Final | 3/24/2016 | 3/28/2016 | 3/28/2016 | P | PASS |
Rock A. Hudson
|
|
|
We are requesting a final inspection for this project on Monday 3/28/16 in the afternoon. Our contact is Rich @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate Final ok
|
Final | 3/16/2016 | 3/16/2016 | 3/16/2016 | P | CANC |
Rock A. Hudson
|
|
|
would like call ahead; Mike Phone #: ###-#### Contact information from ELE15-03985. Contractor at address on this permit did not request an inspection for today.
|
Electrical Rough-In | 1/29/2016 | 2/1/2016 | 2/1/2016 | P | PASS |
Daryl DeGrange
|
|
|
Request end of day inspection for temporary occupancy electrical final for B8 2nd floor. Phone #: ###-#### Inspection requested via web by Clint Tate Request for temporary occupancy ok
|
Final | 2/1/2016 | 2/1/2016 | 2/1/2016 | P | PART |
Daryl DeGrange
|
|
|
Request end of day inspection for temporary occupancy electrical final for B8 2nd floor. Phone #: ###-#### Inspection requested via web by Clint Tate Partial final- additional pendant lighting back ordered
|
Electrical Rough-In | 1/20/2016 | 1/21/2016 | 1/21/2016 | P | PASS |
Rock A. Hudson
|
|
|
We are requesting a ceiling rough-in inspection for tomorrow 1/21/16 in the afternoon. Our contact is Rich @ ###-####. Thank you, Phone #: ###-#### Inspection requested via web by Clint Tate Grid 2nd floor rough in ok cover
|
Conference | 1/21/2016 | 1/21/2016 | 1/21/2016 | P | DONE |
Rock A. Hudson
|
|
|
Our contact is Rich @ ###-####. Thank you, Phone #: ###-#### NEC 110.26(C)(2)-No clearance required on south side of new equipment due to no accessible panels on south side
|
Conference | 1/6/2016 | 1/6/2016 | 1/6/2016 | P | DONE |
Rock A. Hudson
|
|
|
2nd meeting for addition of transfer switches and generators. 230.2(A)(4)- grouping not required for optional stand by systems, 110.26- panic hardware and door swings to be corrected. All service entrance conductors will satisfy 230.6 with interior trans switch installed over underground service entrance and fused outdoor transfer switch.
|
Conference | 1/5/2016 | 1/6/2016 | 1/6/2016 | A | DONE |
Rock A. Hudson
|
|
|
We are requesting a consult. Our contact is Rich @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate Discussed the relocating of unfused service entrance conductors for the addition of generator and transfer switches. Talked about NEC 230.6 service entrance shall need to remain or need to be considered outside building until fused which shall be encased in minimum of 2" of concrete or run under 18" of earth or other recognized form.
|
Electrical Rough-In | 12/11/2015 | 12/11/2015 | 12/11/2015 | P | PASS |
Rock A. Hudson
|
|
|
We are requesting a wall rough-in inspection for this afternoon. Our contact is Rich @ ###-####. Thank you, Phone #: ###-#### Inspection requested via web by Clint Tate Walls located all over 2nd floor. 2nd floor wall rough in ok cover
|