Final | 4/15/2016 | 4/18/2016 | 4/18/2016 | P | PASS |
Rex Boyles
|
|
|
CONTACT - DERRICK KAMPER Phone #: ###-#### Inspection requested via web by Deb Gooden final ok
|
Electrical Rough-In | 11/18/2015 | 11/19/2015 | 11/19/2015 | P | PASS |
Rex Boyles
|
|
|
Contact: Jeremiah Goins. final for the 4th floor please Phone #: ###-#### Inspection requested via web by Deb Gooden final ok 4th flr perm. occupancy ok 4th floor
|
Electrical Rough-In | 10/23/2015 | 10/26/2015 | 10/26/2015 | A | PASS |
Rex Boyles
|
|
|
Contact: Jeremiah Goins - final for the 2nd floor only please Phone #: ###-#### Inspection requested via web by Deb Gooden final ok 2nd flr perm. occupancy ok on 2nd and 3rd floors.
|
Electrical Rough-In | 10/22/2015 | 10/23/2015 | 10/23/2015 | P | PART |
Rex Boyles
|
|
|
CONTACT: JEREMIAH GOINS - FINAL INSPECTION FOR 2ND ; 3RD FLOORS Phone #: ###-#### Inspection requested via web by Deb Gooden 3rd floor final ok will look for bond to server rack next inspection will return to inspect 2nd floor early when office workers are not in the way
|
Electrical Rough-In | 10/21/2015 | 10/22/2015 | 10/22/2015 | A | PASS |
Rex Boyles
|
|
|
Contact: Jeremiah Goins - ceiling inspection please Phone #: ###-#### Inspection requested via web by Deb Gooden r/i t bar ceilings ok on 4th floor
|
Electrical Rough-In | 10/13/2015 | 10/14/2015 | 10/14/2015 | A | PASS |
Rex Boyles
|
|
|
Contact: Jeremiah Goins - 3rd floor Final inspection please Phone #: ###-#### Inspection requested via web by Deb Gooden partial final on 3rd floor. All done except cubicles not in yet. TEMP. OCCUPANCY OK on 3rd floor
|
Electrical Rough-In | 10/12/2015 | 10/13/2015 | 10/13/2015 | P | CANC |
Rex Boyles
|
|
|
Contact: Jeremiah Goins - Final inspection for the 3rd floor please Phone #: ###-#### >> Inspection requested via web by Deb Gooden Inspection cancelled from web by: Deb Gooden
|
Electrical Rough-In | 9/30/2015 | 10/1/2015 | 10/1/2015 | P | PASS |
Rock A. Hudson
|
|
|
Contact: Jeremiah Goins - ceiling inspection, late morning, close to noon if possible please Phone #: ###-#### Inspection requested via web by Deb Gooden 3rd floor ceiling grid rough in ok cover
|
Electrical Rough-In | 9/18/2015 | 9/21/2015 | 9/21/2015 | P | PASS |
Rex Boyles
|
|
|
Contact: Jeremiah Goins - 4th floor rough-in please Phone #: ###-#### Inspection requested via web by Deb Gooden r/i ceilings conf. rm, bathrms, and elevator lobby ok
|
Electrical Rough-In | 8/31/2015 | 9/1/2015 | 9/1/2015 | A | PASS |
Rex Boyles
|
|
|
CONTACT: JEREMIAH GOINS Phone #: ###-#### Inspection requested via web by Deb Gooden r/i walls 3rd floor ok
|
Electrical Rough-In | 6/29/2015 | 6/30/2015 | 6/30/2015 | A | PART |
Rex Boyles
|
|
|
Contact: Jeremiah Goins. Final for the 2nd floor Phone #: ###-#### Inspection requested via web by Deb Gooden 2nd flr final ok except cubicles not installed yet
|
Conference | 5/20/2015 | 5/21/2015 | 5/21/2015 | A | DONE |
Rex Boyles
|
|
|
Contact: Jeremiah Goins - 2nd floor conf. inspection please Phone #: ###-#### Inspection requested via web by Deb Gooden discuss clearance above 2nd flr panelboards. Limited space because of HVAC, OK with Jeramiah as far as being able to get his electrical in. Making an exception on this installation in regards to 110.26 (A)(3) height above panel
|
Electrical Rough-In | 5/14/2015 | 5/15/2015 | 5/15/2015 | A | PASS |
Daryl DeGrange
|
|
|
Contact: Jeremiah Goins, Late morning inspection please Phone #: ###-#### Inspection requested via web by Deb Gooden rough-in ok cover 2n floor walls
|
Conference | 4/8/2015 | 4/8/2015 | 4/8/2015 | P | DONE |
Rex Boyles
|
|
|
Contact on site is Jeremiah Goins cell phone # ###-#### Phone #: ###-#### Inspection requested via web by Deb Gooden meet with arch. and elect. eng. and Jeramiah to discuss 2 hr barrier for fire pump system
|