Information based on query as of Wednesday, July 3, 2024.
Permit Information
Permit NumberELE15-02131
StatusFinaled
Name LEA ELECTRIC LLC
Site Address 1004 W ROYAL BLVD
Project Name 
Customer Number2014-07
ePlanReviewNo
Description
New: Install power and lighting for the East Wing apartment units, including panels, fixtures, wiring devices.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final8/26/20158/26/20158/26/2015APASS
DetailsRex Boyles
5th floor finals. Phone #: ###-#### Inspection requested via web by Rafael Castillo final 100% ok perm. occupancy ok
Final8/25/20158/25/20158/25/2015PPART
DetailsRex Boyles
Units east wing 5th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo final 100% except corridors
Final8/14/20158/15/20158/15/2015PCANC
DetailsRex Boyles
Rafial - ###-#### not needed
Final8/14/20158/15/20158/15/2015APART
DetailsRex Boyles
Rafial - ###-#### final ok rm, 413, 3rd and 4th floor corridors and data closets and lobbys and rooftop units. Temporary Occupancy ok 3rd and 4th floors
Final8/14/20158/14/20158/14/2015PPART
DetailsRex Boyles
Units 3rd and 4th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo final ok room 342. Temporary occupancy ok for 2nd floor rooms, corridors and lobby 100% complete.
Final8/14/20158/14/20158/14/2015APART
DetailsRex Boyles
Unit inspection, 2nd, 3rd, and 4th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo final ok rm 242
Final8/13/20158/13/20158/13/2015PPART
DetailsRex Boyles
Final inspections for units. Phone #: ###-#### Inspection requested via web by Rafael Castillo final ok rms. 308, 408, 416, 442, 419
Electrical Rough-In8/13/20158/13/20158/13/2015APASS
DetailsRex Boyles
Corridor grid ceiling inspection 5th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok
Final8/11/20158/11/20158/11/2015PPART
DetailsRex Boyles
4th floor unit inspections. Phone #: ###-#### Inspection requested via web by Rafael Castillo final ok west wing rms. 401 thru 407, 409 thru 410, 411,412,414,415,417, 418 ,420 ,443 and 444. NOTE rms. 408, 413, 416 and 442 not ready
Final8/10/20158/10/20158/10/2015PPART
DetailsRex Boyles
Unit inspections 2nd and 3rd floors. Phone #: ###-#### Inspection requested via web by Rafael Castillo all rms. on 2nd flr now have 50% energy effiecient lamps CFL's. All rms. on 3rd flr also 50% CFL's. final ok rms. 301 thru 318, 320, 343 and 344. NOTE:242 not ready
Electrical Rough-In8/10/20158/10/20158/10/2015APART
DetailsRex Boyles
Lobby grid ceilings 1st, 2nd, 3rd, and 4th floors. Phone #: ###-#### Inspection requested via web by Rafael Castillo 2nd, 3rd and 4th floor, middle and south elevator lobbys ok
Electrical Rough-In8/6/20158/6/20158/6/2015APASS
DetailsRex Boyles
4th floor corridor grid ceilings. Phone #: ###-#### Inspection requested via web by Rafael Castillo east wing ceilingsok to cover
Final8/5/20158/5/20158/5/2015PNR
DetailsRex Boyles
Final inspections units 2nd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo dishwashers not in yet
Final8/5/20158/5/20158/5/2015APART
DetailsRex Boyles
Final inspections 2nd floor units. Phone #: ###-#### Inspection requested via web by Rafael Castillo final ok on rms. 221, 224 thru 231, 232 thru 241 NOTE; o/s receptacles not done in rms. 200, 218,223 and 233 also need 50% energy effiecient lamps throughout.
Final8/3/20158/3/20158/3/2015PPART
DetailsRex Boyles
Final for units on 2nd floor east wing. Phone #: ###-#### Inspection requested via web by Rafael Castillo rms 201 thru216 ok except GFCI within 6 foot of sinks and exterior receptacles not trimmed out and 50% energy saving lamps in each unit.
