DOC - Permit Expired | 2/12/2019 | 2/12/2019 | 2/12/2019 | P | PASS |
Daryl DeGrange
|
|
|
No activity within 180 days. This permit is EXPIRED. A new permit is required to complete this job.
|
Final | 8/16/2016 | 8/17/2016 | 8/17/2016 | A | NR |
Rock A. Hudson
|
|
|
Michael (Betty''s son) Phone #: ###-#### Main service ok, garage wiring yet to be done. Owner to add garage to existing permit. Notified homeowner about this process.
|
ELE-Request for Extension | 8/17/2016 | 8/17/2016 | 8/17/2016 | P | PASS |
Rock A. Hudson
|
|
|
Michael (Betty''s son) Phone #: ###-#### Existing garage burned. New panel in garage to be wired in the future. Underground ok
|
Final | 4/26/2016 | 4/26/2016 | 4/26/2016 | P | CANC |
Rex Boyles
|
|
|
Michael Phone #: ###-####-please call to meet needed r/i p/s
|
Rough-In Permanent Service | 4/26/2016 | 4/26/2016 | 4/26/2016 | P | PASS |
Rex Boyles
|
|
|
Michael Phone #: ###-####-please call to meet r/i ok u. ground conduit to garage and 2" to pull box on house ok to cover. Told michael to upsize all conductors for de rating in 2" conduit ,added 3rd ground rod due to cutting off of 2nd rod, bond bushing installed in meterbase. Will look for intersysytem bond at final p/s o/h rec ok
|
Final | 4/21/2016 | 4/25/2016 | 4/25/2016 | P | NR |
Bob Reichert
|
|
|
Micheal Phone #: ###-#### really wants p/s but did not buy grounding electrode conductor, bond bushings, weather-head, riser, conductors, burned pvc badly with torch, cut off about 1 foot of ground rod, told to finish and call for p/s
|
Conference | 4/1/2016 | 4/5/2016 | 4/5/2016 | P | DONE |
Rex Boyles
|
|
|
Michael Phone #: ###-#### discuss best location for new electrical service to meet idaho power and NEC requirments now that he verified gas meter requirments with intermounain gas co. also
|
Conference | 3/30/2016 | 3/31/2016 | 3/31/2016 | A | DONE |
Rex Boyles
|
|
|
Mikeal Phone #: ###-#### please call 30 minutes prior for access discuss service upgrade, ground rods, riser requirments, clearances from gas meter not good at this time.Micheal lookin into it prior to making a decision on new meter location
|