Final | 1/15/2016 | 1/19/2016 | 1/19/2016 | A | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins Final ok
|
Electrical Rough-In | 1/4/2016 | 1/5/2016 | 1/5/2016 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins North entrance door on left new conference rm and office wall rough in ok cover.
|
Electrical Rough-In | 12/17/2015 | 12/18/2015 | 12/18/2015 | P | PASS |
Rock A. Hudson
|
|
|
ceiling inspection Phone #: ###-#### Inspection requested via web by Bryan Atkins Grid rough in phase 1 rough in ok cover
|
Electrical Rough-In | 12/9/2015 | 12/9/2015 | 12/9/2015 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins Wall rough in ok cover
|