Final | 11/27/2015 | 11/27/2015 | 11/27/2015 | P | PASS |
Eric Story
|
|
|
we are requesting a final inspection for today in the afternoon. Our contact is Todd @ ###-####. thank you Phone #: ###-#### Inspection requested via web by Clint Tate final ok
|
Final | 11/25/2015 | 11/25/2015 | 11/25/2015 | P | NR |
Eric Story
|
|
|
We are requesting a final inspection for as late as possible today 11/25/15. Our contacts are Todd ###-#### ; Luke ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate contractor not ready
|
Electrical Rough-In | 11/5/2015 | 11/6/2015 | 11/6/2015 | A | PASS |
Eric Story
|
|
|
We are requesting a rough-in inspection for tomorrow 11/6/15 in the AM. Our onsite contact is Luke @ ###-####. Thank you, Phone #: ###-#### Inspection requested via web by Clint Tate walls in bathrooms and hallway wals ok cover
|
Electrical Rough-In | 10/9/2015 | 10/12/2015 | 10/12/2015 | A | PASS |
Eric Story
|
|
|
We are requesting a underground inspection for Monday 10/12/15. Our contact is Luke @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate underground ok cover
|