Electrical Rough-In | 8/6/2020 | 8/7/2020 | 8/7/2020 | A | PASS |
Tom Saunders
|
|
|
Screened- Mika Phone #: ###-####...rough in ok to cover
|
ELE-Aging Inspection | 6/16/2020 | 6/16/2020 | 6/16/2020 | | PEND |
Daryl DeGrange
|
|
|
The permit is still open with the City of Boise. Please call 208 ###-#### with progress report or any questions. If your job is complete, please schedule an final inspection online. Thank you!
|
Conference | 3/17/2020 | 3/20/2020 | 3/20/2020 | A | PASS |
Tom Saunders
|
|
|
Conference with homeowner as close to 8:00 AM as possible ###-#### Micah...discussed progress of job, sub panel makeup-seperating grounds and neutrals, recep layout, and stapling requirements
|
Conference | 3/16/2020 | 3/17/2020 | 3/17/2020 | A | CANC |
Tom Saunders
|
|
|
Conference with homeowner as close to 8:00 AM as possible ###-####...rescheduled to 3/20/20 8AM...due to meeting...called homeowner and he was ok with
|
ELE-Aging Inspection | 3/16/2020 | 3/16/2020 | 3/16/2020 | | DONE |
Daryl DeGrange
|
|
|
Still under construction, homeowner would like an conference AM 3/17/20
|
ELE-Aging Inspection | 12/16/2019 | 12/16/2019 | 12/16/2019 | | PASS |
Tom Saunders
|
|
|
still under construction
|
ELE-Aging Inspection | 9/16/2019 | 9/16/2019 | 9/16/2019 | | PASS |
Tom Saunders
|
|
|
still under construction
|
ELE-Aging Inspection | 6/17/2019 | 6/17/2019 | 6/19/2019 | | PASS |
Tom Saunders
|
|
|
visual inspection...open boxes on exterior of house...still under construction
|
ELE-Aging Inspection | 3/8/2019 | 3/8/2019 | 3/11/2019 | | PASS |
Tom Saunders
|
|
|
still under construction
|
Rough-In Permanent Service | 4/17/2017 | 4/19/2017 | 4/19/2017 | A | PASS |
Tom Saunders
|
|
|
Micah Phone #: ###-####...
ok to cover p/s u/g rec ok overhead feed to underground
|
Conference | 2/17/2017 | 2/17/2017 | 2/17/2017 | P | PASS |
Tom Saunders
|
|
|
Micah Phone #: ###-####....
discussed new service to feed new panel for existing house circuits and panel for new addition....using existing recessed meter main and converting into junction box....new meter with main breaker on outside to feed new panels..explained could not have unfused conductors in wall...explored various options
|
Conference | 6/17/2016 | 6/17/2016 | 6/17/2016 | P | DONE |
Eric Story
|
|
|
Micah Phone #: ###-#### Discussed service change requirments. changing overhead to u/g. will call for another conference once has full scope of work figured out.
|