Final | 6/26/2016 | 6/27/2016 | 6/27/2016 | A | PASS |
Bob Reichert
|
|
|
Ready for final for the three end units call with questions thanks Phone #: ###-#### Inspection requested via web by Don Lustig ok final
|
Final | 6/23/2016 | 6/24/2016 | 6/24/2016 | A | PART |
Bob Reichert
|
|
|
i have 6 or 7 out of nine done, i am on site on friday and will be complete on saturday, i was hoping to get the 6 finaled and then if any issues get them fixed. then on monday i will call it in again for the remaining 2 of this building. call me with questions thanks Phone #: ###-#### Inspection requested via web by Don Lustig 6 east units ok, will do last 3 in center section, west side next week
|
Electrical Rough-In | 2/24/2016 | 2/25/2016 | 2/25/2016 | A | CANC |
Bob Reichert
|
|
|
rought in all units building 4 Phone #: ###-#### Inspection requested via web by Don Lustig see rip
|
Rough-In Permanent Service | 2/24/2016 | 2/25/2016 | 2/25/2016 | A | PASS |
Bob Reichert
|
|
|
Phone #: ###-#### Inspection requested via web by Don Lustig ri ok, p/s u/g n ok, 10 meters required
|