Final | 6/23/2016 | 6/27/2016 | 6/27/2016 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Stacie Tasker final ok
|
Final | 5/19/2016 | 5/20/2016 | 5/20/2016 | P | PART |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Stacie Tasker north side of building ok(will need to verify desk areas and 1 4 of s.e of car bay for car lifts)
|
Final | 5/18/2016 | 5/20/2016 | 5/19/2016 | A | CANC |
Eric Story
|
|
|
We need a partial final for Friday. Site contact is Mike. Thank you! Phone #: ###-#### >> Inspection requested via web by Stacie Tasker Inspection cancelled from web by: Stacie Tasker
|
Final | 5/16/2016 | 5/17/2016 | 5/17/2016 | P | PART |
Eric Story
|
|
|
We need a partial final. Mike is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker salesman area N./training room/GM office and storage/General office/Sales offices/Interior desk/Showroom/Conference and storage/Guest room still needs floor boxes installed/Parts area and up mezzaine/SVM offices/car recieving areas partial ok( Guest area rooms need floor outlets installed due to tile being removed, where all areas have flex coming from floor for island EC will blank all of them for safety)
|
Electrical Rough-In | 5/10/2016 | 5/12/2016 | 5/12/2016 | A | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Stacie Tasker Employee lounge, Empoyee lounge hall, And car recieving loung Grid only. OK to cover
|
Electrical Rough-In | 5/9/2016 | 5/10/2016 | 5/10/2016 | A | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Stacie Tasker Grid in E Conferance, Files, Data and car receiving office areas
|
Electrical Rough-In | 5/6/2016 | 5/9/2016 | 5/9/2016 | P | FAIL |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Stacie Tasker Several lights not tied off Discused pole bases for parking lot lights. Spec sheet calls for 2'6" exposed above grade. will check at final
|
Electrical Rough-In | 5/3/2016 | 5/3/2016 | 5/3/2016 | P | PASS |
Eric Story
|
|
|
Mike Phone #: ###-#### Showroom offices and car receiving ceiling only ok to cover
|
Electrical Rough-In | 4/25/2016 | 4/26/2016 | 4/26/2016 | A | PASS |
Rock A. Hudson
|
|
|
We need a ceiling inspection and would like to request it be your first stop if possible. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Showroom upper grid only rough in ok cover
|
Electrical Rough-In | 4/12/2016 | 4/13/2016 | 4/13/2016 | P | PASS |
Rock A. Hudson
|
|
|
We need a ceiling inspection, Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Grid in service bay rough in ok cover
|
Electrical Rough-In | 4/11/2016 | 4/12/2016 | 4/12/2016 | A | NR |
Rock A. Hudson
|
|
|
We need a ceiling inspection, Thank you! Mike is site contact. Phone #: ###-#### Inspection requested via web by Stacie Tasker Needed PM inspection
|
Electrical Rough-In | 3/28/2016 | 3/29/2016 | 3/29/2016 | A | PASS |
Rock A. Hudson
|
|
|
We need a ceiling inspection, please. Thank you1 Phone #: ###-#### Inspection requested via web by Stacie Tasker Customer lounge hardlid rough in ok cover
|
Electrical Rough-In | 3/21/2016 | 3/23/2016 | 3/23/2016 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Stacie Tasker Bathroom hardlids rough in ok cover
|
Permanent Service | 3/22/2016 | 3/22/2016 | 3/22/2016 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Stacie Tasker Needed rough in inspection
|
Electrical Rough-In | 3/22/2016 | 3/22/2016 | 3/22/2016 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Stacie Tasker Rough in for transformer. Grounding electrode system off building steel. Rough in ok
|
Electrical Rough-In | 3/18/2016 | 3/21/2016 | 3/21/2016 | P | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Stacie Tasker fireplace wall,breakroom,and baths walls only ok cover
|
Electrical Rough-In | 3/15/2016 | 3/16/2016 | 3/16/2016 | A | PASS |
