Final | 2/23/2016 | 2/24/2016 | 2/24/2016 | A | PASS |
Eric Story
|
|
|
Shannon is the contact his cell no is ###-####. Phone #: ###-#### Inspection requested via web by Shawna Gates final on secrurity camera power and gates ok
|
Electrical Rough-In | 10/30/2015 | 11/2/2015 | 11/2/2015 | P | PASS |
Rex Boyles
|
|
|
Underground. Jake is the contact his cell no. is ###-#### Phone #: ###-#### Inspection requested via web by Shawna Gates r/i u.ground from gaurd shack up to large gate ok to cover
|
Electrical Rough-In | 10/20/2015 | 10/20/2015 | 10/20/2015 | A | PASS |
Eric Story
|
|
|
Jake is the contact his cell no. is ###-#### Phone #: ###-#### Inspection requested via web by Shawna Gates underground for gate as per contractors print ok cover
|
Final | 10/20/2015 | 10/20/2015 | 10/20/2015 | A | CANC |
Eric Story
|
|
|
Shawna Phone #: ###-#### needed rough-in
|
Electrical Rough-In | 10/16/2015 | 10/16/2015 | 10/16/2015 | A | DONE |
Eric Story
|
|
|
Underground. Jake is the contact his cell no. ###-####. Phone #: ###-#### Inspection requested via web by Shawna Gates underground as per contractors print ok cover
|
Electrical Rough-In | 10/15/2015 | 10/15/2015 | 10/15/2015 | A | DONE |
Eric Story
|
|
|
underground in the parking lot Jake is the contact ###-#### Phone #: ###-#### Inspection requested via web by Shawna Gates north east underground accross parking lot as per contractors print
|
Final | 8/27/2015 | 8/27/2015 | 8/27/2015 | A | CANC |
Eric Story
|
|
|
Mike is the contact his cell no is ###-#### Phone #: ###-#### >> Inspection requested via web by Shawna Gates Inspection cancelled from web by: Shawna Gates
|
Temporary Service | 8/26/2015 | 8/26/2015 | 8/26/2015 | A | CANC |
Eric Story
|
|
|
Mike Phone #: ###-#### Inspection cancelled from web by: Shawna Gates
|