Permit Information
Permit NumberELE15-01348
StatusFinaled
Name LEA ELECTRIC LLC
Site Address 1099 W FRONT ST
Project NameSimplot WHQ - Customer Experie
Customer Number2014-08
ePlanReviewNo
Description
New: Installation of all electrical systems, wiring, conduit, lights, receptacles, panel boards, switches, generators, etc.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final6/29/20176/29/20176/29/2017PPASS
DetailsRock A. Hudson
corrections complete Final ok
Final4/13/20174/14/20174/14/2017PPART
DetailsRock A. Hudson
Call Tony Keen for final in level 1 stack 4 TI area. Phone #: ###-#### Inspection requested via web by Tom Betty
Level 1 stack 4 is a future TI space with some electrical in it. All safe. Items left for core and shell final need to verify raceways for elevator on 5th floor of Annex. Core and shell TCO OK
Conference2/10/20172/10/20172/10/2017PDONE
DetailsRock A. Hudson
Spoke with Joe, General Foreman with Hoffman to address incomplete raceway covers and firewall penetrations on elevator wireways. Annex 5th floor elevator control room and elevator lobby. All will need to by completed before final inspection.
Final1/31/20172/1/20172/1/2017ACANC
DetailsRock A. Hudson
Level 6 Annex rooftop TCO. Call Brandon Phone #: ###-#### Inspection requested via web by Brandon Robinson
Duplicate request. Notes on other
Final1/31/20172/1/20172/1/2017APART
DetailsRock A. Hudson
Level 6 Annex rooftop TCO. Call Brandon Phone #: ###-#### Inspection requested via web by Brandon Robinson
Area noted TCO ok
Final1/20/20171/23/20171/23/2017APART
DetailsRock A. Hudson
Please call Tom Hartung for TCO inspection of levels 7,8,9 of the office building. Phone #: ###-#### Inspection requested via web by Tom Betty
Level 7 board room 749-2 circuit 72-B to be locked off until table is installed. MC thru floor can not be romoved without removing drywall. All levels furniture covers some are loose on line volt and low volt sides. Some card reader low volt boxes open. Shunt trip locations not changed as per State inspectors request, general contractor hoping for variance.
Signed TCO on HQ.
Final1/19/20171/19/20171/19/2017APART
DetailsRock A. Hudson
Levels 5 and 6 HQ TCO. call Brandon Phone #: ###-#### Inspection requested via web by Brandon Robinson
Lab excluded rest of 5, 6 TCO ok
Final1/16/20171/17/20171/17/2017APART
DetailsRock A. Hudson
Level 5 Annex TCO. Call Brandon Phone #: ###-#### Inspection requested via web by Brandon Robinson
Level 5 Annex TCO ok.
Signed progress sheet in Hofman office for HQ fl 1-4 flood areas and Annex level 5
Final1/12/20171/13/20171/13/2017APART
DetailsRock A. Hudson
Call Tom Hartung for levels 1 through 4 Office building final inspection of requested via web by Tom Betty
Discussed if a handle of buss duct disconnects were required at each floor for disconnects located above 6'7".
368.17(C)- States where such devices are mounted out of reach and contain a disconnecting means, suitable means such as chains, ropes, or sticks shall be provided for operating disconnecting means from floor. 240.24 Overcurrent devices location on premises. Overcurrent devices shall be readily accessible and shall be installed so that the grip of the operating handle at its highest point is not more than 6'7" above floor or platform. 404.8 Switches accessiblity. Same wording handle at its highest point shall not exceed 6'7". At future date will check handles are in place due to someone keeps removing them and not returning to areas needed.
Fountain located on level 1 northwest corner, shall check for drain in equipment room, and GFCI protection located in fountain control panel, unable to test not energized waiting for water. Equipotential bond, luminaire clearance not rquired due to decorative body of water.
All wiring, boxes located below raised floor exposed to water redone to ensure good electrical connections.
Replacing gear west end due to flood over weekend. Will call for inspection when complete.
Call stations on these levels installed.
Areas noted levels 1 thru 4 stack 2 flood areas OK to occupy
Electrical Rough-In12/28/201612/29/201612/29/2016APASS
DetailsRock A. Hudson
Level 7 bathroom ceilings. Call Brandon Phone #: ###-#### Inspection requested via web by Brandon Robinson
Area noted rough in ok cover
Electrical Rough-In12/20/201612/21/201612/21/2016APASS
DetailsRock A. Hudson
Level 6 bathrooms ceilings. Call Brandon Phone #: ###-#### Inspection requested via web by Brandon Robinson
Area noted walls and hardlids rough in ok cover
Electrical Rough-In12/13/201612/14/201612/14/2016PPASS
DetailsRock A. Hudson
Call Brandon Robinson for levels 4 and 5 stack 2 rough in of walls and ceilings. Phone #: ###-#### Inspection requested via web by Tom Betty
Area noted and elevator lobbies rough in ok cover
Electrical Rough-In12/12/201612/12/201612/12/2016PPASS
DetailsRock A. Hudson
Call Brandon Robinson for ceiling and wall reconstruction rough in on level 2 and 3 stack 2. Phone #: ###-#### Inspection requested via web by Tom Betty
Bathrooms and elevator lobbies for areas noted rough in ok cover
Final12/8/201612/8/201612/8/2016APART
DetailsRock A. Hudson
Electrical SW GEAR Located in Garage EXP Basement Phone #: ###-#### Inspection requested via web by Tom Betty
Area noted TCO ok
Conference12/5/201612/6/201612/6/2016ADONE
DetailsRock A. Hudson
Contact Tony about NEC 620.51 (C) and relationship to fused disconnect in machine room and shunt trip breaker location outside elevator machine room. Phone #: ###-#### Inspection requested via web by Tom Betty
Discusses code reference noted which does not specify location of shunt trip device. Provided to contractor documentation from DBS and IDAPA elevator safety which states location of shunt device shall be at controller disconnecting means and that state inspector has authority to enforce. City of Boise inspectors will be enforcing wiring methods and general codes up to controller.
