Final | 8/4/2016 | 8/4/2016 | 8/4/2016 | P | PASS |
Bob Reichert
|
|
|
ready for a final on the last 11 units, call dean with questions at the number above, thanks Phone #: ###-#### Inspection requested via web by Don Lustig ok final
|
Permanent Service | 5/2/2016 | 5/2/2016 | 5/2/2016 | P | PASS |
Bob Reichert
|
|
|
this is for building 5 ready for service inspection call corey with questions thanks Phone #: ###-#### Inspection requested via web by Don Lustig p/s u/g n ok, 12 meters required
|
Electrical Rough-In | 4/13/2016 | 4/14/2016 | 4/14/2016 | A | PASS |
Bob Reichert
|
|
|
rough in on the remainding units, first one done by Eric on the 8th. Phone #: ###-#### Inspection requested via web by Don Lustig rest of units ok for ri, 6 total west end
|
Electrical Rough-In | 4/8/2016 | 4/8/2016 | 4/8/2016 | P | PASS |
Eric Story
|
|
|
please make a rough in inspection after 2 so corey can walk with you Phone #: ###-#### Inspection requested via web by Don Lustig units 2264,2262,2260,2258,2256 ok cover
|
Permanent Service | 10/28/2015 | 10/29/2015 | 10/29/2015 | A | PASS |
Eric Story
|
|
|
this for a ufer ground on the building 5 which is the one with only foundations. Phone #: ###-#### Inspection requested via web by Don Lustig ufer ok
|