Final | 6/7/2016 | 6/8/2016 | 6/8/2016 | A | PASS |
Rock A. Hudson
|
|
|
Andy Phone #: ###-#### Final ok
|
Final | 6/1/2016 | 6/2/2016 | 6/2/2016 | A | PART |
Rock A. Hudson
|
|
|
Andy Phone #: ###-#### 2nd floor temp final ok
|
Electrical Rough-In | 4/12/2016 | 4/12/2016 | 4/12/2016 | P | PASS |
Rex Boyles
|
|
|
Andy-Ceiling Phone #: ###-#### r/i tgrid ceilings 100% 2nd floor
|
Electrical Rough-In | 3/30/2016 | 4/1/2016 | 4/1/2016 | A | PASS |
Rock A. Hudson
|
|
|
Andy-ceiling Phone #: ###-#### Grid around sky lights, north offices rough in ok cover
|
Electrical Rough-In | 3/24/2016 | 3/24/2016 | 3/24/2016 | P | PASS |
Rex Boyles
|
|
|
ceiling; Andy Phone #: ###-#### r/i ok 2nd floor t grid north half of large area. Also r/i ok 1st floor hard lid at back entry. Also asked Andy to relocate 2 raceways in 2nd flr server room in front of HVAC vav control box in ceiling to meet 110.26(A)(1) NEC
|
Conference | 3/21/2016 | 3/22/2016 | 3/22/2016 | A | DONE |
Rex Boyles
|
|
|
Alan Phone #: ###-#### discuss change out of existing gear and installing new 120/208 volt 1200 amp main disconnect and distribution in basement. Need to get Fire Marshall ok for main disconnect location. Meet NEC 230.70(A)(1) and 230.6(1)or(2). Main disconnect shall be in a readily accessable location
|
Conference | 3/14/2016 | 3/15/2016 | 3/15/2016 | P | CANC |
Rex Boyles
|
|
|
Andy Phone #: ###-#### needed r/i
|
Electrical Rough-In | 3/15/2016 | 3/15/2016 | 3/15/2016 | P | PASS |
Rex Boyles
|
|
|
Andy Phone #: ###-#### r/i tgrid ceilings south half from soffit ok
|
Electrical Rough-In | 3/11/2016 | 3/11/2016 | 3/11/2016 | P | PASS |
Bob Reichert
|
|
|
Andy Phone #: ###-#### east entry soffit ok cover
|
Electrical Rough-In | 2/24/2016 | 2/25/2016 | 2/25/2016 | A | PASS |
Eric Story
|
|
|
Andy Phone #: ###-#### entry receptacles and 4-gang and 2nd floor floor receptaces ok cover
|
Electrical Rough-In | 2/4/2016 | 2/4/2016 | 2/4/2016 | P | PASS |
Bob Reichert
|
|
|
Andy Phone #: ###-#### walls only ok cover
|