Final | 11/1/2016 | 11/2/2016 | 11/2/2016 | A | PASS |
Rock A. Hudson
|
|
|
Call Pierce for final of Clearwater TI floors 4-9. Phone #: ###-#### Inspection requested via web by Rafael Castillo Signed off on floors 4 thru 9 of clearwater paperwork. 4th floor page showed different BLD but labelled clearwater. Final ok
|
Final | 10/21/2016 | 10/21/2016 | 10/21/2016 | A | NR |
Rock A. Hudson
|
|
|
Call Pierce to look at KO''s on light fixtures and fire caulking of around conduit at 7th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo All KOs for luminaires have listed cable connector installed. Unable to final core and shell permit not finaled. Check for all arc flash warning stickers installed and bond all cable trays in server rooms.
|
Conference | 10/17/2016 | 10/18/2016 | 10/18/2016 | A | DONE |
Rock A. Hudson
|
|
|
Call Pierce to discuss sealing of 1/2" knockouts in lighting boxes of Clearwater TI. Phone #: ###-#### Inspection requested via web by Rafael Castillo Pierce provided info on a cable connector to close KO in cover. If listed connector they are OK to use.
|
Final | 9/9/2016 | 9/9/2016 | 9/9/2016 | P | PART |
Rock A. Hudson
|
|
|
Call Pierce for final inspections of furniture. Furniture is last electrical installation, TI electrical installation will be complete. Phone #: ###-#### Inspection requested via web by Rafael Castillo Furniture connections 9th floor. Temp final for 9th ok
|
Electrical Rough-In | 9/7/2016 | 9/7/2016 | 9/7/2016 | P | FAIL |
Rock A. Hudson
|
|
|
Call Pierce for all 9th floor office furniture. Phone #: ###-#### Inspection requested via web by Rafael Castillo 9th floor furniture not complete.
|
Electrical Rough-In | 9/6/2016 | 9/6/2016 | 9/6/2016 | P | PASS |
Mark Moncarr
|
|
|
Call Pierce for inspection of last 2 office furniture rows on 8 and office furniture rows on 9. Phone #: ###-#### Inspection requested via web by Rafael Castillo rows already occupied. Cord ends UL listed as per Pierce. Was able to check a few outlets
|
Electrical Rough-In | 9/2/2016 | 9/2/2016 | 9/2/2016 | P | PASS |
Daryl DeGrange
|
|
|
Call Pierce for inspection of 8th floor furniture. Phone #: ###-#### Inspection requested via web by Rafael Castillo Rough-in ok UL lIsted office furniture, Yellow section drawn on print.
|
Electrical Rough-In | 8/31/2016 | 9/1/2016 | 9/1/2016 | P | PASS |
Eric Story
|
|
|
Call Pierce for inspection of office furniture connections on the 8th floor (partial only for the furniture on the 8th floor, more to come). Phone #: ###-#### Inspection requested via web by Rafael Castillo verified connections and wiring of office furniture(plug testedas well) 8th floor N&W areas noted on print ok,E side still to needs to be finished.
|
Electrical Rough-In | 8/17/2016 | 8/17/2016 | 8/17/2016 | P | PASS |
Rock A. Hudson
|
|
|
Call Rafael for inspection of office furniture on 8th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo furniture ok as noted on contractor prints.
