Final | 8/29/2016 | 8/29/2016 | 8/29/2016 | A | PASS |
Mark Moncarr
|
|
|
Final inspection Phone #: ###-#### Inspection requested via web by Daniel Gamboa final ok
|
Electrical Rough-In | 7/25/2016 | 7/26/2016 | 7/26/2016 | A | PASS |
Eric Story
|
|
|
THIS IS FOR CEILING INSPECTION, WANT TO INSTALL TILES. Phone #: ###-#### Inspection requested via web by Daniel Gamboa ceilings only ok cover(will check 4-s box above bathrooms for extension and showroom outlets once tile is installed)
|
Rough-In Permanent Service | 5/10/2016 | 5/11/2016 | 5/11/2016 | A | PASS |
Rock A. Hudson
|
|
|
this is for new walls only and sub panel. sub feed from existing switchgear and 200A breaker. Please call when coming to inspect so I can be there to open doors. Please give me 20 min Phone #: ###-#### Inspection requested via web by Daniel Gamboa Walls only ok to cover p/s u/g n ok
|