Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberELE16-01062
StatusFinaled
Name ENTERPRISE ELECTRIC
Site Address 11311 W CHINDEN BLVD
Project Name 
Customer Number 
ePlanReviewNo
Description
Alteration: underground feeders from generator to new switchgear lineup. Remove existing 8-480A main and install new 3000A ATS in its place. Intercept UG feed to 8-480B at transformer and re-route to new outdoor Main Breaker
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final10/27/201610/28/201610/28/2016PPASS
DetailsJames Ady
We are requesting a final inspection for this project tomorrow afternoon. Our onsite contact is Matt @ ###-####. Thank you Phone #: ###-#### Inspection requested via web by Clint Tate Final ok
Electrical Rough-In8/25/20168/29/20168/29/2016ADONE
DetailsEric Story
We are requesting a rough-in inspection for Monday August 29th in the morning. Our onsite contact is Rich @ ###-####. Thank you,
Phone #: ###-#### Inspection requested via web by Clint Tate
Verified Ground Fault performance testing. Will still have to run generator once all parts arrive.
Permanent Service8/23/20168/25/20168/25/2016PPART
DetailsEric Story
We are requesting a service inspection for Thursday Aug. 25th in the afternoon for this project. Our contact is Rich @ ###-####. Thank you, Phone #: ###-#### Inspection requested via web by Clint Tate
Transfer for shut down ok, will need to verify conductors being landed and bonded and ground fault protection testing.
Temporary Service5/24/20165/26/20165/26/2016ACANC
DetailsEric Story
We are requesting a temp. occupancy final for this project for Thursday May 26th in the morning. Our contact is Rich @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate
called wrong permit #
Electrical Rough-In5/17/20165/17/20165/17/2016PCANC
DetailsRock A. Hudson
We are requesting a wall rough-in inspection for this afternoon. Our contact is Rich @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate
This permit for generator and epuipment related.
Conference5/17/20165/17/20165/17/2016PDONE
DetailsRock A. Hudson
We are requesting a wall rough-in inspection for this afternoon. Our contact is Rich @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate
Do to a change in gear required to complete install area created behind west gear which could entrap someone if fault occured. Contractor to install door on west side of gear and install panic hardware on all doors and all doors shall open out of electrical room new and existing. Other conference notes about generator and gear on permit number ELE15-03984.
Electrical Rough-In5/12/20165/12/20165/12/2016PPASS
DetailsJames Ady
We are requesting a wall rough-in inspection for this project for this afternoon. Our contact is Rich @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate
Underground for generator/ no wall ok to cover