|
Electrical Rough-In | 8/16/2016 | 8/16/2016 | 8/16/2016 | P | PASS |
Rock A. Hudson
|
|
|
Pre-walk inspection for TCO final of 9th and 10th floor. Call Rafael for inspection Phone #: ###-#### Inspection requested via web by Rafael Castillo levels 9-10 TCO ok
|
Electrical Rough-In | 8/15/2016 | 8/15/2016 | 8/15/2016 | P | PASS |
Rock A. Hudson
|
|
|
Call Pierce for ceiling inspection of 9th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo All grid 9th floor rough in ok cover
|
Electrical Rough-In | 8/4/2016 | 8/5/2016 | 8/5/2016 | A | PART |
Rock A. Hudson
|
|
|
Call Rafael for pre-walk final inspection of the 5th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo 400.8- Flexible cord shall not penetrate walls. 300.21- Seal fire wall penetrations. 300.25- all boxes shall have covers. LV boxes. 406.6- Server rm receptacle plates shall seat to mounting surface. Temp final ok
|
Electrical Rough-In | 8/3/2016 | 8/3/2016 | 8/3/2016 | P | PART |
Rock A. Hudson
|
|
|
Call Pierce for pre-walk final of 8th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo TCO of 8th floor 300.15 all boxes shall have covers. LV data, and card readers. 300.21- All electrical penetrations in firewalls shall be sealed with fire resistant materials. check all north side offices noticed. Cover boxes in firewall near N. stair. 110.3- Open neutral LR8D-32 center outlet in eating area off break room. Stair lighting on stair from 8 to 9 not complete. OK to install furniture
|
Conference | 8/2/2016 | 8/2/2016 | 8/2/2016 | P | DONE |
Rock A. Hudson
|
|
|
Sign TCO sheets for 6th and 7th floor that ESI now has set up in a binder as per Dave Hannah''s request. Phone #: ###-#### Inspection requested via web by Rafael Castillo Signed off on floors 6 and 7 in new book provided
|
Electrical Rough-In | 8/2/2016 | 8/2/2016 | 8/2/2016 | P | CANC |
Rock A. Hudson
|
|
|
Call Rafael for pre-walk final of 8th floor. Phone #: ###-#### >> Inspection requested via web by Rafael Castillo Inspection cancelled from web by: Rafael Castillo
|
Electrical Rough-In | 8/1/2016 | 8/2/2016 | 8/2/2016 | A | CANC |
Rock A. Hudson
|
|
|
Pre-walk 8th floor to prepare for final inspection of the floor. Review and sign TCO sign-off sheet for 6th anf 7th floors as per Dave Hannah''s request. Call Rafael for inspection. Phone #: ###-#### >> Inspection requested via web by Rafael Castillo Inspection cancelled from web by: Rafael Castillo
|
Final | 7/29/2016 | 7/29/2016 | 7/29/2016 | P | PART |
Rock A. Hudson
|
|
|
Call Rafael for TCO for floors 6 and 7. Phone #: ###-#### Inspection requested via web by Rafael Castillo temp final for stairways, corridors, egress floors 6 and 7
|
Final | 7/29/2016 | 8/1/2016 | 7/29/2016 | A | CANC |
Rock A. Hudson
|
|
|
Final for floors 6 and 7 only for TCO. Call Rafael for inspection. Phone #: ###-#### >> Inspection requested via web by Rafael Castillo Inspection cancelled from web by: Rafael Castillo
|
Electrical Rough-In | 7/28/2016 | 7/28/2016 | 7/28/2016 | P | PASS |
Rock A. Hudson
|
|
|
Call Pierce for inspection of cabinet wall rough in on 9th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo Millwork rough in ok cover
|
Electrical Rough-In | 7/26/2016 | 7/27/2016 | 7/27/2016 | A | PART |
Rock A. Hudson
|
|
|
Call Pierce for inspection of 8th floor ceiling grid areas and 9th floor reception desk millwork r/i. Phone #: ###-#### Inspection requested via web by Rafael Castillo 9th floor millwork covered prior to inspection remove nad recall. 8th floor office grid rough in ok cover
|
Electrical Rough-In | 7/21/2016 | 7/21/2016 | 7/21/2016 | A | PASS |
Rock A. Hudson
|
|
|
Call Chris for walk through of 7th floor for pre walk final. Phone #: ###-#### Inspection requested via web by Rafael Castillo In server room repair wall around boxes. Checked all receptacles in all rooms. Core and shall areas not ready.
|
Electrical Rough-In | 7/19/2016 | 7/20/2016 | 7/20/2016 | A | PASS |
Rock A. Hudson
|
|
|
R/I inspection for man cave bathroom hard lid and pre walk final for 7th floor. Call Rafael for inspection. Phone #: ###-#### Inspection requested via web by Rafael Castillo 10th floor bath hardlid rough in ok cover
|
Electrical Rough-In | 7/15/2016 | 7/15/2016 | 7/15/2016 | P | PASS |
Rock A. Hudson
|
|
|
Call for r/i inspection of cabinet wall on 8th floor east break room. Phone #: ###-#### Inspection requested via web by Rafael Castillo As noted rough in ok cover
|
Electrical Rough-In | 7/14/2016 | 7/14/2016 | 7/14/2016 | P | PASS |
Rock A. Hudson
|
|
|
Call Rafael for ceiling grid inspection of server room and 7th floor Beta Bar. Look at partial final on 6th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo 7th floor grid noted in book. Pre-walk 6th floor for final. Need to check wiring in fire extinguisher pockets. Vending machine circuits not GFCI, protection should be in cord. Rest ok. Need core and shell final prior to final.
