Final | 10/13/2015 | 10/13/2015 | 10/13/2015 | P | PASS |
Rock A. Hudson
|
|
|
Bob is the site contact Phone #: ###-#### Inspection requested via web by Kerri Hamilton Final ok
|
Electrical Rough-In | 10/8/2015 | 10/9/2015 | 10/9/2015 | P | PASS |
Rock A. Hudson
|
|
|
Bob Thomas Phone #: ###-#### Inspection requested via web by Kerri Hamilton Checked generator, transfer switch, and battery room grid rough in ok cover.
|
Rough-In Permanent Service | 9/10/2015 | 9/10/2015 | 9/10/2015 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Main disconnecting means is fused so talked to contractor to make sure available fault current posted by final. Service rough in ok p/s u/g n ok
|
Electrical Rough-In | 9/8/2015 | 9/9/2015 | 9/9/2015 | A | PASS |
Rock A. Hudson
|
|
|
Underground. Bob Thomas Phone #: ###-#### Inspection requested via web by Kerri Hamilton Common grounding electrode system used. Underground from transformer to CT can rough in ok cover
|
Electrical Rough-In | 7/23/2015 | 7/24/2015 | 7/23/2015 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Underground to generator pads rough in ok cover
|
Electrical Rough-In | 7/21/2015 | 7/22/2015 | 7/22/2015 | A | PASS |
Rock A. Hudson
|
|
|
Bob Thomas Phone #: ###-#### Inspection requested via web by Kerri Hamilton Outer walls to be fished or surface mounted. Interior wall rough in ok cover
|