Final | 2/28/2018 | 2/28/2018 | 2/28/2018 | P | PASS |
Rock A. Hudson
|
|
|
All complete, signed off in office. Final ok
|
Final | 2/26/2018 | 2/27/2018 | 2/27/2018 | A | PART |
Rock A. Hudson
|
|
|
2nd level Mezzanine heat tape final Contact Bob Mott Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek 210.63- Service receptacle required east garage with in 25' of mini split. Mezz heat tape, work clearance for panels located in 217 OK
|
Final | 2/26/2018 | 2/26/2018 | 2/26/2018 | P | PART |
Rock A. Hudson
|
|
|
Roof strapping complete, Check heat tape EPD and service receptacle for mini splits garage. Work clearences 217.
|
Final | 2/1/2018 | 2/2/2018 | 2/2/2018 | A | PART |
Rock A. Hudson
|
|
|
Level 3 Rooms 301-322 (no Rm #303 and #321 community room not ready) Contact Bob Mott Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek Notes listed are covered by ELE16-03931. Signed TCO for rest of parking garage. Island will be removed or relocated due to tight rurn radius entering garage.
|
Final | 1/30/2018 | 1/31/2018 | 1/31/2018 | A | PART |
Rock A. Hudson
|
|
|
Final on Trash recycle 112, mezzanine M06, Mechanical M07, utility 212, storage 214, electrical 217 Phone #: ###-#### Inspection requested via web by Cathy Duchek Complete labels for HVAC units o mezz. Areas noted signed off in office. TCO ok
|
Conference | 1/31/2018 | 1/31/2018 | 1/31/2018 | P | DONE |
Rock A. Hudson
|
|
|
Completion list to 1-31-18- ELE16-00580 Podium permit- 112A trash/ recycle, 113 water/fire, 114 bike parking, 115 generator room, 214 storage, 217 electrical, M06, M07, heat trace, perimeter egress ok, liveworks units are painting stage, Pay island is going to be removed and relocated, wiring to be removed. Wiring exposed as of 1-31-18. Informed wiring shall be removed to maintain TCO.
|
Final | 1/11/2018 | 1/12/2018 | 1/12/2018 | A | PART |
Rock A. Hudson
|
|
|
space 113 fire riser room, 114 bike parking, 115 generator Phone #: ###-#### Inspection requested via web by Cathy Duchek Rooms noted siged off in office. Temp final ok
|
Permanent Service | 1/4/2018 | 1/4/2018 | 1/4/2018 | A | PASS |
Daryl DeGrange
|
|
|
Street lighting control cabinet, p/s u/g n ok
|
Final | 12/20/2017 | 12/20/2017 | 12/20/2017 | P | PART |
Daryl DeGrange
|
|
|
Temporary occupancy of the first 1 1/2 floors of garage Phone #: ###-#### Inspection requested via web by Cathy Duchek Phase one TCO Parking Garage, Partial Final ok
|
Electrical Rough-In | 8/15/2017 | 8/15/2017 | 8/15/2017 | P | PASS |
Rock A. Hudson
|
|
|
walls- 115 generator, 113 water-fire, 114 bikeparking, 214 storage, electrical 217 Phone #: ###-#### Inspection requested via web by Cathy Duchek Rooms noted walls only rough in ok cover
|
Electrical Rough-In | 7/24/2017 | 7/24/2017 | 7/24/2017 | P | PASS |
Rock A. Hudson
|
|
|
mci feeders in garage going in shaft wall Phone #: ###-#### Inspection requested via web by Cathy Duchek Vertical shafts in garage for feeders rough in ok cover
|
Electrical Rough-In | 5/9/2017 | 5/10/2017 | 5/10/2017 | P | PASS |
Rock A. Hudson
|
|
|
rough-in walls in mezzanine M06 Phone #: ###-#### Inspection requested via web by Cathy Duchek Wall rough in ok cover
|
Electrical Rough-In | 4/10/2017 | 4/10/2017 | 4/10/2017 | A | PASS |
Rock A. Hudson
|
|
|
Ceiling inspection in garage area level 1 ; 2. Call Lonny when on site. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Area noted 1,2 garage ceilings and heat trace. Rough in ok to insulate.
|
Electrical Rough-In | 4/10/2017 | 4/10/2017 | 4/10/2017 | P | FAIL |
Rock A. Hudson
|
|
|
Ceiling inspection in garage area level 1 ; 2. Call Lonny when on site. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Level 2 electrical room 212, brace for duct work in work space minimum for panels in room. 110.26- Minimum clear work space for voltage present is 30" wide, 36" deep, from floor to height of 6 1/2'. Heat trace covered by this permit is roof and main water and drains. Fire sprinkler pipes heat trace installation said to be done by others, permit and licensing required.
|
Permanent Service | 10/6/2016 | 10/10/2016 | 10/10/2016 | A | PASS |
Eric Story
|
|
|
Available Arc Flash Current Report in hand. The Fowler Contact Lonny Baum Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek p/s u/g n ok
|
Permanent Service | 10/5/2016 | 10/6/2016 | 10/6/2016 | A | FAIL |
Eric Story
|
|
|
The Fowler Contact Lonny Baum Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek Avaliable fault current needed Main bonding jumper shall be upsized as per 250.66
|
Electrical Rough-In | 5/4/2016 | 5/5/2016 | 5/5/2016 | A | PASS |
Rex Boyles
|
|
|
1st floor and Mez conduit rough-in PT slab. Call Lonny with any questions. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum r/i ok 1st floor and mezz slab on deck conduits and boxes for garage lights. Also u. ground conduits to generator, fire pump and live/work conduits running north on east side of bldg. See Lonny's A sheets highlighted
|
Rough-In Permanent Service | 3/9/2016 | 3/9/2016 | 3/9/2016 | P | CANC |
Rex Boyles
|
|
|
UFER inspection for permanent service and fire pump service. Call Lonny for any questions. Thanks Phone #: ###-#### Inspection requested via web by Lonny Baum just needed r/i
|
Electrical Rough-In | 3/9/2016 | 3/9/2016 | 3/9/2016 | P | PASS |
Rex Boyles
|
|
|
UFER inspection for permanent service and fire pump service. Call Lonny for any questions. Thanks Phone #: ###-#### Inspection requested via web by Lonny Baum r/i ok concrete encased electrode for MSBs and fire pump controller
|
Electrical Rough-In | 3/2/2016 | 3/3/2016 | 3/3/2016 | P | PASS |
Rex Boyles
|
|
|
Under ground inspection on main feeder conduits at garage level. Call Lonny with any questions, thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum r/i ok partial secondaries on north half. Also discuss fire pump again. Waiting for Idaho POwer to ok CT meter mounted directly to ransformer OR ct enclosure mounted inside fire pump room??
|
Conference | 3/1/2016 | 3/1/2016 | 3/1/2016 | P | DONE |
Rex Boyles
|
|
|
Need to review options for fire pump. Thanks, Lonny Phone #: ###-#### Inspection requested via web by Lonny Baum discuss NEC article 695 on fire pump installation. Also ask Tom th super to get inspections prior to cover ex:1 siding drywall . Lonny will get back to us on his plan for fire pump
|
Conference | 2/27/2016 | 2/29/2016 | 2/29/2016 | A | DONE |
Daryl DeGrange
|
|
|
Would like a conference to go over site specifics of job inspections. Thanks, Lonny Phone #: ###-#### Inspection requested via web by Lonny Baum Discussed service conductors inside and outside building structure for uitlity and fire pump power.
|