Electrical Rough-In12/1/201612/5/201612/5/2016APASS
DetailsRock A. Hudson
Call Brandon for overhead electrical rough in. Level 1 stack 2. Phone #: ###-#### Inspection requested via web by Tom Betty
Area noted repair due to flood rough in ok cover
Final11/21/201611/22/201611/22/2016APART
DetailsRock A. Hudson
Call Brandon for levels 1 through 4 Annex TCO sign off. Phone #: ###-#### Inspection requested via web by Tom Betty 5th floor elevator control room,foyer, center rm gutter covers missing where gutter enters walls and above ceiling. Fire caulked with out cover mounted in elevator foyer. TCO ok
Final11/18/201611/18/201611/18/2016PCANC
DetailsRock A. Hudson
Call Brandon for levels 1 though 4 Annex and level 1 stack 1 office. Phone #: ###-#### Inspection requested via web by Tom Betty
Contractor asked to cancel due to flood. Will recall when ready.
Electrical Rough-In11/17/201611/18/201611/18/2016APASS
DetailsRock A. Hudson
Call Brandon for 11:00 a.m. rough in of north exterior columns. Phone #: ###-#### Inspection requested via web by Tom Betty
N.E. columns rough in ok cover
Electrical Rough-In11/17/201611/17/201611/17/2016PCANC
DetailsRock A. Hudson
Column Rough in inspection, call Brandon Robinson ###-#### Phone #: ###-#### Inspection requested via web by Tom Betty
Contractor asked to cancel and will reschedule for 11-18-16
Electrical Rough-In11/4/201611/7/201611/7/2016APASS
DetailsRock A. Hudson
stair 3 soffit annex . call Brandon Phone #: ###-#### Inspection requested via web by Brandon Robinson
Area noted rough in ok cover
Electrical Rough-In11/3/201611/3/201611/3/2016PPASS
DetailsRock A. Hudson
level 2 soffit on stair 3 exterior. call Brandon Phone #: ###-#### Inspection requested via web by Brandon Robinson
Stair 3 annex building level 2 soffit rough in ok cover
Final11/1/201611/1/201611/1/2016APART
DetailsRock A. Hudson
Core and Shell Ground Level Stack 1 and 2 partial Phone #: ###-#### Inspection requested via web by Tom Betty
Headquarters level 1 stack 1 and 2 and out egress lighting for stairs 2 and 3 in.
Temp occupancy for areas noted in Hoffman office OK
Final10/28/201610/28/201610/28/2016PFAIL
DetailsRock A. Hudson
temp final for Headquarters floos 2 thru 7 Tom ###-####
NFPA ###-#### Life Safety Code, Section 7.8 and 7.9- Exterior egress for stairs 2 and 3 shall have an outdoor generated light source on life safety circuits which produce a minimum of 1ft candle per square ft of illumination.
Conference10/28/201610/28/201610/28/2016ADONE
DetailsRock A. Hudson
Site Frank ###-####, Core and shell Tom ###-####
Discussed possibility of temp occupancy for floors 2 thru 7. Outdoor egress lighting not complete for stair 1. Contractor trying to have lighting temp feed from emergency circuits done. Asked to recheck at 2pm today.
Electrical Rough-In10/19/201610/21/201610/20/2016PPASS
DetailsRock A. Hudson
level 4 annex terrace. call Brandon Phone #: ###-#### Inspection requested via web by Brandon Robinson
Conduits under floor of terrace rough in ok cover.
Final10/19/201610/20/201610/20/2016ANR
DetailsRock A. Hudson
Rock, I need to sign off on the permit rather than the matrix paper that Hoffman provided last week. Same levels just the official document Phone #: ###-#### Inspection requested via web by Tom Betty
Official document includes all of HQ and annex. Unable to sign would release all area described on BLD permit. General contractor will develope a sheet for progress to document which areas are ready to occupy.
Electrical Rough-In10/17/201610/18/201610/18/2016PPASS
DetailsRock A. Hudson
Northeast corner of Annex building soffit. call John Phone #: ###-#### Inspection requested via web by Brandon Robinson
Area noted rough in ok cover
Electrical Rough-In10/14/201610/14/201610/14/2016PPASS
DetailsRock A. Hudson
Parking Control Raceways in Islands Mud-in Fixtures @ concierge Stair. Concierge Ceiling, Maint. Office, Dock Manager. Phone #: ###-#### Inspection requested via web by Tom Betty
Underground, hardlids, and grid noted rough in ok cover.
