Final | 4/14/2016 | 4/15/2016 | 4/15/2016 | A | PASS |
Rex Boyles
|
|
|
We are requesting a final inspection for tomorrow morning. Our contact is Bryant @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate final ok
|
Electrical Rough-In | 4/11/2016 | 4/12/2016 | 4/12/2016 | A | PASS |
Rex Boyles
|
|
|
We are requesting an above ceiling inspection for tomorrow 4/12/16 in the morning. Our contact is Bryant @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate r/i ok kitchen t grid ceilings
|
Electrical Rough-In | 4/11/2016 | 4/11/2016 | 4/11/2016 | P | PASS |
Eric Story
|
|
|
We are requesting a new service inspection for this afternoon. Our contact is Bryant @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate meter pack added to existing service ok. p/s u/g rec ok 1 three phase meter
|
Electrical Rough-In | 2/17/2016 | 2/18/2016 | 2/18/2016 | A | PASS |
Rex Boyles
|
|
|
We are requesting a wall rough-in inspection for tomorrow in the AM. Our contact is Bryant @ ###-####. Thank you, Phone #: ###-#### Inspection requested via web by Clint Tate r/i walls ok 1st floor
|