Final | 6/27/2016 | 6/28/2016 | 6/28/2016 | P | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton final ok
|
Electrical Rough-In | 6/27/2016 | 6/27/2016 | 6/27/2016 | P | PASS |
Eric Story
|
|
|
Ceiling Phone #: ###-#### Inspection requested via web by Kerri Hamilton Cieling only ok cover
|
Electrical Rough-In | 6/13/2016 | 6/14/2016 | 6/14/2016 | A | PASS |
Rock A. Hudson
|
|
|
Dan ###-#### phase 2 CT wall rough in ok cover
|
Electrical Rough-In | 6/13/2016 | 6/13/2016 | 6/13/2016 | P | CANC |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Contact called and asked to move inspection to Tuesday AM.
|
Electrical Rough-In | 6/13/2016 | 6/14/2016 | 6/13/2016 | A | CANC |
Rock A. Hudson
|
|
|
Dan ###-####
|
Final | 5/12/2016 | 5/13/2016 | 5/13/2016 | A | PART |
Rex Boyles
|
|
|
Dan Hommel Phone #: ###-#### Inspection requested via web by Kerri Hamilton partial final ok for CT room, CT control room and CT holding room. Not including x ray equip. and ceiling work completion to holding room. Dan will check for open ground to a couple receptacles
|
Electrical Rough-In | 5/10/2016 | 5/11/2016 | 5/11/2016 | A | PASS |
Rex Boyles
|
|
|
Dan Ceiling Phone #: ###-#### Inspection requested via web by Kerri Hamilton r/i ceilings ok in CT control room, CT room and room with wall being removed at a later time.
|
Electrical Rough-In | 3/22/2016 | 3/22/2016 | 3/22/2016 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Work room and break room to be done later. CT-3 wall and hard soffit rough in ok cover
|