Hoffman office has sheet for progress report. Noted each floor seperately for TI and core and shell.
Electrical Rough-In10/13/201610/14/201610/14/2016ACANC
DetailsRock A. Hudson
North east corner exterior soffitt of annex building overhead. call Brandon Phone #: ###-#### Inspection requested via web by Brandon Robinson
Plans changed area not ready. Will recall when ready.
Electrical Rough-In10/13/201610/13/201610/13/2016PPASS
DetailsRock A. Hudson
Level 1, headquarters, northwest corner columns. Call Frank Phone #: ###-#### Inspection requested via web by Brandon Robinson
Duplicate request. Area noted lighting rough in ok cover
Electrical Rough-In10/13/201610/13/201610/13/2016PPASS
DetailsRock A. Hudson
Level 1, headquarters, northwest corner columns. Call Frank Phone #: ###-#### Inspection requested via web by Brandon Robinson
Area noted lighting boxes rough in ok cover.
Final10/12/201610/13/201610/13/2016ANR
DetailsRock A. Hudson
C/S Final Stair 1 and 2 Phone #: ###-#### Inspection requested via web by Tom Betty
Unable to final due to out egress lighting not complete at exits of stairways.
Items to complete for temp occupancy. 404.8(A)- Handle for switch handle on bus duct shall be max height of 6'7" on floors 7, 8, 9.
695.6(A)- Supply conductors and fire pump equipment shall be located where total seperation of other corridors and power sources of at least 2 hours. Only single layer of 5/8" dry wall on stairway walls exposed to fire pump room.
Interior stairways complete 1st floor to roof
Final10/4/201610/5/201610/5/2016ANR
DetailsRock A. Hudson
Level 10 Roof Phone #: ###-#### Inspection requested via web by Tom Betty
Level 10 all checked ok other areas in stairs 1 and 2 and egress paths lighting not complete.
Electrical Rough-In10/3/201610/3/201610/3/2016PPASS
DetailsRock A. Hudson
overhead and walls rough in at ramp. call Frank Phone #: ###-#### Inspection requested via web by Brandon Robinson
Wall near stair 2 not framed yet. Rest of ramp walls and ceiling rough in ok cover
Final9/28/20169/28/20169/29/2016PFAIL
DetailsRock A. Hudson
Level 5 and Level 6 C/S Power and Lighting Phone #: ###-#### Inspection requested via web by Tom Betty
110.3- furniture connections shall be installed as per manufacturers instructions. 51C-28 open neutral.
300.15- All boxes containing cables and wiring shall have covers installed.
300.21- Fire wall penetrations shall be sealed.
392.60- ladder racks and cable tray bonding shall be complete.
605.5- Furniture connections and installation shall be complete.
All stack 1 lab to remain unfinished until after 10-7-16.
All panic hardware installed for annex to be energized.
Basement electrical room that has gen set in to retest breakers due to flood.
Final9/24/20169/26/20169/24/2016ACANC
DetailsRock A. Hudson
Level5 C@S Branch Circuit Panels, Lighting and Power Outlets, Equip. Conn. Phone #: ###-#### >> Inspection requested via web by Tom Betty Inspection cancelled from web by: Tom Betty
Final9/23/20169/23/20169/23/2016AFAIL
DetailsRock A. Hudson
Branch Circuit Panels, Branch Circuits, Equip. Conn. , Outlets,
Level 4 Stack 1,2,3,4 Phone #: ###-#### Inspection requested via web by Tom Betty
110.3- Connect furniture as per manufacturers instructions. Furniture fed by panel 41A circuits 63, 65 not working.
300.15- All boxes containing cables shall be covered. Some blinds back ordered wiring not in boxes operates at 15 volt DC. Tie up and store neatly for future installation. Secure covers on furniture several loose.
300.21- Seal large 4x4 hole on interior of electrical room. Seal floor and ceiling when temp wiring has been removed.
392.60- Ladder racks for data cabling shall be bonded.
605.5- Connections to some furniture not complete and furniture missing.
Final9/21/20169/22/20169/22/2016AFAIL
DetailsRock A. Hudson
Level 3 Stack 1,2,3,4 Power Electrical Rooms, Restrooms, IDF Rooms, Vestibules. Branch Circuit Panels and Circuits to Equip, outlets, Phone #: ###-#### Inspection requested via web by Tom Betty
110.3- Furniture connections between each piece shall be complete. Panel 31A 21, 23, 25 not working. 31A 13, 15, 17 not working.
300.15- All boxes installed shall have covers. Low volt card reader, internet interface, misc.
300.15- Funiture covers missing and loose.
300.21- All penetrations in firewalls shall be sealed electrical and non electrical.
392.60- Cable trays and ladder racks bonding shall be complete.
422.30- Hardwired appliances shall have a disconnecting means. 110.25 lock out acceptable.
605.5- Office furniture installation shall be complete. Misc. not connected and level 3 stack 1 no furniture installed
Final9/21/20169/21/20169/21/2016PFAIL
DetailsRock A. Hudson
This is a inspection of level 2 only today. Please keep this permit active for remainder of floors. Contact Brandon Robinson for walk through. Phone #: ###-#### Inspection requested via web by Tom Betty
All lighting for TI portion complete on 2nd floor only. Core and shell lighting not complete in stairways of 2nd floor. Bathrooms and corridors complete.
