Final | 3/28/2017 | 3/28/2017 | 3/28/2017 | P | PASS |
Mark Moncarr
|
|
|
Christina Phone #: ###-#### Talked to Doug of PHE, electrical is finaled. They were waiting for a fire inspection by Jim Paige which was done and passed.
|
Final | 12/1/2016 | 12/2/2016 | 12/2/2016 | P | PART |
Mark Moncarr
|
|
|
Final 3rd and 4th floor building P Phone #: ###-#### Inspection requested via web by Bob Stephens Partial final on building P. Temporary use for personnel
|
Final | 11/30/2016 | 12/1/2016 | 12/1/2016 | P | PART |
Mark Moncarr
|
|
|
Final on 1st ; 2nd floors Building P Phone #: ###-#### Inspection requested via web by Bob Stephens partial final ok floors 1&2
|
Rough-In Permanent Service | 7/25/2016 | 7/26/2016 | 7/26/2016 | A | PASS |
James Ady
|
|
|
Building P 1st floor reinspect Phone #: ###-#### Inspection requested via web by Bob Stephens Rough in 1st floor ok. p/s u/g n ok
|
Electrical Rough-In | 7/21/2016 | 7/22/2016 | 7/22/2016 | P | CANC |
James Ady
|
|
|
Building P 1st floor rough electrical and permanent power Phone #: ###-#### Inspection requested via web by Bob Stephens not ready
|
Electrical Rough-In | 7/20/2016 | 7/21/2016 | 7/21/2016 | A | PART |
James Ady
|
|
|
Rough inspection on 2nd floor Phone #: ###-#### Inspection requested via web by Bob Stephens rough in 2nd floor ok
|
Electrical Rough-In | 7/19/2016 | 7/20/2016 | 7/20/2016 | A | PASS |
James Ady
|
|
|
Rough 3rd floor of building P Phone #: ###-#### Inspection requested via web by Bob Stephens 3rd floor rough in ok
|
Electrical Rough-In | 7/18/2016 | 7/19/2016 | 7/19/2016 | A | PART |
James Ady
|
|
|
4th floor building P Phone #: ###-#### Inspection requested via web by Bob Stephens 4th floor all 8 appts. OK to covetr
|