Final | 9/28/2016 | 10/3/2016 | 10/3/2016 | A | PASS |
Mark Moncarr
|
|
|
Please Call Caroline ###-#### prior to your arrival. Phone #: ###-#### Inspection requested via web by Clay Morgan final ok
|
Electrical Rough-In | 8/29/2016 | 8/30/2016 | 8/30/2016 | A | PASS |
James Ady
|
|
|
There should be someone there. If you have any questions, please call Clay at ###-####. This is for the floor heat. Thank You. Phone #: ###-#### Inspection requested via web by Clay Morgan Floor heat ok to cover
|
Final | 7/27/2016 | 7/28/2016 | 7/28/2016 | A | FAIL |
James Ady
|
|
|
If you have any questions please call Jared ###-####. Thank you!! Phone #: ###-#### Inspection requested via web by Clay Morgan Cannot final until master bath floor heat has been installed
|
Electrical Rough-In | 5/30/2016 | 5/31/2016 | 5/31/2016 | A | PASS |
Rock A. Hudson
|
|
|
If you have questions, please call Jared at ###-####. Thank you!! Phone #: ###-#### Inspection requested via web by Clay Morgan Kitchen and master bath rough in ok cover
|