Final9/20/20169/21/20169/21/2016AFAIL
DetailsRock A. Hudson
Level 2 Stack 1,2,3,4 Electrical Rooms Phone #: ###-#### Inspection requested via web by Tom Betty
300.21- Complete fire caulking of penetrations in electrical room walls. Non-electrical found, sprinkler pipe, communication cables and conduits.
Electrical Rough-In9/19/20169/20/20169/20/2016PPASS
DetailsEric Story
Level 1 stack 2 ceiling. Call Brandon Phone #: ###-#### Inspection requested via web by Brandon Robinson
Hard lid ceilings as noted on print ok cover
Electrical Rough-In9/17/20169/19/20169/19/2016APASS
DetailsRock A. Hudson
Annex Xfmr DBE and Dist. DBE, ATS EQ and ATS-EL Complete Phone #: ###-#### Inspection requested via web by Tom Betty
Panic hardware shall be installed on doors and doors shall be installed prior to energizing Annex electrical rooms. All gear noted rough in ok cover
Electrical Rough-In9/16/20169/16/20169/16/2016PPASS
DetailsEric Story
overhead Level 1 stack 2 partial. Call Frank. Requesting after 2 pm show up. Phone #: ###-#### Inspection requested via web by Brandon Robinson

hard lid as noted on print ok to cover
Electrical Rough-In9/15/20169/16/20169/16/2016APASS
DetailsEric Story
Quad Core Elev. Pits ; top of hoistway east side Ground Level stack 1

Conference on Article 400.7 and 400.8 IDF Rack PWR
Walk thru Basement Discuss TCO prior to meeting 9/21
Thanks
Phone #: ###-#### Inspection requested via web by Tom Betty

rough elevator pit and hoist area-light and outlet ok....conference wiring of low volt room using s/o cable for wiring method....tco conference did not do-wait for Rock/Daryl
Electrical Rough-In9/15/20169/16/20169/16/2016PCANC
DetailsRock A. Hudson
Level 1 stack 2 partial ceiling inspection. Call Frank Phone #: ###-#### >> Inspection requested via web by Brandon Robinson Inspection cancelled from web by: Brandon Robinson
Electrical Rough-In9/15/20169/15/20169/15/2016PFAIL
DetailsRock A. Hudson
Level 1 stack 2 partial ceiling inspection. Call Frank Phone #: ###-#### Inspection requested via web by Brandon Robinson
300.11- All cables and condiuts shall be supported independant of ceiling support system. Low volt cables hanging below ceiling and on ceiling support system.
Electrical Rough-In9/12/20169/12/20169/12/2016PPASS
DetailsRock A. Hudson
Level 5 Annex Men''s bathroom ceiling. Phone #: ###-#### Inspection requested via web by Brandon Robinson mens bathroom annex 5th floor...ok to cover hard lid
Electrical Rough-In9/6/20169/8/20169/8/2016PPASS
DetailsRock A. Hudson
elevator lobby ceilings, levels 6-9. call Frank Phone #: ###-#### Inspection requested via web by Brandon Robinson
9th floor elevator lobby not ready. 6, 7, 8th floor elevator lobby ceilings rough in ok cover.
Electrical Rough-In8/30/20168/31/20168/31/2016PPASS
DetailsEric Story
Level 9 bathroom ceiling. Numerous elevator vestibule ceilings. levels 2-6 Headquarters. Call Frank Phone #: ###-#### Inspection requested via web by Brandon Robinson
Level 9 bathrooms hard lids ok cover
Levels 2,3,4,5 elevator vestibuls hard lids ok cover
Electrical Rough-In8/30/20168/31/20168/30/2016ACANC
DetailsRock A. Hudson
Level 9 bathroom ceiling. call Frank Phone #: ###-#### Inspection requested via web by Brandon Robinson
Duplicate request
Electrical Rough-In8/30/20168/30/20168/30/2016PCANC
DetailsRock A. Hudson
Level 9 bathroom ceiling. call Frank Phone #: ###-#### Inspection requested via web by Brandon Robinson
Called contact and He stated inspection needed 8/31/16
Electrical Rough-In8/29/20168/30/20168/30/2016APASS
DetailsRock A. Hudson
Level 1 and level 8 bathroom ceilings Headquarters. Call Frank Phone #: ###-#### Inspection requested via web by Brandon Robinson
Area noted rough in ok cover
Electrical Rough-In8/26/20168/26/20168/26/2016PPASS
DetailsRock A. Hudson
C;S Room # 104,105 Walls Walls North side Room 100, 123 Phone #: ###-#### Inspection requested via web by Tom Betty
Area 100 corridor north walls and columns 06, 07, 08. 09 column not ready.
Area 123 north wall and column 011 west side only.
Bathrooms 104, 105 walls only.
Areas noted rough in ok cover
Conference8/22/20168/22/20168/23/2016PDONE
DetailsRock A. Hudson
Inspect progress on panic hwd. in Garage EXP Discuss all Electrical Rooms in SWHQ , are we in compliance with 110.26 Personnel Doors? Phone #: ###-#### Inspection requested via web by Tom Betty
Discussed if panic hardware require on all floors where electrical rooms are located. NEC 110.26(C)(3)- States equipment rated 800 amps or more that contain overcurrent devices, switching devices, or control devices, doors for egress located within 25' shall have panic hardware. As per Daryl DeGrange each room with a disconnecting means under 800 amp panic hardware is not required, if disconnects are rated 800 amp or larger panic hard ware required.
