Final | 9/22/2016 | 9/23/2016 | 9/23/2016 | A | PASS |
Eric Story
|
|
|
Rob Phone #: ###-#### Final for Life Flight center ok
|
Electrical Rough-In | 9/15/2016 | 9/15/2016 | 9/15/2016 | P | PASS |
Rock A. Hudson
|
|
|
ceiling; Rob Phone #: ###-#### Signed card by mistake, behind visqueen found temp power installed for temp desk locations. when furniture in place contractor to call for final at that time. Ceiling grid rough in ok cover
|
Electrical Rough-In | 9/1/2016 | 9/1/2016 | 9/1/2016 | P | PASS |
James Ady
|
|
|
Rob Phone #: ###-#### 4th floor rm 4425 ceiling only
|
Electrical Rough-In | 8/30/2016 | 8/30/2016 | 8/30/2016 | P | PASS |
Eric Story
|
|
|
Please call Rob when onsite. Phone #: ###-#### Inspection requested via web by Kevin Perez ceilings only ok cover
|
Electrical Rough-In | 8/3/2016 | 8/3/2016 | 8/3/2016 | P | PASS |
Eric Story
|
|
|
Please Call Rob Patterson When onsite. Thank you and have a great day!! Phone #: ###-#### Inspection requested via web by Kevin Perez 4th floor life flight center entry switch and exit lite only ok cover
|