Final | 7/10/2015 | 7/13/2015 | 7/13/2015 | A | PASS |
Rex Boyles
|
|
|
Final inspection. Please contact Alex with any questions Phone #: ###-#### Inspection requested via web by Clint Tate corrections made final ok
|
Final | 7/10/2015 | 7/10/2015 | 7/10/2015 | P | FAIL |
Rex Boyles
|
|
|
Final inspection. Please contact Alex with any questions Phone #: ###-#### Inspection requested via web by Clint Tate 210.12 AFCI required in all outlets. 210.8(B)(5)-GFCI required within 6 foot of sinks
|
Final | 6/29/2015 | 6/30/2015 | 6/30/2015 | P | NR |
Rex Boyles
|
|
|
Contact is Alex, he would like to meet you onsite for inspection. Phone #: ###-#### Inspection requested via web by Clint Tate kitchen cabinets not complete. Remove millwork in front of loadcenter -NEC 110.26(A)(1)- 36" standing room required in front of loadcenter.210.8- GFCI protection required on all 120volt receptacles in kitchen.
|
Electrical Rough-In | 5/8/2015 | 5/8/2015 | 5/8/2015 | P | PASS |
Rex Boyles
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Tate correction done, rough-in ok cover
|
Rough-In Permanent Service | 5/7/2015 | 5/7/2015 | 5/7/2015 | P | FAIL |
Daryl DeGrange
|
|
|
Any time after 11:30. Please contact Alex with any questions ###-#### Phone #: ###-#### Inspection requested via web by Clint Tate NEC 210.52 Receptacle spacing(bedroom) NEC 330.12(1) MC install where subject to physical damage.NEC 330.30 Securing within 12 in. of everybox
|