Electrical Rough-In8/17/20168/18/20168/18/2016PPASS
DetailsRock A. Hudson
Level 1,3,5,7,9 Life Safety 480/ 120-208 Xfmrs and Branch Circuit Panels

Level 2,4,6,8 EQ. Branch 480/120-208 Xfmers and Branch Circuit Panels Phone #: ###-#### Inspection requested via web by Tom Betty area noted roughin ok
Electrical Rough-In8/17/20168/18/20168/18/2016APASS
DetailsRock A. Hudson
BUSSDUCT BDAA, BDBB, BDCC. associated Bussduct disconnects,480/277 Panels , 480/120-208 xfmers,Branch circuit panels and subpanels ALL NORMAL POWER Phone #: ###-#### Inspection requested via web by Tom Betty for final extensions for disc over 6'7, complete labeling of equiptment. floors 1-5 ok, and 6-9 still terminating. Gentlemen with Hoffman engineering was asking if a lock could be placed on disconnects related to septic systems power. There will be maintenance personnel onsite if needed open.
Electrical Rough-In8/15/20168/16/20168/16/2016APASS
DetailsRock A. Hudson
level 2-5 stair rough in, stair 2 Phone #: ###-#### Inspection requested via web by Brandon Robinson
stair 2 levels 2-5 wall rough-in ok to cover.
Rough-In Permanent Service8/12/20168/12/20168/12/2016PPASS
DetailsRock A. Hudson
Annex HV XFMR 5, 1600 amp MAIN MSSE, 1600 amp Buss Duct MSSE,Grounding Electrode System, Main Bonding Jumper. Want to Energize , Doors and Panic Hwd Annex Phone #: ###-#### Inspection requested via web by Tom Betty
SWHQ stair #2 levels6-9, annex core walls level 5 Phone #: ###-#### Inspection requested via web by Brandon Robinson
Wall rough in as noted ok cover. Annex service ok to energize for temp 200 amp power only. Door issues with electical room.
Electrical Rough-In8/12/20168/12/20168/12/2016PFAIL
DetailsRock A. Hudson
Annex HV XFMR 5, 1600 amp MAIN MSSE, 1600 amp Buss Duct MSSE,Grounding Electrode System, Main Bonding Jumper. Want to Energize , Doors and Panic Hwd Annex Phone #: ###-#### Inspection requested via web by Tom Betty
NEC 110.26(C)(2)- For electrical equipment rated 1200 amps or more and 6 ft wide or more doors for egress shall be at each end of work space. Doors shall remain.
NEC 110.26(C)(3)- Doors located within 25' of electrical gear rated 800 amps or more shall have panic hardware. Doors shall open out in direcion of egress.
If correction not complete by 8-19-16 step will be taken to disconnect power from electrical gear in rooms OBG 121 and 122.
Electrical Rough-In8/4/20168/4/20168/4/2016PPASS
DetailsRock A. Hudson
Ground Level Stack 2/3 Overhead ceiling insp at exterior soffit front entry RM 100,107,108 Phone #: ###-#### Inspection requested via web by Tom Betty
Ceiling as noted rough in ok cover
Electrical Rough-In8/2/20168/3/20168/3/2016PPASS
DetailsRock A. Hudson
Emergency Generator EG-C 1600A, EMSBB GEN. DIST.,T-EQGEN1,EQ-GEN 1 Branch circuit panel, Branch circuits fed from EQGEN 1 ROOM # OBG111 Phone #: ###-#### Inspection requested via web by Tom Betty
Gen set main bonding jumper installed at factory, Tom to remove main bonding jumper at ATS LS and ATS EQ. Gen set and associated gear noted rough in ok cover
Electrical Rough-In8/2/20168/3/20168/3/2016APASS
DetailsRock A. Hudson
level 3 core ceiling, women''s bathroom ( where 3 can lights were missing ),
possibly level 4 core ceiling. Phone #: ###-#### Inspection requested via web by Brandon Robinson
Level 3 womens bath lid complete rough in ok cover, elevator lobby on 1, and 3 wall and ceiling rough in ok cover.
Electrical Rough-In7/27/20167/27/20167/27/2016PPASS
DetailsRock A. Hudson
MDBCC Dist. and more EQ feeders and LS feeders level 5 thru 9
RDBB level 10 and VFD Cooling Towers and Controls
AHU 1,2,3 Feeders and other MDBCC equip Phone #: ###-#### Inspection requested via web by Tom Betty
Areas noted rough in ok cover and energize. furniture whip all have dedicated neutrals for each and all circuits.
Discussed door joining 2 electrical rms.
110.12(C)(2)(b)- If work depth is double only 1 door for egress is required however 2nd door exist and is within 25' from gear and shall open out of each room for egress or be removed.
Electrical Rough-In7/22/20167/22/20167/22/2016PPASS
DetailsRock A. Hudson
EQDBB DIST and its 277/480v BC Panels, 120/208 v BC Panels
LSDBB DIST and its 277/480v BC Panels, 120/208v BC Panels
MDBB Dist and its associated 480 v Controllers Phone #: ###-#### Inspection requested via web by Tom Betty
Still working on panic hardware for electrical rms on lower level. Walked equipment rm in lower level and up thru 4 electrical rms.
