Final | 7/14/2016 | 7/15/2016 | 7/15/2016 | A | PASS |
Bob Reichert
|
|
|
Phone #: ###-#### Inspection requested via web by Karl Paige ok final, signed card
|
Electrical Rough-In | 7/11/2016 | 7/11/2016 | 7/11/2016 | P | CANC |
Bob Reichert
|
|
|
part final area 1 and 2. Areas 3 and 4 end of week for total final Phone #: ###-#### Inspection requested via web by Karl Paige see part final
|
Final | 7/11/2016 | 7/11/2016 | 7/11/2016 | P | PART |
Bob Reichert
|
|
|
part final area 1 and 2. Areas 3 and 4 end of week for total final Phone #: ###-#### Inspection requested via web by Karl Paige part final for area 1 and 2 ok, no card signed yet
|
Electrical Rough-In | 6/22/2016 | 6/22/2016 | 6/22/2016 | P | PASS |
Bob Reichert
|
|
|
ceiling cover area 4 Phone #: ###-#### Inspection requested via web by Karl Paige ok cover ceilings, area 4
|
Electrical Rough-In | 6/13/2016 | 6/13/2016 | 6/13/2016 | A | PASS |
Bob Reichert
|
|
|
ceiling cover area 3 Phone #: ###-#### Inspection requested via web by Karl Paige ok cover ceiling area 3
|
Electrical Rough-In | 6/2/2016 | 6/3/2016 | 6/3/2016 | A | PASS |
Daryl DeGrange
|
|
|
CEILING COVER AREA 2 Phone #: ###-#### Inspection requested via web by Karl Paige rough-in ok cover area 2 ceiling grid
|
Electrical Rough-In | 5/26/2016 | 5/27/2016 | 5/27/2016 | A | PASS |
Bob Reichert
|
|
|
grid ceiling cover area 1 Phone #: ###-#### Inspection requested via web by Karl Paige ok cover phase 1 ceiling
|
Electrical Rough-In | 5/15/2016 | 5/16/2016 | 5/16/2016 | A | PASS |
Bob Reichert
|
|
|
Bathroom hard lid area 4 Phone #: ###-#### Inspection requested via web by Karl Paige hard lids as requested ok cover
|
Electrical Rough-In | 5/3/2016 | 5/4/2016 | 5/4/2016 | A | PASS |
Bob Reichert
|
|
|
ceiling cover Phone #: ###-#### Inspection requested via web by Karl Paige ok cover hard lids in baths
|
Electrical Rough-In | 4/25/2016 | 4/25/2016 | 4/25/2016 | P | PASS |
Bob Reichert
|
|
|
area two bathroom ceiling cover Phone #: ###-#### Inspection requested via web by Karl Paige ok cover area 2 bath ceilings
|
Electrical Rough-In | 4/8/2016 | 4/8/2016 | 4/8/2016 | P | PASS |
Eric Story
|
|
|
Ceiling cover area 3 bathroom Phone #: ###-#### Inspection requested via web by Karl Paige area 3 boys and girls bathrooms hard lid cielings ok cover
|
Electrical Rough-In | 4/5/2016 | 4/6/2016 | 4/6/2016 | P | PASS |
Bob Reichert
|
|
|
wall cover area 4 - Karl Phone #: ###-#### ok cover walls only, area 4
|
Electrical Rough-In | 3/15/2016 | 3/16/2016 | 3/16/2016 | A | PASS |
Daryl DeGrange
|
|
|
wall cover area 2 Phone #: ###-#### Inspection requested via web by Karl Paige rough-in ok cover walls in 4 classroom with library and SW corridor soffit
|
Electrical Rough-In | 3/2/2016 | 3/2/2016 | 3/2/2016 | P | PASS |
Bob Reichert
|
|
|
AREA 3, NORTH WEST CORNER FOR A COVER INSPECTION AND THE WALL IN AREA 1 SOUTH EAST CORNER THAT WAS NOT BUILT LAST INSPECTION Phone #: ###-#### Inspection requested via web by Karl Paige ok cver area requested
|
Electrical Rough-In | 2/22/2016 | 2/23/2016 | 2/23/2016 | P | PASS |
Bob Reichert
|
|
|
south east side (phase 1) wall cover Phone #: ###-#### Inspection requested via web by Karl Paige ok cover walls only se part bldg
|