|
Electrical Rough-In | 7/13/2016 | 7/13/2016 | 7/13/2016 | P | PASS |
Rock A. Hudson
|
|
|
7th floor grid ceiling inspection and transformer inspection in penthouse mechanical room. Phone #: ###-#### Inspection requested via web by Rafael Castillo Areas noted in book on 7th and transformer on penthouse level rough in ok cover
|
Electrical Rough-In | 7/8/2016 | 7/8/2016 | 7/8/2016 | A | PASS |
Rock A. Hudson
|
|
|
Call Pierce for r/i inspection of 9th floor soffit. Phone #: ###-#### Inspection requested via web by Rafael Castillo 9th fl conference rm soffit as noted in book rough in ok cover
|
Electrical Rough-In | 7/5/2016 | 7/6/2016 | 7/6/2016 | A | PASS |
Eric Story
|
|
|
Call Pierce to look at transformer wiring on 7th floor before energizing. Phone #: ###-#### Inspection requested via web by Rafael Castillo transformer on 7th floor ok energize
|
Electrical Rough-In | 6/16/2016 | 6/16/2016 | 6/16/2016 | P | PASS |
Rock A. Hudson
|
|
|
Call Pierce for inspection of columns on the 8th floor north end of building. Phone #: ###-#### Inspection requested via web by Rafael Castillo As noted on print and books rough in ok cover
|
Electrical Rough-In | 6/13/2016 | 6/14/2016 | 6/14/2016 | A | PASS |
Rock A. Hudson
|
|
|
Call Pierce for ceiling inspection of 7th floor server room area. Phone #: ###-#### Inspection requested via web by Rafael Castillo 7th floor server room center grid tiles ok to install for equipment.
|
Electrical Rough-In | 6/8/2016 | 6/8/2016 | 6/8/2016 | P | CANC |
Rock A. Hudson
|
|
|
Call Pierce for inspection of 9th floor columns, grid ceilings on 6th floor and grid ceiling on 5th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo As noted in book, walls and grid rough in ok cover
|
Electrical Rough-In | 6/6/2016 | 6/7/2016 | 6/7/2016 | A | PASS |
Rock A. Hudson
|
|
|
R/I of millwork on 6th and 7th floor, R/I of conference room 9th floor, ceiling grid inspection on 6th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo 9th floor conference rm 920, 6th and 7th millwork rough in ok cover. 6th floor grid not ready.
|
Conference | 5/18/2016 | 5/19/2016 | 5/19/2016 | A | DONE |
Rock A. Hudson
|
|
|
Walk through to review project progress. Phone #: ###-#### Inspection requested via web by Rafael Castillo Met and walked 5, 6, 7 to get caught up on jb progress. Still HVAC units with clearence issue at junction box.
|
Electrical Rough-In | 5/17/2016 | 5/17/2016 | 5/17/2016 | P | PASS |
Rock A. Hudson
|
|
|
R/I of walls on 6th floor in NW corner of building, call Joey for inspection. Phone #: ###-#### Inspection requested via web by Rafael Castillo Noted on contractor print and in book in blue. wall rough in ok cover
|
Electrical Rough-In | 5/13/2016 | 5/13/2016 | 5/13/2016 | A | PASS |
Rex Boyles
|
|
|
Inspection of interior and exterior walls in NW corner of 7th floor. Call Joey. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok for above plus wall on 4th floor ok see yellow
|
Electrical Rough-In | 5/10/2016 | 5/11/2016 | 5/11/2016 | A | PASS |
Rex Boyles
|
|
|
Call Joey for R/I inspection of walls on the west end of the 8th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i walls ok
|
Electrical Rough-In | 5/9/2016 | 5/10/2016 | 5/10/2016 | A | PASS |
Rex Boyles
|
|
|
Call Joey for inspection of interior walls on the 9th floor, partial only. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok see green on Lea plans
|
Electrical Rough-In | 5/3/2016 | 5/3/2016 | 5/3/2016 | P | PASS |
Rex Boyles
|
|
|
Call Joey for R/I inspection of 9th floor executive stairwell. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok 9th flr and penthouse stairwells Also discuss with Joey loadcenter in "closet". OK because electrical and associated equipment only
|
Electrical Rough-In | 5/2/2016 | 5/2/2016 | 5/2/2016 | P | CANC |
Rex Boyles
|
|
|
