Final | 11/3/2017 | 11/3/2017 | 11/3/2017 | P | PASS |
Eric Story
|
|
|
Final for LEED comission Final ok
|
Permanent Service | 5/11/2017 | 5/11/2017 | 5/11/2017 | P | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton p/s u/g n ok
|
Final | 5/2/2017 | 5/3/2017 | 5/3/2017 | A | PART |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Temp occ is fine and for final we are waiting for leed test report to close out permit
|
Final | 5/2/2017 | 5/2/2017 | 5/2/2017 | P | PART |
Eric Story
|
|
|
Temp occ ok
|
Final | 4/19/2017 | 4/20/2017 | 4/20/2017 | A | CANC |
Eric Story
|
|
|
Partial final Phone #: ###-#### Inspection requested via web by Per Eric take out notes and change to Cancel until energy inspection has been received.
|
Final | 4/18/2017 | 4/19/2017 | 4/19/2017 | A | CANC |
Eric Story
|
|
|
Partial Final Phone #: ###-#### Inspection requested via web by Kerri Hamilton Items discussed will be corrected for temp and need access to rooftop
|
Electrical Rough-In | 4/12/2017 | 4/13/2017 | 4/13/2017 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton All remaining ceilings ok cover
|
Electrical Rough-In | 4/6/2017 | 4/6/2017 | 4/6/2017 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton...
2nd floor ceiling ok to cover
|
Electrical Rough-In | 3/27/2017 | 3/27/2017 | 3/27/2017 | P | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton 1st floor ceilings minus 3 areas where gutters still needed finish ok cover
|
Permanent Service | 3/10/2017 | 3/10/2017 | 3/10/2017 | P | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton p/s u/g n ok
|
Permanent Service | 3/9/2017 | 3/10/2017 | 3/10/2017 | A | FAIL |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton 110.24 Avaliable fault calculation required
|
Electrical Rough-In | 3/7/2017 | 3/7/2017 | 3/7/2017 | A | PASS |
Tom Saunders
|
|
|
UG Phone #: ###-#### Inspection requested via web by Kerri Hamilton...
u/g ok to cover
|
Electrical Rough-In | 2/27/2017 | 2/28/2017 | 2/28/2017 | P | PASS |
Eric Story
|
|
|
underground Phone #: ###-#### Inspection requested via web by Kerri Hamilton u/g south of buiding ok cover
|
Electrical Rough-In | 2/23/2017 | 2/23/2017 | 2/23/2017 | P | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton South stair ceiling only ok cover
|
Electrical Rough-In | 2/14/2017 | 2/15/2017 | 2/15/2017 | A | PASS |
Eric Story
|
|
|
Stairwell hardily and upstairs wall. Early am if possible please Phone #: ###-#### Inspection requested via web by Graham Estep North stair hard lid and 2nd floor panel wall ok cover
|
Electrical Rough-In | 2/14/2017 | 2/14/2017 | 2/14/2017 | P | CANC |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton No one onsite to guide to area that needed inspection, General wasnt there as well. Will need better discription as to what is needed to be looked at and will need to reschedule.
|
Electrical Rough-In | 1/30/2017 | 1/31/2017 | 1/31/2017 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Graham Estep 2nd floor walls only ok cover
|
Electrical Rough-In | 1/23/2017 | 1/24/2017 | 1/24/2017 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Remaining walls on 1st floor and stairway lights going to second floor ok cover
|
Electrical Rough-In | 1/19/2017 | 1/20/2017 | 1/20/2017 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Bathroom hard lids and walls also and stairways and soffit ok cover
|
Electrical Rough-In | 1/17/2017 | 1/18/2017 | 1/18/2017 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Walls on west side and bath walls only ok cover,hard lids to be looked at on another day
|
Electrical Rough-In | 9/20/2016 | 9/21/2016 | 9/21/2016 | P | PASS |
Eric Story
|
|
|
Early pm if possible please. Phone #: ###-#### Inspection requested via web by Kerri Hamilton primary feeds underground only ok cover
|
Temporary Service | 9/15/2016 | 9/15/2016 | 9/15/2016 | P | CANC |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton
need new permit
|
Temporary Service | 9/14/2016 | 9/15/2016 | 9/15/2016 | A | FAIL |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton
590.6 ALL 120V-240V OUTLETS SHALL BE GFI PROTECTED
|
Electrical Rough-In | 9/9/2016 | 9/12/2016 | 9/12/2016 | A | PASS |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton cover ok
|
Electrical Rough-In | 8/31/2016 | 9/1/2016 | 9/1/2016 | P | PASS |
Eric Story
|
|
|
UG Early pm if possible please Phone #: ###-#### Inspection requested via web by Kerri Hamilton s.w of building underground ok cover
|
Electrical Rough-In | 8/30/2016 | 8/31/2016 | 8/31/2016 | P | PASS |
Eric Story
|
|
|
UG Phone #: ###-#### Inspection requested via web by Kerri Hamilton area north of main column underground ok cover
|
Electrical Rough-In | 8/22/2016 | 8/22/2016 | 8/22/2016 | P | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton underground on E side of building ok to cover.
|