Electrical Rough-In7/21/20167/21/20167/21/2016PPASS
DetailsRock A. Hudson
Level 9 bathrooms ceilings. Call Frank Phone #: ###-#### Inspection requested via web by Brandon Robinson
Bathrooms noted hardlid rough in ok cover
Electrical Rough-In7/13/20167/13/20167/13/2016PPASS
DetailsRock A. Hudson
Level 1 of Annex exterior soffit overhead. Phone #: ###-#### Inspection requested via web by Brandon Robinson
Annex level 1 south soffit rough in ok cover
Electrical Rough-In7/8/20167/11/20167/11/2016AFAIL
DetailsRock A. Hudson
Level 8 stack 2 bathroom ceiling inspection. Call Frank Phone #: ###-#### Inspection requested via web by Brandon Robinson
Ceilings covered prior to inspection. Shall remove and recall
Electrical Rough-In6/24/20166/24/20166/24/2016PPASS
DetailsRock A. Hudson
Annex level 1 core walls.
Elevator lobby and stair wall rough in ok cover
Electrical Rough-In6/13/20166/13/20166/13/2016APASS
DetailsEric Story
Bathrooms Level 7. Phone #: ###-#### Inspection requested via web by Tom Betty
floor 7 bathrooms walls and hard lid cielings ok cover
Electrical Rough-In6/9/20166/10/20166/10/2016PNH
DetailsRock A. Hudson
annex level 1 wall inspection Phone #: ###-#### Inspection requested via web by Brandon Robinson
Called 3 times no answer left message, waited 10 minutes, told to recall Monday
Electrical Rough-In6/9/20166/9/20166/9/2016PPASS
DetailsRock A. Hudson
wall rough in inspection. Level 3 Annex restrooms and interior core walls. Phone #: ###-#### Inspection requested via web by Brandon Robinson
As noted and marked on contractor print wall rough in ok cover
Electrical Rough-In6/7/20166/7/20166/7/2016PPASS
DetailsRock A. Hudson
Lighting rough in for stack 3 exterior of service elevator core and exterior of TI space . Phone #: ###-#### Inspection requested via web by Tom Betty
Areas noted rough in ok cover. Cover had begun on part of area, spoke with contact if cover begins again prior to inspection covering will be removed for inspection.
Electrical Rough-In5/18/20165/18/20165/19/2016PPASS
DetailsRock A. Hudson
SWHQ Ground Level in slab Stack 3 Topping Slab Phone #: ###-#### Inspection requested via web by Tom Betty Ground level stack 1, 2, 3, underslab rough in ok cover
Electrical Rough-In5/18/20165/19/20165/19/2016ANH
DetailsRock A. Hudson
Lvl 6 Bathroom Ceilings Phone #: ###-#### Inspection requested via web by Tom Betty
Tryed to call contact number, no answer, message said no voicemail set up yet. recall
Electrical Rough-In4/29/20164/29/20164/29/2016PCANC
DetailsRex Boyles
Phone #: 2088607130 >> Inspection requested via mobile web by Wayne Nihart Inspection cancelled from web by: Tom Betty
Electrical Rough-In4/28/20164/28/20164/28/2016PPASS
DetailsRex Boyles
Rough in for loading dock managers offices , rooms G124 , G126 , G128 , G132 . Phone #: ###-#### Inspection requested via web by Tom Betty r/i walls and ceilings ok
Electrical Rough-In4/27/20164/27/20164/27/2016APASS
DetailsRex Boyles
Rough in slab of Level 1 stack 3 Phone #: ###-#### Inspection requested via web by Tom Betty r/i ok slab on slab conduits and floor boxes medical area telco and electic room
Rough-In Permanent Service4/19/20164/19/20164/19/2016PCANC
DetailsRex Boyles
MSSC , MSSD and associated transformers Phone #: ###-#### Inspection requested via web by Tom Betty needed p/s only
Permanent Service4/19/20164/19/20164/19/2016PPASS
DetailsRex Boyles
MSSC , MSSD and associated transformers Phone #: ###-#### Inspection requested via web by Tom Betty doors are lockable with signage posted, available fault current labeled and lockoffs present on all breakers not ready for energizing. p/s u/g n ok
Rough-In Permanent Service4/11/20164/11/20164/11/2016PNR
DetailsRex Boyles
MSSC , MSSD , Buss duct , 480V Feeders Phone #: ###-#### Inspection requested via web by Tom Betty available fault current as per 110.24 still required prior to energizing service on both main breakers
Conference3/28/20163/28/20163/28/2016PDONE
DetailsRex Boyles
Level 3 Stack 3 Smoke Fire Damper Motor accessibility Phone #: ###-#### Inspection requested via web by Tom Betty fire smoke damper INSIDE duct work not " readily accessable" as per requirments in NEC article 100. Access panel not designed for physically accessing damper. Unsafe confined space not meeting requirments in NEC110-26(C)(1)
Conference3/14/20163/14/20163/14/2016PDONE
DetailsRex Boyles
Contact Tony Keen for conference on bus duct protection. Phone #: ###-#### Inspection requested via web by Tony Keen Discuss unfused buss duct running thru ceiling space in corridor in Bsmt. 230.6-Service entrance conductors shall be considered outside of a building or other structure under the following condition-Where installed within a building or other structure in a raceway that is encased in concrete or brick not less than 2 inches thick. Other option -install fused disconnect feeding buss duct.