Call Joey for R/I inspection of executive stairwell from 9th floor to executive suite (10th floor). Phone #: ###-#### Inspection requested via web by Rafael Castillo Lea electric guys gone for the day. Missed this inspection. Called Joey and he will reschedule inspection
|
Electrical Rough-In | 4/29/2016 | 4/29/2016 | 4/29/2016 | A | PASS |
Rex Boyles
|
|
|
Call Joey for partial R/I inspection of walls on west end of 9th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok see orange highlighted areas
|
Electrical Rough-In | 4/12/2016 | 4/13/2016 | 4/13/2016 | P | PASS |
Rex Boyles
|
|
|
Contact Joey for inspection of interior walls on east end of 9th floor. 1200pm inspection time would be appreciated. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok including giant ballroom curtain wall e lights at 2 locations see Lea's esheets
|
Electrical Rough-In | 4/8/2016 | 4/11/2016 | 4/11/2016 | A | PASS |
Rex Boyles
|
|
|
Contact Rafael for inspection of 5th floor exterior walls from break area to patio door and along outside patio to GBAD stairwell. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok exterior walls and south walls to relocate wiring as per Rafael
|
Electrical Rough-In | 4/5/2016 | 4/6/2016 | 4/6/2016 | A | PASS |
Rock A. Hudson
|
|
|
Contact Joey for inspection of exterior walls on 8th floor and walls in executive suite (penthouse). Phone #: ###-#### Inspection requested via web by Rafael Castillo Discussed providing an access to a airhandler disconnecting means that will be located on each floorcovered by a wall. Asked that access be around 24" wide to give service personel a visual of area. 8th floor marked in pink exterior wall at southwest corner. 9th floor all perimeter walls only. Penthouse suite on 10th south 1/2 lounge walls. As noted and marked on prints in pink wall rough in ok cover
|
Electrical Rough-In | 3/23/2016 | 3/25/2016 | 3/25/2016 | A | PASS |
Rex Boyles
|
|
|
Interior wall inspections for 6th and 7th floor, west side of building. Call Joey for inspection. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok look for orange area on plans
|
Electrical Rough-In | 3/19/2016 | 3/22/2016 | 3/22/2016 | A | PASS |
Rex Boyles
|
|
|
Call Joey for inspection of hard lids on 6th, 7th, and 8th floor, as well as 7th floor west interior/exterior walls. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok hard lids 6th and 7th floors ONLY
|
Electrical Rough-In | 3/14/2016 | 3/15/2016 | 3/15/2016 | A | PASS |
Rex Boyles
|
|
|
R/I inspection for walls on 7th floor in server room area and 8th floor east to include interior and exterior walls. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i walls ok see blue highlighted areas on ESI binder
|
Electrical Rough-In | 2/29/2016 | 3/1/2016 | 3/1/2016 | A | PASS |
Rex Boyles
|
|
|
R/I inspection for east walls on 7th floor. Contact Joey for inspection. Phone #: ###-#### Inspection requested via web by Rafael Castillo 7th floor walls ok except n. west corner see pink highlighted areas on Leas' plans
|
Electrical Rough-In | 2/25/2016 | 2/25/2016 | 2/25/2016 | A | PASS |
Rex Boyles
|
|
|
R/I inspection for interior walls on east end of 6th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo partial wall r/i ok see Joey"s E1-6 sheets for pink areas only
|
Electrical Rough-In | 2/16/2016 | 2/16/2016 | 2/16/2016 | P | PASS |
Rex Boyles
|
|
|
Call Joey for partial inspection of exterior walls on 6th and 7th floor for cover. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok
|
Electrical Rough-In | 2/2/2016 | 2/3/2016 | 2/3/2016 | A | PASS |
Rex Boyles
|
|
|
Rough in inspection for hard lid area on 5th floor in Clearwater building. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok 5th floor hard lid ceilings in bathroom and showers
|
Electrical Rough-In | 12/16/2015 | 12/16/2015 | 12/16/2015 | P | PASS |
Rex Boyles
|
|
|
Rough-in for walls on 5th floor in shower and beta bar area only. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i walls ok see Rafael's e sheets
|