Final | 8/19/2016 | 8/19/2016 | 8/19/2016 | P | PASS |
Bob Reichert
|
|
|
Brandon G. is contact ###-#### Phone #: ###-#### Inspection requested via web by Debby Pierce ok final
|
Final | 8/18/2016 | 8/25/2016 | 8/19/2016 | P | CANC |
Eric Story
|
|
|
Brandon G. is contact at ###-####. Phone #: ###-#### >> Inspection requested via web by Debby Pierce Inspection cancelled from web by: Debby Pierce
|
Final | 8/17/2016 | 8/18/2016 | 8/18/2016 | A | NR |
Eric Story
|
|
|
Brandon is contact at ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce Not ready, poles are not grounded
|
Electrical Rough-In | 8/4/2016 | 8/5/2016 | 8/5/2016 | A | CANC |
Eric Story
|
|
|
existing service feeding out buildings. contact on this job site is Brandon G. at ###-####. thank you. Phone #: ###-#### Inspection requested via web by Debby Pierce needed p/s
|
Permanent Service | 8/5/2016 | 8/5/2016 | 8/5/2016 | P | PASS |
Eric Story
|
|
|
existing service feeding out buildings. contact on this job site is Brandon G. at ###-####. thank you. Phone #: ###-#### Inspection requested via web by Debby Pierce p/s u/g n ok
|
Electrical Rough-In | 7/18/2016 | 7/18/2016 | 7/18/2016 | P | PASS |
Eric Story
|
|
|
LAST 3 light poles north side of bld. Brandon is contact at ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce north 3 pole bases ok to pour
|
Electrical Rough-In | 7/14/2016 | 7/15/2016 | 7/15/2016 | A | PASS |
Rock A. Hudson
|
|
|
Brandon is contact at ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce 11 of 14 west, south and east pole bases. Underground installed prior to inspection. All U/G under sidewalk and planter areas. rough in ok cover
|