Final | 4/30/2015 | 4/30/2015 | 4/30/2015 | P | PASS |
Daryl DeGrange
|
|
|
Final Solar Inspection. Will Schedule a time to meet on site. Phone #: ###-#### Inspection requested via web by Matthew Dunay wiring complete to inverter, final ok
|
Electrical Rough-In | 4/27/2015 | 4/28/2015 | 4/28/2015 | A | PASS |
Daryl DeGrange
|
|
|
Will be onsite. Second Solar Inspection Phone #: ###-#### Inspection requested via web by Matthew Dunay rough-in ok CSA listed modules, bonding
|
Electrical Rough-In | 3/31/2015 | 4/1/2015 | 4/1/2015 | P | PART |
Daryl DeGrange
|
|
|
Will meet you onsite to explain set up. Have Scheduled to coordinate with other electrical rough in on different permit at same address. Phone #: ###-#### Inspection requested via web by Matthew Dunay partial rough-in ok cover ceiling and walls
|