Final | 5/6/2016 | 5/6/2016 | 5/6/2016 | P | PASS |
Rex Boyles
|
|
|
Phone #: ###-#### Inspection requested via web by Ben Archibald final ok
|
Electrical Rough-In | 4/28/2016 | 4/28/2016 | 4/28/2016 | P | PASS |
Rex Boyles
|
|
|
Ceiling inspection Phone #: ###-#### Inspection requested via web by Ben Archibald t grid ceilings ok will need to see gutter above rear ceiling at final insp. Told Ben to add more showwindow receptacles and circuits and no receptacles above t grid
|
Rough-In Permanent Service | 3/29/2016 | 3/29/2016 | 3/29/2016 | P | PASS |
Rex Boyles
|
|
|
Rough-in inspection on hard lid areas. Phone #: ###-#### Inspection requested via web by Ben Archibald r/i hardlids in bathrooms and entry ok. p/s u/g n ok (will look for available fault current plaque at final)
|
Rough-In Permanent Service | 3/24/2016 | 3/24/2016 | 3/24/2016 | P | NR |
Bob Reichert
|
|
|
Phone #: ###-#### Inspection requested via web by Ben Archibald service not ready
|
Electrical Rough-In | 3/24/2016 | 3/24/2016 | 3/24/2016 | P | PASS |
Bob Reichert
|
|
|
Phone #: ###-#### Inspection requested via web by Ben Archibald walls only ok cover
|
Electrical Rough-In | 2/19/2016 | 2/19/2016 | 2/19/2016 | P | PASS |
Rex Boyles
|
|
|
Building underground inspection Phone #: ###-#### Inspection requested via web by Ben Archibald r/i underslab raceways ok
|
Electrical Rough-In | 2/17/2016 | 2/17/2016 | 2/17/2016 | P | PASS |
Rex Boyles
|
|
|
Pole light base inspection Phone #: ###-#### Inspection requested via web by Ben Archibald r/i 5 pole bases ok to pour
|
Electrical Rough-In | 2/16/2016 | 2/16/2016 | 2/16/2016 | P | PASS |
Rex Boyles
|
|
|
Underground inspection Phone #: ###-#### Inspection requested via web by Ben Archibald u. ground racways to light poles and secondaries ok to cover
|
Electrical Rough-In | 2/9/2016 | 2/9/2016 | 2/9/2016 | P | PASS |
Bob Reichert
|
|
|
Need to look at upher ground. Phone #: ###-#### Inspection requested via web by Ben Archibald ok cover concrete encased electrode
|