Rock A. Hudson
|
|
|
Mike Phone #: ###-#### North and west underground for parking lot lights, guest bathrooms, office near guest bath, and entry walls and hardlids
|
Electrical Rough-In | 3/9/2016 | 3/10/2016 | 3/10/2016 | P | PASS |
Rock A. Hudson
|
|
|
Mike Phone #: ###-#### S.E. showroom and offices wall rough in ok cover
|
Permanent Service | 3/2/2016 | 3/2/2016 | 3/2/2016 | P | PASS |
Rock A. Hudson
|
|
|
Inspection requested via web by Stacie Tasker p/s u/g n ok
|
Permanent Service | 2/29/2016 | 3/4/2016 | 3/2/2016 | A | CANC |
Rock A. Hudson
|
|
|
Phone #: ###-#### >> Inspection requested via web by Stacie Tasker Inspection cancelled from web by: Stacie Tasker
|
Electrical Rough-In | 2/29/2016 | 2/29/2016 | 2/29/2016 | P | PASS |
Rock A. Hudson
|
|
|
We need an underground inspection for today. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker 4" and 1 1/2" for signage and communication on south east corner of lot. Rough in ok cover
|
Rough-In Permanent Service | 2/24/2016 | 2/25/2016 | 2/25/2016 | A | FAIL |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Stacie Tasker 110.24- Available fault current shall be posted with date calculated prior to P/S. 230.95(C)- performance test shall be performed for 1600 amp 480 service prior to P/S. 250.24- Grounding electrode system shall be connected to grounded conductor prior to P/S. 2 Spare conduits in electrical room off service bay shall be permenantly sealed as ventalation provided but vents not with in 12" of floor. Verbal with electrical foreman.
|
Electrical Rough-In | 2/24/2016 | 2/24/2016 | 2/24/2016 | P | PASS |
Eric Story
|
|
|
underground; Mike Phone #: ###-#### south parking lot underground for parking lot lights ok cover
|
Temporary Service | 2/24/2016 | 2/24/2016 | 2/24/2016 | P | CANC |
Eric Story
|
|
|
underground; Mike Phone #: ###-#### needed seperate permit for temp service
|
Electrical Rough-In | 1/21/2016 | 1/21/2016 | 1/21/2016 | P | PASS |
Rock A. Hudson
|
|
|
We need an underground inspection. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker East electrical room underground rough in ok cover
|
Electrical Rough-In | 12/7/2015 | 12/7/2015 | 12/7/2015 | P | PASS |
Rock A. Hudson
|
|
|
underground Phone #: ###-#### East electrical room rough in ok cover
|
Electrical Rough-In | 11/20/2015 | 11/23/2015 | 11/23/2015 | P | PASS |
Rock A. Hudson
|
|
|
We need an underground inspection. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Under slab (C) rough in ok cover
|
Electrical Rough-In | 11/13/2015 | 11/16/2015 | 11/16/2015 | P | PASS |
Rock A. Hudson
|
|
|
We need an underground inspection. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Slab B underground rough in ok cover
|
Electrical Rough-In | 11/10/2015 | 11/10/2015 | 11/10/2015 | P | PASS |
Rock A. Hudson
|
|
|
We need an underground inspection. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Slab A only rough in ok cover
|
Electrical Rough-In | 11/10/2015 | 11/12/2015 | 11/10/2015 | A | CANC |
Rock A. Hudson
|
|
|
We need an underground inspection for Thursday. Thank you! Phone #: ###-#### >> Inspection requested via web by Stacie Tasker Inspection cancelled from web by: Stacie Tasker
|
Electrical Rough-In | 10/28/2015 | 10/29/2015 | 10/29/2015 | A | PASS |
Rock A. Hudson
|
|
|
We need an underground inspection. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker Underground to east electrical room and concrete encased electrode rough in ok cover
|
Rough-In Permanent Service | 10/22/2015 | 10/23/2015 | 10/23/2015 | P | PASS |
Rock A. Hudson
|
|
|
We need an underground inspection. Thank you! Please contact Danny at the number listed Phone #: ###-#### Inspection requested via web by Stacie Tasker Electical room underground rough in ok cover
|