room and IT room and mechanical rm ok
|
Electrical Rough-In | 4/1/2016 | 4/1/2016 | 4/1/2016 | P | PASS |
Daryl DeGrange
|
|
|
Cover inspections for walls Phone #: ###-#### Inspection requested via web by Toby Groves Rough-in ok cover interior walls highlighted in green and dated
|
Electrical Rough-In | 3/7/2016 | 3/7/2016 | 3/7/2016 | P | PASS |
Rex Boyles
|
|
|
Wall cover inspection Phone #: ###-#### Inspection requested via web by Toby Groves r/i ok G line wall from col. 4 to col. 2, 2 Line wall from col. K to col. G
|
Electrical Rough-In | 3/2/2016 | 3/2/2016 | 3/2/2016 | P | PASS |
Rex Boyles
|
|
|
Rough in for cover and catch up on inspection binder. Phone #: ###-#### Inspection requested via web by Toby Groves r/i walls ok level 4 thru 8 IT rooms and everything marked in green in ESI binder 1/4 size prints
|
Electrical Rough-In | 2/25/2016 | 2/25/2016 | 2/25/2016 | P | PASS |
Rex Boyles
|
|
|
Cover inspection for the South Stairwell Clearwater building. Phone #: ###-#### Inspection requested via web by Toby Groves r/i ok south stairwell 1 thru 8 only
|
Conference | 2/12/2016 | 2/12/2016 | 2/12/2016 | P | CANC |
Rex Boyles
|
|
|
Cover inspection for North Stairwell. Phone #: ###-#### Inspection requested via web by Toby Groves needed r/i insp
|
Electrical Rough-In | 2/12/2016 | 2/12/2016 | 2/12/2016 | P | PASS |
Rex Boyles
|
|
|
Phone #: ###-#### Inspection requested via web by Cindie Swaim r/i north stairwells level 1 thru level 9 ok
|
Conference | 2/3/2016 | 2/3/2016 | 2/3/2016 | P | DONE |
Rex Boyles
|
|
|
Would like approval for the Draka Lifeline 2hr rated fire cable assybly being used for the firepump. Contact Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves after reviewing product info for fire pump conductors "Draka Lifeline 2 hour fire resistive cable" this product is acceptable for use on this project to feed fire pump. However we are still waiting for confirmation to install overcurrent protection with additional disconnect ahead of fire pump controller disconnect as previously discussed. Asked Toby to hold off on that installation until "fire planning dept. and the NFPA 20" will allow this application.
|
Electrical Rough-In | 1/12/2016 | 1/13/2016 | 1/13/2016 | A | PASS |
Rex Boyles
|
|
|
Rough-in for can lights on 3rd floor West Patio. Contact Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves r/i ok
|
Conference | 1/6/2016 | 1/7/2016 | 1/7/2016 | A | DONE |
Rex Boyles
|
|
|
Would like to go over fire pump feeds and options on site again. Would like to discuss 695.4(B)(3) interpretation. Contact is Toby Groves. ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves discuss disconnect locations for fire pump utility power and generator power. OK to install disconnects inside Telco Demarc room if painted red and satisfying all other items in 695. Also maintain access and 2 hr protection to pullboxes or condulets if installed.
|
Rough-In Permanent Service | 1/4/2016 | 1/4/2016 | 1/4/2016 | P | CANC |
Daryl DeGrange
|
|
|
Concrete encased electrodes for Main Service and Generator. Toby Groves is contact ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves not needed yet
|
Electrical Rough-In | 1/4/2016 | 1/4/2016 | 1/4/2016 | P | PASS |
Daryl DeGrange
|
|
|
Concrete encased electrodes for Main Service and Generator. Toby Groves is contact ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves r/i ok concrete encased electrode for generator and main service Discussed fire pump issues not compliant with NEC
|
Conference | 12/23/2015 | 12/23/2015 | 12/23/2015 | A | DONE |
Rex Boyles
|
|
|
Contact Toby Groves ###-#### Want to discuss bus way clearances. Phone #: ###-#### Inspection requested via web by Toby Groves discuss clearances on vertical bussway for rear of bussway. OK if blanked off or lockedout so no future disconnects can be installed. Toby checking with manufacturer.
|
Electrical Rough-In | 12/16/2015 | 12/16/2015 | 12/16/2015 | P | PASS |
Rex Boyles
|
|
|
Call me and I will meet you in the lobby of the US Bank Building. Thanks. Toby Groves Phone #: ###-#### Inspection requested via web by Toby Groves r/i ok level 2 area 3 can lights in soffit ok to cover Also preliminary walk thru on fire pump, main electrical roo m and disconnects mounted to vertical busway higher than nec requirements, ok as per 368.17(C) to eceed 6' 7". .third pary testing for main gear, arc fault labeling, etc. Possible issues with fire pump meter and generator disconnect locations not in 2 hr envelope??
|
Conference | 4/22/2015 | 4/22/2015 | 4/22/2015 | P | DONE |
Daryl DeGrange
|
|
|
Would like to discuss instillation of the tower crane. Toby Groves is the contact. ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Discussed overcurrent protection and bonding.
|
Conference | 3/24/2015 | 3/25/2015 | 3/24/2015 | A | CANC |
Rex Boyles
|
|
|
Toby Groves is the contact ###-####. Would like to conference about a 1200 amp temp service we are building. Phone #: ###-#### >> Inspection requested via web by Toby Groves Inspection cancelled from web by: Toby Groves
|
Electrical Rough-In | 3/3/2015 | 3/4/2015 | 3/4/2015 | A | PASS |
Rex Boyles
|
|
|
Cast in place lights and PVC in formed concrete walls. Phone #: ###-#### Inspection requested via web by Toby Groves ramp lights r/i ok 100%
|