Final | 11/16/2015 | 11/17/2015 | 11/17/2015 | P | PASS |
Eric Story
|
|
|
This install was done on a Saturday, so the rough-in inspection for the panel and inverter listing check was not called in. If this is needed for this project you can give me a call a couple hours ahead of your inspection, and I can meet you there to pull a couple panels up.
Otherwise the install was done according to approved plans, with no deviations or product changes. There is a single home run from the array to the knife switch located next to the meter base. And from the knife switch to the exterior sub panel also next to the meter base. The panels, inverters and rails are all bonded with a number six ground that runs unbroken from the array to the visible electrode under the meter base. The service panel, sub panel and knife switch are all exterior, so no inside access will be needed. Thanks guy''s, Ryan King Phone #: ###-#### Inspection requested via web by Ryan King final ok
|
Electrical Rough-In | 11/17/2015 | 11/17/2015 | 11/17/2015 | P | PASS |
Eric Story
|
|
|
This install was done on a Saturday, so the rough-in inspection for the panel and inverter listing check was not called in. If this is needed for this project you can give me a call a couple hours ahead of your inspection, and I can meet you there to pull a couple panels up.
Otherwise the install was done according to approved plans, with no deviations or product changes. There is a single home run from the array to the knife switch located next to the meter base. And from the knife switch to the exterior sub panel also next to the meter base. The panels, inverters and rails are all bonded with a number six ground that runs unbroken from the array to the visible electrode under the meter base. The service panel, sub panel and knife switch are all exterior, so no inside access will be needed. Thanks guy''s, Ryan King Phone #: ###-#### Inspection requested via web by Ryan King rough-in ok
|