Final | 10/25/2016 | 10/26/2016 | 10/26/2016 | A | PASS |
Tom Saunders
|
|
|
CONTACT IS STEVE NUXOLL AT ###-#### Phone #: ###-#### Inspection requested via web by JENNY EMEL...ok to final
|
Electrical Rough-In | 10/26/2016 | 10/26/2016 | 10/26/2016 | A | PASS |
Tom Saunders
|
|
|
CONTACT IS STEVE NUXOLL AT ###-#### Phone #: ###-#### Inspection requested via web by JENNY EMEL....all work done on surface of room....ok
|
Electrical Rough-In | 6/29/2016 | 6/29/2016 | 6/29/2016 | P | PASS |
Eric Story
|
|
|
UNDERGROUND INSPECTION Phone #: ###-#### Inspection requested via web by JENNY EMEL underground for pump house ok cover
|
Electrical Rough-In | 6/21/2016 | 6/21/2016 | 6/21/2016 | P | PASS |
Eric Story
|
|
|
Uffer grd inspection at well house Phone #: ###-#### Inspection requested via web by JENNY EMEL ufer ground for pump house ok to pour(also talked with contractor about who governs the inspections public works or city)
|