Final | 6/27/2016 | 6/27/2016 | 6/27/2016 | P | PASS |
Rock A. Hudson
|
|
|
Early afternoon if possible please Phone #: ###-#### Inspection requested via web by Kerri Hamilton All flexible cord assemblies for desks have been removed and a seperate permit required for any additional installations. Final ok
|
Final | 6/23/2016 | 6/24/2016 | 6/24/2016 | A | PART |
Rock A. Hudson
|
|
|
Early AM for 1st Floor Phone #: ###-#### Inspection requested via web by Kerri Hamilton Temp Final ok (This activity was added in error so we have changed the case status back to Issued.) 605.9- Flexible cords feeding furniture shall have max length of 2', shall be 12ga min and shall not have more than 13 15 amp receptacles
|
Electrical Rough-In | 6/21/2016 | 6/22/2016 | 6/22/2016 | A | PASS |
Rock A. Hudson
|
|
|
Partial Final ; Ceiling Late am if posible please Phone #: ###-#### Inspection requested via web by Kerri Hamilton Partial final not ready. 1st floor grid complete, transformers done, GFCI in place. As noted rough in ok cover
|
Electrical Rough-In | 6/21/2016 | 6/21/2016 | 6/21/2016 | P | PASS |
Rock A. Hudson
|
|
|
Basement ; Formers Phone #: ###-#### Inspection requested via web by Kerri Hamilton Basement GFCI 6' sink, 1st transformers, museum grid, Listed furniture. Basement final ok
|
Electrical Rough-In | 6/20/2016 | 6/20/2016 | 6/20/2016 | P | PASS |
Rock A. Hudson
|
|
|
Final for 2nd ; 3rd Floor Phone #: ###-#### Inspection requested via web by Kerri Hamilton Still to complete 4th floor transformers, 1st floor, basement and penthouse. Rest complete temp final for 2, 3, 5, 6.
|
Electrical Rough-In | 6/16/2016 | 6/16/2016 | 6/16/2016 | P | PASS |
Rock A. Hudson
|
|
|
1st Floor Ceiling Phone #: ###-#### Inspection requested via web by Kerri Hamilton Break rom, conference rms, museum yet to do. West conference, S.E. reception areas grid rough in ok cover
|
Electrical Rough-In | 6/14/2016 | 6/15/2016 | 6/15/2016 | A | PASS |
Rock A. Hudson
|
|
|
Ceiling Phone #: ###-#### Inspection requested via web by Kerri Hamilton All room on N.E. side of main corridor grid rough in ok cover
|
Electrical Rough-In | 6/2/2016 | 6/3/2016 | 6/3/2016 | P | PASS |
Rock A. Hudson
|
|
|
2nd Floor Ceiling Phone #: ###-#### Inspection requested via web by Kerri Hamilton 2nd floor grid rough in ok cover
|
Final | 5/26/2016 | 5/27/2016 | 5/27/2016 | A | FAIL |
Rock A. Hudson
|
|
|
###-#### 3rd or 4th floor prewalk final Lighting not working in 1 large room on 3 and 1 on 4. All electrical rooms to be checked in future and will check lighting then.
|
Final | 5/26/2016 | 5/26/2016 | 5/26/2016 | P | CANC |
Rock A. Hudson
|
|
|
Partial Final - Walk thru 3rd and 4th floor Phone #: ###-#### Inspection requested via web by Kerri Hamilton Rescheduled
|
Electrical Rough-In | 5/26/2016 | 5/26/2016 | 5/26/2016 | P | PASS |
Rock A. Hudson
|
|
|
Basement Ceiling Phone #: ###-#### Inspection requested via web by Kerri Hamilton Basement grid rough in ok cover. 2 room not accessible to to secure areas will check in future.
|
Electrical Rough-In | 5/25/2016 | 5/25/2016 | 5/25/2016 | P | FAIL |
Rock A. Hudson
|
|
|
Ceiling Late pm if possible please Phone #: ###-#### Inspection requested via web by Kerri Hamilton Addressed existing conduits and boxes, All conduits supported by wires shall be secured at top and bottom. Too many open boxes in perimeter rooms. Will check on existing low voltage cable in plenum rated ceiling. Bond required on cable tray
|
Final | 5/19/2016 | 5/19/2016 | 5/19/2016 | P | NR |
Rock A. Hudson
|
|
|
Partial - Floors 5 ; 6 Only Roger Bachman Phone #: ###-#### Inspection requested via web by Kerri Hamilton Pre walk to cover most of floors noted. Bath outlet not GFCI protected, 5th floor electrical rm ground listed splice needed. 4 sq cover and ko seal. furniture on sight will be wired rest to be covered under seperate permit.
