Final | 5/12/2016 | 5/13/2016 | 5/13/2016 | A | PASS |
Rex Boyles
|
|
|
Bud-would like between 1 & 2 Phone #: ###-#### final ok
|
Electrical Rough-In | 5/3/2016 | 5/3/2016 | 5/3/2016 | P | PASS |
Rex Boyles
|
|
|
Bud Phone #: ###-#### r/i garage ok
|
Permanent Service | 5/3/2016 | 5/3/2016 | 5/3/2016 | P | PASS |
Rex Boyles
|
|
|
Bud Phone #: ###-#### p/s o/h n ok relocate drop to garage main panel
|
Electrical Rough-In | 4/20/2016 | 4/22/2016 | 4/22/2016 | P | FAIL |
Rex Boyles
|
|
|
Patricia Phone #: ###-#### change out 2" LB condulet to a factory 90 elbow for service entrance conductors. Install tie off point for service drop. Make up all ground wires in branch circuitry leaving at least 6" free conductors in each box. Install mud ring over rebar for concrete encased electrode access.
|
Electrical Rough-In | 3/31/2016 | 3/31/2016 | 3/31/2016 | P | PASS |
Rex Boyles
|
|
|
underground; Teresa Phone #: ###-#### u.ground to house from garage ok
|
Conference | 3/21/2016 | 3/22/2016 | 3/22/2016 | A | DONE |
Rex Boyles
|
|
|
Bud Phone #: ###-#### discuss new detached garage with new 200 amp service and 200 amp sub feed to house. Go over trench depth, grounding, separation of grounded conductor at house sub panel and garage wiring and service entrance requirments
|