Final | 8/9/2016 | 8/10/2016 | 8/10/2016 | P | PASS |
James Ady
|
|
|
Contact is Robert Gates Phone #: ###-#### Inspection requested via web by Scott Campbell Final ok
|
Electrical Rough-In | 12/10/2015 | 12/11/2015 | 12/11/2015 | P | PASS |
Eric Story
|
|
|
This is for a PVC conduit trench. We have an AM inspection scheduled fro tomorrow morning on the pole bases - it may be possible to do both of these in the morning, depending on what time the inspector shows up. Any questions on this please call Derek Ball at number listed in request. Phone #: ###-#### Inspection requested via web by Scott Campbell underground power feed for pole lights ok cover
|
Electrical Rough-In | 12/10/2015 | 12/11/2015 | 12/11/2015 | A | PASS |
Eric Story
|
|
|
Contact is Derek Ball. Inspection of pole bases prior to pouring same. Phone #: ###-#### Inspection requested via web by Scott Campbell pole base grounding ok to pour
|
Electrical Rough-In | 11/24/2015 | 11/25/2015 | 11/25/2015 | A | PASS |
Eric Story
|
|
|
Contact is Sean Sivesind. Underground conduit inspection Phone #: ###-#### Inspection requested via web by Scott Campbell underground along sidewalk ok cover
|
Electrical Rough-In | 11/9/2015 | 11/10/2015 | 11/10/2015 | A | PASS |
Eric Story
|
|
|
Please make as close to 8:00 AM as possible - for pole base concrete pour. Contact is Derek Ball, ###-#### Phone #: ###-#### Inspection requested via web by Scott Campbell light pole bases ok to pour
|
Electrical Rough-In | 10/26/2015 | 10/27/2015 | 10/27/2015 | A | PASS |
Eric Story
|
|
|
Contact is Derek Ball Phone #: ###-#### Inspection requested via web by Scott Campbell pathway lighting parrell to 1161 building ok cover
|
Electrical Rough-In | 10/23/2015 | 10/27/2015 | 10/26/2015 | P | CANC |
Eric Story
|
|
|
Contact is Derek Ball - conduit rough-in inspection Phone #: ###-#### >> Inspection requested via web by Scott Campbell Inspection cancelled from web by: Scott Campbell
|