|
Electrical Rough-In | 5/9/2016 | 5/9/2016 | 5/9/2016 | P | PASS |
Eric Story
|
|
|
1st Floor hard lid cover Phone #: ###-#### Inspection requested via web by Kerri Hamilton 1st floor hard lid corridors and bath walls and cielings ok cover
|
Electrical Rough-In | 5/4/2016 | 5/4/2016 | 5/4/2016 | P | PASS |
Eric Story
|
|
|
3rd floor ceiling Phone #: ###-#### Inspection requested via web by Kerri Hamilton 3rd floor cielings ok cover
|
Electrical Rough-In | 4/25/2016 | 4/25/2016 | 4/25/2016 | P | PASS |
Eric Story
|
|
|
Basement Walls Phone #: ###-#### Inspection requested via web by Kerri Hamilton 6 th floor remaining office walls excluding bathrooms ok cover
|
Electrical Rough-In | 4/22/2016 | 4/22/2016 | 4/22/2016 | P | PASS |
Eric Story
|
|
|
Roger Phone #: ###-#### Inspection requested via web by Kerri Hamilton as noted on green sticker areas walls only ok cover
|
Electrical Rough-In | 4/6/2016 | 4/7/2016 | 4/7/2016 | A | NR |
Daryl DeGrange
|
|
|
Ceiling Cover 6th Floor Phone #: ###-#### Inspection requested via web by Kerri Hamilton Not ready at this time
|
Final | 4/7/2016 | 4/7/2016 | 4/7/2016 | A | PASS |
Daryl DeGrange
|
|
|
Ceiling Cover 5th Floor Phone #: ###-#### Inspection requested via web by Kerri Hamilton rough-in ok cover 5th floor ceiling grid
|
Electrical Rough-In | 4/6/2016 | 4/6/2016 | 4/6/2016 | P | NR |
Eric Story
|
|
|
Ceiling Cover 6th Floor Phone #: ###-#### Inspection requested via web by Kerri Hamilton not ready still needs to support fixture wires through out
|
Electrical Rough-In | 4/4/2016 | 4/4/2016 | 4/4/2016 | P | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton 2nd floor hard lid cielings in corridor ok cover
|
Electrical Rough-In | 3/28/2016 | 3/29/2016 | 3/28/2016 | A | PASS |
Eric Story
|
|
|
KIP YERTON Phone #: ###-#### Inspection requested via web by Kerri Hamilton 2nd floor walls only ok cover
|
Electrical Rough-In | 3/28/2016 | 3/29/2016 | 3/28/2016 | P | CANC |
Eric Story
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kerri Hamilton Inspection cancelled from web by: Kerri Hamilton
|
Electrical Rough-In | 3/25/2016 | 3/28/2016 | 3/27/2016 | A | PASS |
Daryl DeGrange
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton rough-in ok cover 6th floor ceiling grid
|
Electrical Rough-In | 3/18/2016 | 3/21/2016 | 3/21/2016 | A | PASS |
Bob Reichert
|
|
|
Roger Bachman Phone #: ###-#### Inspection requested via web by Kerri Hamilton 3rd floor corridor and west wall break room ok cover
|
Electrical Rough-In | 3/10/2016 | 3/11/2016 | 3/11/2016 | P | PASS |
Eric Story
|
|
|
Roger Bachman Phone #: ###-#### Inspection requested via web by Kerri Hamilton 3rd floor walls only ok cover
|
Electrical Rough-In | 3/8/2016 | 3/9/2016 | 3/9/2016 | P | PASS |
Eric Story
|
|
|
Cover Phone #: ###-#### Inspection requested via web by Kerri Hamilton 4th floor cielings ok cover
|
Electrical Rough-In | 3/7/2016 | 3/8/2016 | 3/8/2016 | P | PASS |
Bob Reichert
|
|
|
Wall/Ceiling Cover Roger Bachman Phone #: ###-#### Inspection requested via web by Kerri Hamilton 4th floor bath, lids, walls as noted on green card ok cover
|
Electrical Rough-In | 3/2/2016 | 3/3/2016 | 3/3/2016 | A | PASS |
Eric Story
|
|
|
Rough-in 4th floor Phone #: ###-#### Inspection requested via web by Kerri Hamilton 4th floor main offices and breakroom walls only ok cover, discussed with contractor and GC no one siding allowed.
|
Electrical Rough-In | 3/1/2016 | 3/2/2016 | 3/2/2016 | A | CANC |
Eric Story
|
|
|
4th Floor rough-in Phone #: ###-#### >> Inspection requested via web by Kerri Hamilton Inspection cancelled from web by: Kerri Hamilton
|
Electrical Rough-In | 2/25/2016 | 2/26/2016 | 2/26/2016 | A | PASS |
Eric Story
|
|
|
5th Floor Cover Phone #: ###-#### Inspection requested via web by Kerri Hamilton 5th floor remaining walls and hard lid cielings ok cover
|
Electrical Rough-In | 2/17/2016 | 2/18/2016 | 2/18/2016 | A | PASS |
Eric Story
|
|
|
Roger Bachman Phone #: ###-#### Inspection requested via web by Kerri Hamilton 5th floor walls and 6th floor hard lids in corrider and halls ok cover
|
Electrical Rough-In | 2/17/2016 | 2/18/2016 | 2/17/2016 | P | CANC |
Eric Story
|
|
|
Roger Bachman Phone #: ###-#### >> Inspection requested via web by Kerri Hamilton Inspection cancelled from web by: Kerri Hamilton
|
Electrical Rough-In | 2/10/2016 | 2/11/2016 | 2/11/2016 | P | PASS |
Eric Story
|
|
|
Roger Bachman Phone #: ###-#### Inspection requested via web by Kerri Hamilton 6th floor baths firred out wall and breakroom ok cover
|
Electrical Rough-In | 2/3/2016 | 2/4/2016 | 2/4/2016 | P | PASS |
Eric Story
|
|
|
Roger Bachman Phone #: ###-#### Inspection requested via web by Kerri Hamilton discussed one siding of walls ok/ walls only 6th floor ok cover
|