Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberELE15-01138
StatusFinaled
Name ENTERPRISE ELECTRIC
Site Address 1055 N CURTIS RD
Project NameSaint Als North Tower Second F
Customer Number344-0441
ePlanReviewNo
Description
Electrical Permit - Alteration: Demo all electrical, furnish and install electrical system, fire alarm and access control system.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final10/15/201510/19/201510/19/2015APASS
DetailsRex Boyles
We are requesting a final inspection for Monday 10/19/15 in the AM. Our contact is Bryant @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate final ok exam rooms cancer care center
Electrical Rough-In10/1/201510/2/201510/2/2015PPASS
DetailsRex Boyles
We are requesting a ceiling inspection for tomorrow 10/2/15 in the afternoon. Our contact is Bryant @ ###-####. Thank you, Phone #: ###-#### Inspection requested via web by Clint Tate r/i ceilings ok cancer center exam rooms and corridor
Electrical Rough-In9/24/20159/25/20159/25/2015ACANC
DetailsRock A. Hudson
We are requesting a temp. occupancy inspection for tomorrow 9/25/15 in the AM. Our onsite contact is Bryant @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate
OK to occupy soil holding rms, bathroom, exam areas not ready yet. Temp final ok
Electrical Rough-In9/21/20159/22/20159/22/2015APASS
DetailsRex Boyles
We are requesting a ceiling rough-in inspection for tomorrow 9/22/15 in the am. Our onsite contact is Bryant @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate 2nd flr cancer center soil holding rm, clean linen rm. and bathroom ceiings r/i ok
Electrical Rough-In9/15/20159/16/20159/16/2015APASS
DetailsRex Boyles
we are requesting a wall rough-in inspection for phase 4 for tomorrow 9/16/15 in am. Our onsite contact is Bryant ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate r/i ok cancer charting area walls at new wall opening ok
Electrical Rough-In8/26/20158/27/20158/27/2015APASS
DetailsRex Boyles
We are requesting a rough-in inspection for tomorrow 8/27/15 for Phase 4. Our onsite contact is Bryant @ ###-####. Thank you. Phone #: ###-#### Inspection r/i walls only in soil holding rm, bathroom and exam rms. across hall r/i ok requested via web by Clint Tate
Electrical Rough-In7/23/20157/24/20157/24/2015APASS
DetailsRock A. Hudson
We are requesting a final inspection for Phase III only for tomorrow 7/24/15 in the AM. Our onsite contact is Bud @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate Still have work to do phase 4. Phase 3 pharmacy final ok
Final7/23/20157/24/20157/23/2015ACANC
DetailsRex Boyles
We are requesting a final inspection for tomorrow 7/24/15 in the AM. Our onsite contact is Bud @ ###-####. Thank you! Phone #: ###-#### >> Inspection requested via web by Clint Tate Inspection cancelled from web by: Clint Tate
Electrical Rough-In7/20/20157/21/20157/21/2015APASS
DetailsRex Boyles
We are requesting a ceiling rough-in inspectio.
Our onsite contact is Bud ###-####, Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate r/i ceilings ok
Electrical Rough-In7/16/20157/17/20157/17/2015PCANC
DetailsRex Boyles
We are requesting a ceiling rough-in inspection for tomorrow 7/17/15 in the afternoon. Our onsite contact is Bud @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate wrong permit for this address, also inspected second job did inspections and will look for them Monday to input correct info
Electrical Rough-In6/25/20156/26/20156/26/2015PPASS
DetailsRex Boyles
We are requesting a final inspection for Rooms 206 ; 207. Please note that this project is not completed, they just want these rooms final inspected so they can move people into them. Our onsite contact is Bud @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate FINAL ON RMS 206 AND 207 OK
Electrical Rough-In6/24/20156/25/20156/25/2015PPASS
DetailsRex Boyles
We are requesting a ceiling rough-in inspection for tomorrow 6/25/15 in the afternoon. Our contact is Bud @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate r/i ok t bar ceilings in rms 206 and 207
Electrical Rough-In6/16/20156/17/20156/17/2015PPASS
DetailsDaryl DeGrange
We are requesting a wall rough-in on the 2nd floor for tomorrow 6/17/15 in the afternoon. Our onsite contact is Bud @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate rough-in ok cover walls
Electrical Rough-In4/23/20154/24/20154/24/2015APASS
DetailsRock A. Hudson
We are requesting an rough-in inspection for tomorrow 4/24/15. Our contact for this project is Bud @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate Assigned to BLD15-00199. Provider rm 215 and janitors closet power relocated and dividing wall rough in ok cover