Electrical Rough-In7/31/20157/31/20157/31/2015PPASS
DetailsRex Boyles
2nd floor east t grid ceiling inspection, corridors only. Phone #: ###-#### Inspection requested via web by Rafael Castillo 2nd flr corridor ceiling east r/i ok
Electrical Rough-In7/30/20157/30/20157/30/2015PPASS
DetailsRex Boyles
Grid ceiling inspection 3rd floor corridors. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i 3rd flr corridor t bar ceiling ok to cover
Electrical Rough-In7/23/20157/23/20157/23/2015APASS
DetailsRex Boyles
5th floor drop ceilings. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceilings in rms. 540, 541, 545, 531, 533 and 538
Electrical Rough-In7/22/20157/22/20157/22/2015PPASS
DetailsRex Boyles
5th floor drop ceiling rough in. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceilings in rms. 504, 508, 510, and 516
Final7/21/20157/21/20157/21/2015PCANC
DetailsRex Boyles
5th floor drop ceiling. Phone #: ###-#### Inspection requested via web by Rafael Castillo needed r/i
Electrical Rough-In7/21/20157/21/20157/21/2015PPASS
DetailsRex Boyles
5th floor drop ceiling. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceiling in 544
Electrical Rough-In7/21/20157/21/20157/21/2015APASS
DetailsRex Boyles
5th floor drop ceiling rough in. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceilings in rms 501 thru 503, 506 and 543
Electrical Rough-In7/10/20157/10/20157/10/2015APASS
DetailsRex Boyles
Rough in of drop ceilings on 5th floor east wing. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceilings in rms. 503, 505, 509, 511, 512, 513 and 514
Electrical Rough-In7/7/20157/7/20157/7/2015APASS
DetailsRex Boyles
5th floor drop ceilings. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok rm. soffits in 515,518 thru 524, 526 thru 528
Electrical Rough-In7/1/20157/1/20157/1/2015APASS
DetailsRex Boyles
5th floor east corridor walls. Phone #: ###-#### Inspection requested via web by Rafael Castillo 5th flr east corridors wall receptacles and sconces ok to cover
Electrical Rough-In6/25/20156/25/20156/25/2015APASS
DetailsRex Boyles
4th floor drops, 5th floor shafts. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceilings in rms. 432 thru 434, 436, 437, 439, 427 thru 429. Also vent. shafts in 5th flr see E3.2 sheet
Electrical Rough-In6/19/20156/19/20156/19/2015ANR
DetailsEric Story
4th floor drop ceilings west wing. Phone #: ###-#### Inspection requested via web by Rafael Castillo rot ready at this time
Electrical Rough-In6/4/20156/4/20156/4/2015APASS
DetailsRex Boyles
Shaft inspection 3rd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok vent. shafts in rms. 308,310,316,333,331 and 325
Electrical Rough-In6/3/20156/3/20156/3/2015APASS
DetailsRex Boyles
5th floor unit rough-in. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok rms. 512 thru 520 and 542 thru 544. Also r/i ok stairwell C on all floors
Electrical Rough-In6/2/20156/2/20156/3/2015APASS
DetailsRex Boyles
Units 5th floor east. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i rms 501 thru 511 ok
Electrical Rough-In5/21/20155/21/20155/21/2015APASS
DetailsRex Boyles
Drop ceilings 2nd floor, units 4th floor east, spa room ceiling. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok spa ceiling, drop ceilings in rms. 221thru224, 226 thru 230,240 and 241. r/i ok in rms. 419,421,422,443 and 444. Vent. shafts in 421 and 422.
