Information based on query as of Thursday, June 20, 2024.
Permit Information
Permit NumberELE16-01652
StatusFinaled
Name ANDERSON & WOOD CONSTRUCTION
Site Address 826 W MAIN ST
Project Name 
Customer Number16-7388
ePlanReviewNo
Description
Addition: Provide site electrical and lighting to the Grove Plaza, electrical to new restroom, and electrical to new fountain.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final6/4/20176/5/20176/5/2017PPASS
DetailsRock A. Hudson
Rock Call when you are on your way.
Thanks
John Phone #: ###-#### Inspection requested via web by John Rourke
Final ok
Electrical Rough-In5/3/20175/4/20175/4/2017APASS
DetailsRock A. Hudson
Underground PVC in south west end of south spoke.Is ready early am i should be on site by 8.
Thanks
John Phone #: ###-#### Inspection requested via web by John Rourke
All underground complete. Rough in ok cover
Electrical Rough-In4/20/20174/21/20174/21/2017APASS
DetailsRock A. Hudson
underground north end west side south spur. I will be skipping the 7am safety meeting so i will be on site early if this works into your sch.
Thanks
John Phone #: ###-#### Inspection requested via web by John Rourke
Area noted rough in ok cover
Electrical Rough-In4/17/20174/18/20174/18/2017APASS
DetailsRock A. Hudson
East side of south spur early am would be great if possible. Call when you are on your way
Thanks
John Phone #: ###-#### Inspection requested via web by John Rourke
Area noted rough in ok cover
Final4/18/20174/18/20174/18/2017PPART
DetailsRock A. Hudson
East side of south spur early am would be great if possible. Call when you are on your way
Thanks
John Phone #: ###-#### Inspection requested via web by John Rourke
Information office TCO ok
Electrical Rough-In4/5/20174/6/20174/6/2017APASS
DetailsRock A. Hudson
Underground at north end of south wing.Please call when you are walking over early am would be great if that works for you. Phone #: ###-#### Inspection requested via web by John Rourke
Area noted rough in ok cover
Electrical Rough-In11/17/201611/17/201611/17/2016PPASS
DetailsEric Story
Heat Tape on water line in Parking garage Phone #: ###-#### Inspection requested via web by John Rourke
Heat tape in garage ok to cover
Conference11/8/201611/9/201611/9/2016PDONE
DetailsRock A. Hudson
Rock they are trying to get an ok to occupy the restrooms. Not sure what we need to do to make this happen Phone #: ###-#### Inspection requested via web by John Rourke
Discussed area to have temp occupancy. Only area of building not ready is information office.
Final11/9/201611/9/201611/9/2016PPART
DetailsRock A. Hudson
Rock they are trying to get an ok to occupy the restrooms. Not sure what we need to do to make this happen Phone #: ###-#### Inspection requested via web by John Rourke
Information office not included. Rest of building and center area of grove ok to occupy. GFCI protection in place and 1 pole light to mount after christmas tree is set.
Permanent Service10/14/201610/14/201610/14/2016PPASS
DetailsRock A. Hudson
will be ready early pm Phone #: ###-#### Inspection requested via web by John Rourke Fuse main disconnect, available fault current will post Monday. p/s u/g n ok
Electrical Rough-In10/5/201610/5/201610/5/2016PPASS
DetailsJames Ady
restroom ceilings need ok to cover hardlid Phone #: ###-#### Inspection requested via web by John Rourke Restroom ceilings only ok to cover
Electrical Rough-In9/27/20169/28/20169/28/2016PPASS
DetailsRock A. Hudson
Fountain rebar bonding and lighting piping. will be ready early pm Thanks John Phone #: ###-#### Inspection requested via web by John Rourke
Areas noted rough in ok cover
Electrical Rough-In9/23/20169/23/20169/23/2016PPASS
DetailsRock A. Hudson
Bonding of fountain cans. Contact John @ ###-#### about 30mins prior to inspection. Phone #: ###-#### Inspection requested via web by Kristopher Wilson
Bonding as noted rough in ok cover
Electrical Rough-In9/13/20169/14/20169/14/2016APASS
DetailsEric Story
underground north center core area. Early am if possible Thanks John Phone #: ###-#### Inspection requested via web by John Rourke
North center core only underground ok cover
Electrical Rough-In9/8/20169/9/20169/9/2016PPASS
DetailsRock A. Hudson
Rough In inspection for Restroom building. Phone #: ###-#### Inspection requested via web by Kristopher Wilson
Walls for area noted rough in ok cover
Electrical Rough-In9/8/20169/9/20169/9/2016APASS
DetailsRock A. Hudson
Underground north east section of center core for lighting and outlets.early am if possible Thanks. Phone #: ###-#### Inspection requested via web by John Rourke Area noted rough in ok cover
Electrical Rough-In9/1/20169/2/20169/2/2016APASS
DetailsDaryl DeGrange
Grounding of re bar around fountain in trench drain concrete also bonding of trench drain cover. Please call 8604010 when headed over thanks.John Phone #: ###-#### Inspection requested via web by John Rourke Rough-ok cover common bonding grid around fountain. Discussed bonding perimeter surface
Electrical Rough-In8/29/20168/30/20168/30/2016APASS
DetailsRock A. Hudson
Underground West Center Court. AM inspection. Contact John @ ###-#### Phone #: ###-#### Inspection requested via web by Kristopher Wilson
Area noted around vault rough in ok cover
Electrical Rough-In8/21/20168/22/20168/22/2016PPASS
DetailsRock A. Hudson
Underground north area of center core Phone #: ###-#### Inspection requested via web by John Rourke
Discussed bonding around fountain area. Shall bond shell, 4 stubs for equipotential plane, metal spray housings. GFCI protection of LED lights depend on transformer type. North underground 20' to south rough in ok cover
Electrical Rough-In8/18/20168/19/20168/19/2016APASS
DetailsRock A. Hudson
Underground Center Court - North
John @ ###-#### Phone #: ###-#### Inspection requested via web by Kristopher Wilson North section of circle underground and pole base rough in ok cover
Electrical Rough-In8/4/20168/5/20168/5/2016APASS
DetailsRock A. Hudson
Underground East Side of North Spur. AM early please. Phone #: ###-#### Inspection requested via web by Kristopher Wilson
Area as noted underground rough in ok cover
Electrical Rough-In7/27/20167/28/20167/28/2016APASS
DetailsRock A. Hudson
U.G. inspection of the Northwest Spoke. Contact John @ ###-#### ~30 mins prior to inspection. Phone #: ###-#### Inspection requested via web by Kristopher Wilson
North spur west half underground rough in ok cover
Electrical Rough-In7/8/20167/11/20167/11/2016APASS
DetailsRock A. Hudson
Underground inspection. Contact John @ ###-#### 30mins prior to inspection Phone #: ###-#### Inspection requested via web by Kristopher Wilson
West underground rough in ok cover
Electrical Rough-In6/29/20166/30/20166/30/2016APASS
DetailsEric Story
Underground - South East Core
John @ ###-#### Phone #: ###-#### Inspection requested via web by Kristopher Wilson
southeast corner underground ok cover
Electrical Rough-In6/23/20166/24/20166/24/2016PPASS
DetailsRock A. Hudson
Underground inspection. Contact John @ ###-#### 30mins prior to inspection. Phone #: ###-#### Inspection requested via web by Kristopher Wilson
S.W. corner underground rough in ok cover. Discussed the outdoor receptacle outlets GFCI protection. Print shows 30ma equipment protective device, GFCI protection for personel shall be installed as per 210.8(B)(4)