Electrical Rough-In2/26/20162/26/20162/26/2016PPASS
DetailsRex Boyles
Wayne Phone #: ###-#### r/i walls division 2 and 3 walls and bathrooms see blue highlighted area on Wayne's plans
Electrical Rough-In2/15/20162/16/20162/16/2016APASS
DetailsRex Boyles
Level 10 Zone 2 Slab Inspection Phone #: ###-#### Inspection requested via web by Tom Betty r/i ok slab on deck inspections 100%
Electrical Rough-In2/11/20162/12/20162/12/2016APASS
DetailsRex Boyles
Call Brandon for level 2 rough in the Annex building. Phone #: ###-#### Inspection requested via web by Tom Betty r/i south auditorium wall ok
Electrical Rough-In2/2/20162/2/20162/2/2016PPASS
DetailsRex Boyles
Level 8 Slab Phone #: ###-#### Inspection requested via web by Tom Betty LEVEL 10-slab on deck (roof) conduits phase 1 r/i ok
Electrical Rough-In1/19/20161/21/20161/21/2016APASS
DetailsRex Boyles
Level 9 Stack 3/4 Slab Phone #: ###-#### Inspection requested via web by Tom Betty r/i level 9 west slab on deck conduits and floor boxes ok
Electrical Rough-In1/4/20161/6/20161/6/2016APASS
DetailsRex Boyles
Contact Brandon Robinson for Level 5 elevator equipment room rough in. Phone #: ###-#### Inspection requested via web by Tom Betty r/i walls ok
Conference12/31/20151/4/20161/4/2016APASS
DetailsRex Boyles
Questions regarding uses permitted for type MC cable/standard box enclosures Phone #: ###-#### Inspection requested via web by Tom Betty discuss installation of MC cable inside sandstone facade. OK as per NEC 330.10 (A)(11) c
Electrical Rough-In12/31/20151/4/20161/4/2016APASS
DetailsRex Boyles
Level 9/Zone 2 Slab inspection Phone #: ###-#### Inspection requested via web by Tom Betty r/i ok S.O.D. conduits and floor boxes
Final12/21/201512/21/201512/21/2015PPASS
DetailsRex Boyles
Deck inspection Level 8 Stack 2/3 Phone #: ###-#### Inspection requested via web by Tom Betty r/i ok level 8 zone 2 S.O.D conduits and floor boxes ok
Electrical Rough-In11/16/201511/17/201511/17/2015APASS
DetailsDaryl DeGrange
Level 8 Zone 1 Phone #: ###-#### Inspection requested via web by Tom Betty rough-in ok pour slab
Electrical Rough-In11/9/201511/10/201511/10/2015APASS
DetailsRex Boyles
Level 7 Zone 3 Phone #: ###-#### Inspection requested via web by Tom Betty r/i ok slab on deck conduits and floor boxes
Electrical Rough-In10/30/201510/30/201510/30/2015PPASS
DetailsRex Boyles
Level 7 Zone 2 Phone #: ###-#### Inspection requested via web by Tom Betty r/i ok slab on deck conduits and floor boxes
Electrical Rough-In10/30/201510/30/201510/30/2015PCANC
DetailsRex Boyles
Phone #: 2088001408 >> Inspection requested via mobile web by Tom Hartung Inspection cancelled from web by: Tom Betty
Electrical Rough-In10/23/201510/26/201510/26/2015PPASS
DetailsRex Boyles
Contact Brandon Robinson for level 4 Annex building underslab raceways. Phone #: ###-#### Inspection requested via web by Tom Betty r/i ok annex bldg. 4th flr exterior dining areas south and east underslab ok
Electrical Rough-In10/21/201510/21/201510/21/2015PPASS
DetailsRex Boyles
Lvl 7 Zone 1 Slab Inspection Phone #: ###-#### Inspection requested via web by Tom Betty r/i ok slab on deck SWH bldg
Conference10/16/201510/16/201510/16/2015PDONE
DetailsRex Boyles
Conference re: MC supports on Fantoni ceiling structure Phone #: ###-#### Inspection requested via web by Tom Betty discuss Fantoni ceiling electrical installation, each fixture to have seismic wire but mc cable ok to clip to grid in this application using listed clips. Separate support wire not necessary here.
Electrical Rough-In9/25/20159/28/20159/28/2015APASS
DetailsRex Boyles
Contact Brandon Robinson for Annex building levels 2 and 3 wall rough in. Phone #: ###-#### Inspection requested via web by Tom Betty r/i walls 2nd and 3rd flr electrical rms, IDF rms and janitor closets ok
Electrical Rough-In9/23/20159/23/20159/23/2015PPASS
DetailsRex Boyles
Lvl 6 Zone 1 In slab inspection Phone #: ###-#### Inspection requested via web by Tom Betty r/i ok slab on deck
Electrical Rough-In9/14/20159/14/20159/14/2015PPASS
DetailsRex Boyles
Lvl 5, Zone 3 Phone #: ###-#### Inspection requested via web by Tom Betty r/i slab on deck ok
Conference9/2/20159/2/20159/2/2015PDONE
DetailsRex Boyles
Article 376 Wireways - Fill and Derating Conductors Phone #: ###-#### Inspection requested via web by Tom Betty discuss with Tom 2-custom pull boxes with 2 covers being made for electrical room. After reviewing drawings and NEC requirements, we agreed on this application that will satisfy NEC 376.22(A)&(B), will also satisfy 310.10 (H), will also satisfy 314.28(A)(2), will also satisfy 314.40(C)and(D), will also satisfy 314.71(A) and (B). Cables will be supported so as to not lay on cover.
