Final | 9/2/2016 | 9/2/2016 | 9/2/2016 | A | PASS |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by mike brown final ok
|
Electrical Rough-In | 8/25/2016 | 8/25/2016 | 8/25/2016 | P | PASS |
James Ady
|
|
|
Pole bases Phone #: ###-#### Inspection requested via web by mike brown Pole bases ok
|
Conference | 8/16/2016 | 8/17/2016 | 8/17/2016 | A | DONE |
James Ady
|
|
|
Check panel on 2nd floor for clearances from furnace Phone #: ###-#### Inspection requested via web by mike brown Spoke with mike about second floor panel clearance. Clearance is ok
|
Permanent Service | 8/16/2016 | 8/16/2016 | 8/16/2016 | P | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by mike brown p/s u/g n ok
|
Electrical Rough-In | 8/9/2016 | 8/9/2016 | 8/9/2016 | A | PASS |
Eric Story
|
|
|
Trench Phone #: ###-#### Inspection requested via web by mike brown underground on west end of parking lot ok cover east end will be done when trenched.
|
Electrical Rough-In | 7/21/2016 | 7/21/2016 | 7/21/2016 | P | PASS |
James Ady
|
|
|
1st floor walls only Phone #: ###-#### Inspection requested via web by mike brown 1st floor walls only ok to cover
|
Electrical Rough-In | 7/14/2016 | 7/14/2016 | 7/14/2016 | P | PASS |
James Ady
|
|
|
2nd floor complete rough in Phone #: ###-#### Inspection requested via web by mike brown 2nd floor rough in ok to cover
|
Electrical Rough-In | 7/8/2016 | 7/8/2016 | 7/8/2016 | P | PASS |
James Ady
|
|
|
3rd floor complete rough-in Phone #: ###-#### Inspection requested via web by mike brown Rough in ok
|
Electrical Rough-In | 7/1/2016 | 7/1/2016 | 7/1/2016 | P | PASS |
James Ady
|
|
|
4th floor drop ceiling and walls. all remaining R/I for 4th floor Phone #: ###-#### Inspection requested via web by mike brown Remainder of 4th floor walls and ceilings Rough in ok to cover
|
Electrical Rough-In | 6/28/2016 | 6/29/2016 | 6/29/2016 | A | PASS |
Eric Story
|
|
|
Ceiling only first floor Phone #: ###-#### Inspection requested via web by mike brown 1st floor hard lids only ok cover
|
Electrical Rough-In | 6/16/2016 | 6/17/2016 | 6/17/2016 | A | PASS |
Eric Story
|
|
|
Fourth floor ceilings only Phone #: ###-#### Inspection requested via web by mike brown 4th floor cielings ok cover
|
Electrical Rough-In | 6/13/2016 | 6/14/2016 | 6/14/2016 | A | PASS |
Eric Story
|
|
|
3rd floor ceiling Phone #: ###-#### Inspection requested via web by mike brown 3rd floor hard lids for drop cielings only ok cover
|
Electrical Rough-In | 6/7/2016 | 6/8/2016 | 6/8/2016 | A | PASS |
Daryl DeGrange
|
|
|
Ceilings only for pre rock and insulation Phone #: ###-#### Inspection requested via web by mike brown rough-in ok cover hard lid second floor only
|
Conference | 5/16/2016 | 5/18/2016 | 5/18/2016 | A | DONE |
James Ady
|
|
|
let Eric Story know so he can join in as well please Phone #: ###-#### Inspection requested via web by mike brown Talked about 2nd floor Apartment and common areas as well as service an sub panel feeders
|