Electrical Rough-In5/20/20155/20/20155/20/2015APASS
DetailsRex Boyles
Spa room, corridors 3rd floor, units 4th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok all 3rd flr corridors, all 3rd flr comm. rms. and trash rms.. All house panel electric rooms on 2,3,4 and 5th flrs.. Vent. shafts in rms. 412 thru 415 and 417. Rms. 409 thru 418 r/i ok
Electrical Rough-In5/19/20155/19/20155/19/2015APASS
DetailsRex Boyles
Stairwell "A" rough-in. Units 4th level east. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok stairwell A, drop ceilings in rms. 232,234 thru237 and 239. r/i ok rms. 401 thru 408
Electrical Rough-In5/11/20155/11/20155/11/2015APASS
DetailsRex Boyles
2nd floor drop down ceilings. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok rm. soffits rms. 208, 209, 211, 213 thru 215. NOTE: ok to install nm cable at west wing from center corridor to the north due to progress of roof work
Electrical Rough-In5/6/20155/7/20155/7/2015APASS
DetailsRex Boyles
3rd floor shafts, drop down ceilings 2nd floor, corridor MC 2nd and 3rd floors. Phone #: ###-#### Inspection requested via web by Rafael Castillo east wing rm. soffits rm. 210 and 207 r/i ok Note:west half of bldg. roof not dryed in yet. No nm cable can be installed yet.
Electrical Rough-In5/4/20155/5/20155/5/2015APASS
DetailsRex Boyles
3rd floor east wing shafts, drop ceilings on 2nd floor east wing. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok 202 thru 206 rm. soffits, vent. shafts ok in rms. 302 thru 307, 309, 311 thru315 and 318
Electrical Rough-In5/3/20155/4/20155/4/2015APASS
DetailsRex Boyles
3rd floor east wing units, 3rd floor shafts, roof progress on west wing. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok rms. 317 thru 320, 342 thru 344 NOTE: west wing roof not sealed up or done. Not ok to run nm cable yet under this area.
Electrical Rough-In5/1/20155/1/20155/1/2015APASS
DetailsRex Boyles
Rough-in shafts 2nd floor, rough-in units east wing 3rd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok rms 301 thru 316 and shaft 208
Electrical Rough-In4/7/20154/7/20154/7/2015AFAIL
DetailsDaryl DeGrange
Rough in north exterior wall in clubhouse, walls only. Phone #: ###-#### Inspection requested via web by Rafael Castillo Insulation and sheet rock installed prior in cover inspection on north wall og clubhouse, Remove insulation and sheet rock to complete cover inspection. Stop work on electrical installation of East Wing till roofing envelope 100% completed, do to exccessive amount of rain water still getting in below.
Electrical Rough-In3/19/20153/19/20153/19/2015APASS
DetailsRex Boyles
Rough-in inspection 2nd floor units west wing. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok 2nd level west wing see E2.1
Electrical Rough-In3/18/20153/18/20153/18/2015APASS
DetailsRex Boyles
Rough-in inspection for remainder of 2nd floor east wing. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i 2nd flr east wing ok see E2.1
Electrical Rough-In3/16/20153/17/20153/17/2015APASS
DetailsRex Boyles
Rough-in inspection for units on 2nd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo partial r/i units on 2nd floor see pg.E2.1
Electrical Rough-In2/25/20152/25/20152/25/2015APASS
DetailsRex Boyles
Corridors east wing walls only. Unit rough-in. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i 2nd flr corridors ok to cover
Conference2/6/20152/6/20152/6/2015ADONE
DetailsRex Boyles
Discuss panel locations and main breakers not located in units. Phone #: ###-#### Inspection requested via web by Rafael Castillo discuss access to main breakers for each tenant.
Conference2/4/20152/4/20152/4/2015ADONE
DetailsRex Boyles
Discuss panel locations and accessibility. Phone #: ###-#### Inspection requested via web by Rafael Castillo discuss access to loadcenters in each unit. Each rental unit is separate inside unit. EX: only one renter will have access to panel out of 4 renters.