Conference8/28/20158/31/20158/31/2015PCANC
DetailsRex Boyles
Article 376, wireways. Capacity, derating conductors Phone #: ###-#### Inspection requested via web by Tom Betty re schedule for am conf. Could'nt reach Tom
Electrical Rough-In8/28/20158/31/20158/31/2015PPASS
DetailsRex Boyles
SHQ Lvl 5 Zone 2 in slab inspection Phone #: ###-#### Inspection requested via web by Tom Betty level 5 zone 2 slab on deck ok to pour
Conference8/21/20158/24/20158/24/2015ADONE
DetailsEric Story
Article 376.22 Metal Wireways Phone #: ###-#### Inspection requested via web by Tom Betty discussed using a raceway and adding a barrier in the enclosure to seperate parrelled conductors as per 376.22
Electrical Rough-In8/21/20158/24/20158/24/2015APASS
DetailsEric Story
Lvl 5/Zone 1 Slab on Deck Rough In Phone #: ###-#### Inspection requested via web by Tom Betty lvl 5 zone 1 ok cover
Electrical Rough-In8/12/20158/12/20158/12/2015PPASS
DetailsRex Boyles
Slab inspection: HQ Lvl4, Zone 3 Phone #: ###-#### Inspection requested via web by Tom Betty r/i ok level 4 zone 3 slab on deck
Conference8/5/20158/6/20158/6/2015ADONE
DetailsRex Boyles
Contact Tom Hartung for question on acceptable dry in classification for project. Phone #: ###-#### Inspection requested via web by Tom Betty discuss installing mc cable in annex building metal stud walls prior to exterior wall installation. 2014 NEC 330.10(11) In wet locations where a corrosion resistant jacket is provided over the metallic covering AND any of the following conditions are met (a)the metallic covering is impervious to moisture (b) a jacket resistant to moisture is provided under the metal covering (c)The insulated conductors under the metallic covering are listed for use in wet locations
Electrical Rough-In8/5/20158/6/20158/6/2015APASS
DetailsRex Boyles
Contact Tom Hartung for level 4 area 2 rough in slab location Phone #: ###-#### Inspection requested via web by Tom Betty r/i slab on deck conduits and floor boxes ok
Electrical Rough-In7/28/20157/28/20157/28/2015PPASS
DetailsRex Boyles
r/i ok level 4 / zone 1 slab on deck conduits
Final7/27/20157/28/20157/28/2015ACANC
DetailsRex Boyles
Contact Tom Hartung for level 4 rough in slab of SWHQ job. Phone #: ###-#### Inspection requested via web by Tom Betty needed r/i
Electrical Rough-In7/18/20157/20/20157/20/2015APASS
DetailsRex Boyles
Contact Tom Hartung for level 3 concrete pad roughin of SWHQ. Phone #: ###-#### Inspection requested via web by Tom Betty r/i ok slab on deck zone 3 level3
Electrical Rough-In7/10/20157/13/20157/13/2015APASS
DetailsRex Boyles
Contact Tom Hartung for level 3 in slab rough in. Phone #: ###-#### Inspection requested via web by Tom Betty ZONE2 LEVEL 2 SLAB ON GRADE R/I OK
Electrical Rough-In6/30/20156/30/20156/30/2015PPASS
DetailsRex Boyles
Slab inspection for Level 3 Zone 1

Please call Tom Hartung for jobsite access. Phone #: ###-#### Inspection requested via web by Tom Betty level 3 zone 1 slab on deck ok to pour
Electrical Rough-In6/19/20156/22/20156/22/2015APASS
DetailsRex Boyles
Under-slab inspection Simplot HQ- Call Tom Hartung for access.
###-####. Phone #: ###-#### Inspection requested via web by Tom Betty r/i ok s.o.d. level2 / zone 3
Electrical Rough-In6/3/20156/5/20156/5/2015PPASS
DetailsRex Boyles
Contact Tom Hartung for level 2 rough in slab. Phone #: ###-#### Inspection requested via web by Tom Betty r/i ok level2 zone 2 slab on deck conduits and floor boxes ok to pour
Electrical Rough-In5/12/20155/12/20155/12/2015PPASS
DetailsDaryl DeGrange
Contact Tom Hartung for in slab rough in level 2 Simplot World Headquarters. Phone #: ###-#### Inspection requested via web by Tom Betty rough-in ok pour zone 1(blue)
Final5/12/20155/12/20155/12/2015PCANC
DetailsDaryl DeGrange
Contact Tom Hartung for in slab rough in on level 2 Simplot World headquarters. Phone #: ###-#### >> Inspection requested via web by Tom Betty Inspection cancelled from web by: Tom Betty